XML 183 R101.htm IDEA: XBRL DOCUMENT v3.6.0.2
COMMITMENTS AND GUARANTEES (Mining Contracts) (Details)
T in Millions, $ in Millions
12 Months Ended
Dec. 31, 2016
USD ($)
extension
T
$ / lb
Dec. 31, 2015
USD ($)
Dec. 31, 2014
USD ($)
Surety Bond      
Contractual Obligations Mining Contracts [Line Items]      
Assurance Bond, Smelter Development $ 371    
PT-FI      
Contractual Obligations Mining Contracts [Line Items]      
Number of Extention Periods Available Under Mining Contract | extension 2    
Period For Option To Extend Mining Contract 10 years    
Gold And Silver Sales Royalty Rate 1.00%    
Quantity of ore produced subject to additional royalties | T 0.2    
Progressive Export Duty on Copper Concentrates, Lower Threshold, Percent 5.00%    
Progressive Export Duty on Copper Concentrates, Higher Threshold, Percent 7.50%    
Smelter Development Progress, Lower Threshold, Percent 7.50%    
Smelter Development Progress, Higher Threshold, Percent 30.00%    
Royalty Expense $ 131 $ 114 $ 115
Export Duties Expense $ 95 $ 109 $ 77
Incremental Percent of Undivided Interest Owned by Third Party 20.64%    
PT-FI | Copper      
Contractual Obligations Mining Contracts [Line Items]      
Royalty Interest in Future Production 4.00%   3.50%
PT-FI | Gold      
Contractual Obligations Mining Contracts [Line Items]      
Royalty Interest in Future Production 3.75%   1.00%
PT-FI | Construction Contracts | Surety Bond      
Contractual Obligations Mining Contracts [Line Items]      
Assurance Bond, Smelter Development $ 115    
PT-FI | Minimum      
Contractual Obligations Mining Contracts [Line Items]      
Copper Royalty Rate Payable 1.50%    
Price Of Copper Per Pound | $ / lb 0.90    
PT-FI | Maximum      
Contractual Obligations Mining Contracts [Line Items]      
Copper Royalty Rate Payable 3.50%    
Price Of Copper Per Pound | $ / lb 1.10