XML 30 R19.htm IDEA: XBRL DOCUMENT v3.22.2.2
Commitments and Contingencies
9 Months Ended
Sep. 30, 2022
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies

Note 12. Commitments and Contingencies

Indemnities

Edison International and SCE have various financial and performance guarantees and indemnity agreements which are issued in the normal course of business.

Edison International and SCE have agreed to provide indemnifications through contracts entered into in the normal course of business. These are primarily indemnifications against adverse litigation outcomes in connection with underwriting agreements, indemnities for specified environmental liabilities and income taxes with respect to assets sold or other contractual arrangements. Edison International's and SCE's obligations under these agreements may or may not be limited in terms of time and/or amount, and in some instances Edison International and SCE may have recourse against third parties. Edison International and SCE have not recorded a liability related to these indemnities. The overall maximum amount of the obligations under these indemnifications cannot be reasonably estimated.

Contingencies

In addition to the matters disclosed in these Notes, Edison International and SCE are involved in other legal, tax, and regulatory proceedings before various courts and governmental agencies regarding matters arising in the ordinary course of business. Edison International and SCE believe the outcome of each of these other proceedings will not materially affect its financial position, results of operations and cash flows.

Southern California Wildfires and Mudslides

California has experienced unprecedented weather conditions in recent years due to climate change and wildfires in SCE's territory, including those where SCE's equipment may be alleged to be associated with the fire's ignition, have caused loss of life and substantial damage in recent years. SCE's service territory remains susceptible to additional wildfire activity.

Numerous claims related to wildfire events have been initiated against SCE and Edison International. Edison International and SCE have incurred material losses in connection with the 2017/2018 Wildfire/Mudslide Events (defined below), which are described below. In addition, SCE's equipment has been, and may further be, alleged to be associated with wildfires that have originated in Southern California subsequent to 2018.

Liability Overview

The extent of liability for wildfire-related damages in actions against utilities depends on a number of factors, including whether the utility substantially caused or contributed to the damages and whether parties seeking recovery of damages will be required to show negligence in addition to causation. California courts have previously found utilities to be strictly liable for property damage along with associated interest and attorneys' fees, regardless of fault, by applying the theory of inverse condemnation when a utility's facilities were determined to be a substantial cause of a wildfire that caused the property damage. If inverse condemnation is held to be inapplicable to SCE in connection with a wildfire, SCE still could be held liable for property damages and associated interest if the property damages were found to have been proximately caused by SCE's negligence. If SCE were to be found negligent, SCE could also be held liable for, among other things, fire suppression costs, business interruption losses, evacuation costs, clean-up costs, medical expenses, and personal injury/wrongful death claims. Additionally, SCE could potentially be subject to fines and penalties for alleged violations of CPUC rules and state laws investigated in connection with the ignition of a wildfire.

Final determinations of liability for wildfire events, including determinations of whether SCE was negligent, would only be made during lengthy and complex litigation processes. Even when investigations are still pending or liability is disputed, an assessment of likely outcomes, including through future settlement of disputed claims, may require estimated losses to be accrued under accounting standards. Each reporting period, management reviews its loss estimates for remaining alleged and potential claims related to wildfire events. The process for estimating losses associated with alleged and potential wildfire

related claims requires management to exercise significant judgment based on a number of assumptions and subjective factors, including, but not limited to: estimates of known and expected claims by third parties based on currently available information, opinions of counsel regarding litigation risk, the status of and developments in the course of litigation, and prior experience litigating and settling wildfire litigation claims. As additional information becomes available, management's estimates and assumptions regarding the causes and financial impact of wildfire events may change. Actual losses incurred may be higher or lower than estimated based on several factors, including the uncertainty in estimating damages that have been or may be alleged.

2017/2018 Wildfire/Mudslide Events

Wildfires in SCE's territory in December 2017 and November 2018 caused loss of life, substantial damage to both residential and business properties, and service outages for SCE customers. The investigating government agencies, the Ventura County Fire Department ("VCFD") and California Department of Forestry and Fire Protection ("CAL FIRE"), have determined that the largest of the 2017 fires in SCE's territory originated on December 4, 2017, in the Anlauf Canyon area of Ventura County (the investigating agencies refer to this fire as the "Thomas Fire"), followed shortly thereafter by a second fire that originated near Koenigstein Road in the City of Santa Paula (the "Koenigstein Fire"). The December 4, 2017 fires eventually burned substantial acreage in both Ventura and Santa Barbara Counties. According to CAL FIRE, the Thomas and Koenigstein Fires, collectively, burned over 280,000 acres, destroyed or damaged an estimated 1,343 structures and resulted in two confirmed fatalities. The largest of the November 2018 fires in SCE's territory, known as the "Woolsey Fire," originated in Ventura County and burned acreage in both Ventura and Los Angeles Counties. According to CAL FIRE, the Woolsey Fire burned almost 100,000 acres, destroyed an estimated 1,643 structures, damaged an estimated 364 structures and resulted in three confirmed fatalities. Four additional fatalities are alleged to have been associated with the Woolsey Fire.

