Basis of Presentation (Policies) | 9 Months Ended | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Sep. 30, 2011 | |||||||||||||||||
Organization, Consolidation and Presentation of Financial Statements [Abstract] | |||||||||||||||||
Profit Recognition Completed Contract Method [Policy Text Block] | Our profit recognition related to construction contracts is based on estimates of costs to complete each project. These estimates can vary in the normal course of business as projects progress and uncertainties are resolved. We do not recognize revenue on contract change orders or claims until we have a signed agreement; however, we do recognize costs as incurred and revisions to estimated total costs as soon as the obligation to perform is determined. Approved change orders and claims, as well as changes in related estimates of costs to complete, are considered revisions in estimates. We use the cumulative catch-up method applicable to construction contract accounting to account for revisions in estimates. Under this option, revisions in estimates are accounted for in their entirety in the period of change. As of September 30, 2011, we had no revisions in estimates that are reasonably certain to impact future periods. | ||||||||||||||||
Impairment or Disposal of Long-Lived Assets, Policy | To determine if impairment charges should be recognized, the carrying amount of each consolidated real estate development project is reviewed on a quarterly basis in accordance with ASC Topic 360, Property, Plant, and Equipment, and each real estate development project accounted for under the equity method of accounting is reviewed in accordance with ASC Topic 323, Investments - Equity Method and Joint Ventures. The review of each project includes an evaluation of entitlement status, market conditions, existing offers to purchase, cost of construction, debt load, development schedule, status of joint venture partners and other factors specific to each project to determine if events or changes in circumstances indicate that a project’s carrying amount may not be recoverable. If events or changes in circumstances indicate that a project’s carrying amount may not be recoverable, the undiscounted future cash flows are estimated and compared to the project’s carrying amount. In the event that the estimated undiscounted future cash flows are not sufficient to recover the carrying amount of a project, it is written down to its estimated fair value | ||||||||||||||||
Retention Receivable Policy | We evaluate our non-escrow retention receivables for collectability using certain customer information that includes the following:
| ||||||||||||||||
Consolidation, Variable Interest Entity, Policy | We have determined that certain of these joint ventures are variable interest entities (“VIEs”) as defined by Accounting Standards Codification (“ASC”) Topic 810, Consolidation, and related standards. To ascertain if we are required to consolidate the VIE, we continually evaluate whether we are the VIE’s primary beneficiary. The factors we consider in determining whether we are a VIE’s primary beneficiary include the decision authority of each partner, which partner manages the day-to-day operations of the project and the amount of our equity investment in relation to that of our partners. We have determined that certain of the real estate joint ventures are VIEs as defined by ASC Topic 810, Consolidation, and related standards. To ascertain if we are required to consolidate the VIE, we continually evaluate whether we are the VIE’s primary beneficiary. The factors we consider in determining whether we are a VIE’s primary beneficiary include the decision authority of each partner, which partner manages the day-to-day operations of the project and the amount of our equity investment in relation to that of our partners. Based on our ongoing primary beneficiary assessments, there were no changes to our determinations of whether we are the VIE’s primary beneficiary for existing real estate entities during the nine months ended September 30, 2011 and 2010. |