Construction Contracts in Progress
12 Months Ended
Dec. 31, 2015
LongTermContractsOrProgramsDisclosureTextBlockAbstract  
Construction Contracts in Progress
CONSTRUCTION CONTRACTS IN PROGRESS
The status of contracts in progress as of December 31, 2015 and 2014 is as follows:
 
 
2015
 
2014
Costs incurred on uncompleted contracts
 
$
94,686

 
$
92,190

Estimated earnings
 
52,246

 
47,510

Earned revenue
 
146,932

 
139,700

Less billings to date
 
(141,478
)
 
(132,790
)
Total
 
$
5,454

 
$
6,910

Classified as follows:
 
 
 
 
Costs and estimated earnings in excess of billings on uncompleted contracts
 
$
7,312

 
$
9,904

Billings in excess of costs and estimated earnings on uncompleted contracts
 
(1,858
)
 
(2,994
)
Total
 
$
5,454

 
$
6,910


Costs and estimated earnings in excess of billings on uncompleted contracts are included in accounts receivable on the consolidated balance sheet, while billings in excess of costs and estimated earnings on uncompleted contracts are included in other accrued liabilities on the consolidated balance sheet.
As of December 31, 2015 we had two construction contracts in progress that were identified as loss contracts and a provision for losses of $3 was recorded in other accrued liabilities on the consolidated balance sheet. As of December 31, 2014, we had one construction contract in progress that was identified as a loss contract and a provision for losses of $4 was recorded in other accrued liabilities on the consolidated balance sheet.