Commitments and Contingencies Disclosure [Abstract]  
Status of Company's Rigs under Construction
The following table presents the status of the Company’s rigs under construction as of September 30, 2013.  Amounts include capitalized interest and an estimate for project contingencies (in millions):

 
Scheduled delivery date
 
Total estimated project costs
 
Total costs incurred through September 30, 2013
 
Projected costs for the remainder of 2013
 
Projected costs in 2014
 
Projected costs in 2015
 
Total future costs
 
 
 
 
 
 
 
 
 
 
 
 
 
 
Rowan Renaissance
December 2013
 
$
728

 
$
260

 
$
457

 
$
11

 
$

 
$
468

Rowan Resolute
June 2014
 
736

 
270

 
29

 
437

 

 
466

Rowan Reliance
October 2014
 
730

 
199

 
19

 
508

 
4

 
531

Rowan Relentless
March 2015
 
751

 
183

 
12

 
108

 
448

 
568

 
 
 
$
2,945

 
$
912

 
$
517

 
$
1,064

 
$
452

 
$
2,033