Property And Equipment
9 Months Ended
Jun. 30, 2016
Property, Plant and Equipment [Abstract]  
Property and Equipment
PROPERTY AND EQUIPMENT

A summary of property and equipment by classification is as follows:
(In thousands)
June 30,
2016
 
September 30,
2015
Drilling vessels and equipment
$
3,951,885

 
$
4,003,483

Construction work in progress
843,778

 
720,852

Drill pipe
52,725

 
55,248

Office equipment and other
39,155

 
36,379

Total cost
4,887,543

 
4,815,962

Less: Accumulated depreciation
(689,474
)
 
(643,830
)
Property and equipment, net
$
4,198,069

 
$
4,172,132



Impairments

The Atwood Falcon completed the contract it was working under in early March 2016. Based on the lack of contracting opportunities and the further deterioration of commodity prices, we determined that it was not likely that additional work would be obtained in the foreseeable future. Based on our analysis, we concluded that the Atwood Falcon and its materials and supplies were impaired as of December 31, 2015, and we wrote them down to their approximate salvage value. We recorded a non-cash impairment charge of approximately $64.7 million ($64.7 million, net of tax, or $1.00 per diluted share), which is included in Asset Impairment on the Condensed Consolidated Statement of Operations for the three months ended December 31, 2015. This impairment charge includes a write-down of property and equipment of $53.0 million and a write-down of our inventory of materials and supplies specific to the Atwood Falcon of $11.7 million.

Following contract completion and mobilization of the vessel to international waters, on March 24, 2016, we executed a sale and recycling agreement with respect to the Atwood Falcon, pursuant to which the vessel, together with associated equipment and machinery would be sold to a third party to be demolished and recycled. On April 13, 2016, the Atwood Falcon sale and recycling transaction closed and title of the vessel and associated equipment and machinery transferred to a third party buyer.
The total non-cash impairment charges recorded for the Atwood Falcon of approximately $64.8 million is included in Asset Impairment on the Condensed Consolidated Statement of Operations for the nine months ended June 30, 2016.
The Atwood Hunter completed the contract it was working under in December 2014. Based on the lack of contracting opportunities and the further deterioration of commodity prices, in January 2015, we determined that it was not likely that additional work would be obtained in the foreseeable future. Based on our analysis, in the three months ended December 31, 2014, we determined that the Atwood Hunter and its materials and supplies were impaired, and we wrote them down to their salvage value. We recorded a non-cash impairment charge of approximately $60.8 million ($56.1 million, net of tax, or $0.86 per diluted share), which is included in Asset Impairment on the Condensed Consolidated Statement of Operations for the three months ended December 31, 2014. This impairment charge included write-downs of property and equipment of $48.0 million and write-downs of our inventory of materials and supplies that was specific to the Atwood Hunter of $8.4 million. In August 2015, we completed the sale of the Atwood Hunter.

Other Income—During the three months ended December 31, 2015, we recognized approximately $18.0 million ($18.0 million, net of tax, or $0.28 per diluted share) of additional expected insurance recoveries related to cyclone damage to the Atwood Osprey. This amount is included in Other Income on the Condensed Consolidated Statement of Operations for the nine months ended June 30, 2016. We collected receivables from the insurance company of approximately $6.7 million and $11.8 million during the three month periods ending March 31, 2016 and June 30, 2016, respectively.

Loss on sale of assets— Our loss on sale of assets for the nine months ended June 30, 2015 was primarily due to a loss of approximately $8.0 million ($7.1 million, net of tax, or $0.11 per diluted share) due to the sale of the Atwood Southern Cross and a loss of approximately $5.5 million ($5.5 million, net of tax, or $0.08 per diluted share), due to the sale of Atwood Hunter.

Construction Projects

On December 17, 2015, we entered into a supplemental agreement (collectively, "Supplemental Agreement No. 4") to the construction contracts with Daewoo Shipbuilding and Marine Engineering Co., Ltd ("DSME") which delay our requirements to take delivery of the Atwood Admiral to September 30, 2017 and the Atwood Archer to June 30, 2018. Supplemental Agreement No. 4 amends all material terms of the previous agreements. In consideration of the agreement, we made a payment of $50 million for each drillship on December 31, 2015. DSME has extended all remaining milestone payments, $93.9 million for the Atwood Admiral and $305.9 million for the Atwood Archer, until their respective delivery dates. We retain the option to take earlier delivery of each vessel, subject to a forty-five-day notice period to DSME.

In May 2016, we entered into an agreement with Hydril USA Distribution, LLC ("GE") to manufacture a complete second Blowout Preventer stack ("BOP") and an Auxiliary Stack Test System ("ASTS") for the Atwood Condor. The addition of the second BOP will increase the marketability and operational efficiency of the vessel. Total consideration for this agreement is approximately $19 million with 20% due upon placement of the purchase order and the remaining 80% due upon delivery. To accelerate the manufacturing and delivery process, which is targeted for February 2017, we provided certain capital spares we maintained to GE to be used in the manufacturing process. These capital spares will be replenished by GE with similar capital spares upon delivery of the BOP.