15835 Park Ten Place Drive | (281) 749-7800 | |
Houston, Texas, 77084 | (Registrant's Telephone Number, | |
(Address of Principal Executive Offices) | Including Area Code) | |
N/A | ||
(Former Name or Former Address, if Changed Since Last Report) | ||
(d) | EXHIBITS |
99.1 | Fleet Status Report at January 2, 2014 |
EXHIBIT NO | DESCRIPTION |
99.1 | Fleet Status Report at January 2, 2014 |
ATWOOD OCEANICS, INC | ||
(Registrant) | ||
/s/ Mark L. Mey Mark L. Mey Senior Vice President | ||
DATE: | January 2, 2014 |
Rig Name | Rated Water Depth | Location | Customer | Estimated Contract End Date | Estimated Contract Day Rate | Additional Comments |
ULTRA-DEEPWATER | ||||||
ATWOOD ADVANTAGE | 12,000' | U.S. Gulf of Mexico | NOBLE ENERGY INC. | March 2017 (36 months) | $584,000 | The rig is currently mobilizing to the U.S. Gulf of Mexico at a day rate of approximately $409,000 with expected arrival in March 2014. Day Rate subject to change due to cost escalation provisions in the contract. |
ATWOOD ACHIEVER | 12,000' | Under construction in South Korea scheduled for delivery in June 2014. | --- | --- | --- | |
Multiple countries, to commence in Morocco | KOSMOS ENERGY LTD. | September 2017 (36 months) | $595,000 (day rate will be grossed up for all applicable taxes, approximately $660,000 in Morocco) | Upon delivery from the shipyard, the rig will commence mobilization at a day rate of approximately $417,000 with a scheduled arrival in September 2014. Day rate subject to change due to cost escalation and tax reimbursement provisions in the contract. | ||
ATWOOD ADMIRAL | 12,000' | Under construction in South Korea scheduled for delivery in March 2015. | --- | AVAILABLE | N/A | |
ATWOOD ARCHER | 12,000' | Under construction in South Korea scheduled for delivery in December 2015. | --- | AVAILABLE | N/A | |
ATWOOD CONDOR | 10,000' | U.S. Gulf Of Mexico | SHELL OFFSHORE INC. | November 2016 (Fixed term) | $555,000 | Day rate subject to change due to cost escalation provisions in the contract. The rig incurred approximately 25 zero rate days in December related to BOP repairs and maintenance but is now working at full operating rate. |
ATWOOD OSPREY | 8,200' | Australia | CHEVRON AUSTRALIA PTY. LTD. | May 2017 (Fixed term) | Approximately $490,000 through May 2014/ approximately $470,000 thereafter | Day rate subject to change due to cost escalation and currency exchange provisions in the contract. |
Rig Name | Rated Water Depth | Location | Customer | Estimated Contract End Date | Estimated Contract Day Rate | Additional Comments |
DEEPWATER SEMISUBMERSIBLES | ||||||
ATWOOD EAGLE | 5,000' | Australia | WOODSIDE ENERGY LTD. (“WOODSIDE”)/ APACHE ENERGY LTD. (“APACHE”) | June 2014 (Fixed term) | Approximately $436,000 WOODSIDE/ $385,000 APACHE | Anticipated order of remaining drilling program is: WOODSIDE (2 wells) and APACHE (remainder of term). Day rate subject to change due to cost escalation and currency exchange provisions in the contract. |
Australia | WOODSIDE | June 2016 (24 months) | Approximately $460,000 | Day rate subject to change due to cost escalation and currency exchange provisions in the contract. | ||
ATWOOD FALCON | 5,000' | Australia | APACHE | November 2014 (Fixed term) | Approximately $385,000 | Day rate subject to change due to cost escalation and currency exchange provisions in the contract. |
Australia | MURPHY AUSTRALIA WA-481-P OIL PTY LTD | January 2015 (2 wells) | $499,500 | Day rate subject to change due to cost escalation provisions in the contract. The contract provides an option for one well with a minimum duration of 20 days. | ||
ATWOOD HUNTER | 5,000' | Cameroon | --- | March 2014 | --- | The rig is currently undergoing planned maintenance and regulatory inspections. |
Equatorial Guinea | GUINEA ECUATORIAL DE PETROLEOS | July 2014 (3 wells) | $515,500 | The contract provides for an option for one well at the contracted rate with an estimated duration of 30 days. |
Rig Name | Rated Water Depth | Location | Customer | Estimated Contract End Date | Estimated Contract Day Rate | Additional Comments |
JACKUPS | ||||||
ATWOOD MAKO | 400' | Thailand | SALAMANDER ENERGY (BUALUANG) LIMITED | September 2014 (Fixed term) | $155,000 | |
ATWOOD MANTA | 400' | Malaysia/Thailand | CEC INTERNATIONAL, LTD. (“CEC”) | December 2015 (Fixed term) | $174,500 Malaysia/$159,500 Thailand | Day rate subject to change due to cost escalation provisions in the contract. |
ATWOOD ORCA | 400' | Thailand | MUBADALA PETROLEUM | May 2015 (Fixed Term) | $159,500 | Day rate subject to change due to cost escalation provisions in the contract. |
ATWOOD BEACON | 400' | Italy | ENI S.p.A. | January 2016 (24 months) | 135,100 EUR (approximately $185,000 USD) | Day rate subject to change due to cost escalation provisions in the contract. The contract provides a one year option at market rates. |
ATWOOD AURORA | 350' | Cameroon | GLENCORE EXPLORATION CAMEROON LTD | May 2014 (3 wells remaining) | $155,000 | Day rate subject to change due to cost escalation and currency exchange provisions in the contract. The rig could incur approximately 5 zero rate days for regulatory inspections in the second quarter of fiscal year 2014. |
Cameroon | ADDAX PETROLEUM CAMEROON LIMITED | May 2015 (12 months) | $164,000/$193,000 (inclusive of Cameroon withholding tax depending on well location) | |||
VICKSBURG | 300' | Thailand | CEC | Early January 2014 (Fixed Term) | $115,000 | During October, we entered into an agreement to sell the rig. The sale is expected to close when the current drilling program is completed. |
Rig Name | Rated Water Depth | Location | Customer | Estimated Contract End Date | Estimated Contract Day Rate | Additional Comments |
OTHER | ||||||
ATWOOD SOUTHERN CROSS | 2,000' | Malta | --- | COLD STACKED | N/A | |
SEAHAWK | 1,800' | Ghana | --- | COLD STACKED | N/A |