XML 50 R16.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments
12 Months Ended
Mar. 31, 2012
Commitments  
Commitments

10           Commitments

 

Capital expenditures contracted at the balance sheet date but not yet provided for is as follows:

 

   March 31,
   2011  2012
   $ in thousands  $ in thousands
       
Construction in Xinxing, Guangdong, PRC   548    757 
           
    548    757 
           

 

As of March 31, 2012, the Company entered into contractor agreements to construct factory building, warehouse, dormitories and leasehold improvements on the land in Xinxing, the PRC for total consideration of $5,814,000. $5,057,000 had been paid and the remaining balance of $757,000  is to be paid in accordance with the progress of the construction. The first phase of construction is expected to be completed by December 2012.