Drilling vessels and equipment
$
4,026,004

 
$
4,181,774

Construction work in progress
471,046

 
319,548

Drill pipe
42,576

 
31,265

Office equipment and other
36,035

 
35,566

Total cost
4,575,661

 
4,568,153

Less: Accumulated depreciation
(564,970
)
 
(601,125
)
Property and equipment, net
$
4,010,691

 
$
3,967,028

Schedule of Expected Delivery Dates and Status
The expected delivery dates of the Atwood Admiral and Atwood Archer are as follows:

 
Atwood Admiral
 
Atwood Archer
 
Expected Delivery
 
Status
 
Expected Delivery
 
Status
Prior to supplemental agreements
3/31/2015
 
 
 
12/31/2015
 
 
Supplemental Agreement No. 1:
9/30/2015
 
Exercised
 
6/30/2016
 
Exercised
Supplemental Agreement No. 2:
 
 
 
 
 
 
 
Option No. 1
3/31/2016
 
Exercised
 
12/31/2016
 
Unexercised
Option No. 2
9/30/2016
 
Unexercised
 
6/30/2017
 
Unexercised
Long-term Purchase Commitment
expected payments for the Atwood Admiral and Atwood Archer as impacted by Supplemental Agreement No. 1 and Supplemental Agreement No. 2 are as follows:

(In millions)
Date
 
Atwood Admiral
 
Atwood Archer
Milestone
6/30/2015
 
$
25

 
$
25

Milestone
9/30/2015
 
150

 
 
Final payment
3/31/2016
 
146

 
 
Final payment
6/30/2016
 
 
 
358

Total
 
 
$
321

 
$