As described below, multiple lawsuits related to the Thomas and Koenigstein Fires and the Woolsey Fire have been initiated against SCE and Edison International. Some of the Thomas and Koenigstein Fires lawsuits claim that SCE and Edison International have responsibility for the damages caused by debris flows and flooding in Montecito and surrounding areas in January 2018 (the "Montecito Mudslides") based on a theory alleging that SCE has responsibility for the Thomas and/or Koenigstein Fires and further alleging that the Thomas and/or Koenigstein Fires proximately caused the Montecito Mudslides. According to Santa Barbara County initial reports, the Montecito Mudslides destroyed an estimated 135 structures, damaged an estimated 324 structures, and resulted in 21 confirmed fatalities, with two additional fatalities presumed. One of the presumed fatalities has been confirmed.

The Thomas Fire, the Koenigstein Fire, the Montecito Mudslides (defined below) and the Woolsey Fire are each referred to as a "2017/2018 Wildfire/Mudslide Event," and, collectively, referred to as the "2017/2018 Wildfire/Mudslide Events."

Recent developments

Each reporting period, management reviews its loss estimates for remaining alleged and potential claims related to the 2017/2018 Wildfire/Mudslide Events. Management’s third quarter 2022 review included a review of information obtained after the statute of limitations for individual plaintiffs for the Woolsey Fire expired, including information regarding the nature of claims remaining in the Woolsey Fire litigation. Management also reviewed information obtained from settling a substantial portion of the claims in the 2017/2018 Wildfire/Mudslide Events litigations, including higher than expected costs to settle claims. As a result of management’s third quarter 2022 review, SCE recorded an $880 million increase in estimated losses for the 2017/2018 Wildfire/Mudslide Events as of September 30, 2022, which increase is related to the Woolsey Fire. As a result, expected recoveries through FERC electric rates of $50 million against the charge were also recorded, and the resulting net charge to earnings was $830 million ($598 million after-tax).

As of September 30, 2022, Edison International and SCE had paid $7.3 billion under executed settlements, had $237 million to be paid under executed settlements, including $175 million to be paid under the SED Agreement (as defined below), and had $1.2 billion of estimated losses for remaining alleged and potential claims reflected on their consolidated balance sheets

related to the 2017/2018 Wildfire/Mudslide Events. As of the same date, Edison International and SCE had assets for expected recoveries through FERC electric rates of $163 million on their consolidated balance sheets and had exhausted expected insurance recoveries related to the 2017/2018 Wildfire/Mudslide Events.

The estimated losses for the 2017/2018 Wildfire/Mudslide Events do not include an estimate of potential losses related to certain alleged and potential claims made by the California Governor's Office of Emergency Service ("Cal OES") seeking recovery on behalf of itself and 30 state and local government entities that did not pursue their own suits against SCE, but sustained damage in the 2017/2018 Wildfire/Mudslide Events and received funding through the Federal Emergency Management Agency ("FEMA") that was dispersed by the Cal OES. As of the filing of this report SCE has not concluded that losses related to FEMA funds disbursed by Cal OES are probable.

Edison International and SCE may incur a material loss in excess of amounts accrued in connection with the remaining alleged and potential claims related to the 2017/2018 Wildfire/Mudslide Events. Due to the number of uncertainties and possible outcomes related to the 2017/2018 Wildfire/Mudslide Events litigation, Edison International and SCE cannot estimate the upper end of the range of reasonably possible losses that may be incurred.

Estimated losses for the 2017/2018 Wildfire/Mudslide Events litigation are based on a number of assumptions and are subject to change as additional information becomes available. Actual losses incurred may be higher or lower than estimated based on several factors, including the uncertainty in estimating damages that have been or may be alleged. For instance, SCE will receive additional information with respect to damages claimed as the mediation process progresses. Other factors that can cause actual losses incurred to be higher or lower than estimated include the ability to reach settlements and the outcomes of settlements reached through the ongoing claims mediation processes, uncertainties related to the sufficiency of insurance held by plaintiffs, uncertainties related to the litigation processes, uncertainty as to the legal and factual determinations to be made during litigation, including uncertainty as to the contributing causes of the 2017/2018 Wildfire/Mudslide Events, the complexities associated with fires that merge and whether inverse condemnation will be held applicable to SCE with respect to damages caused by the Montecito Mudslides, and the uncertainty as to how these factors impact future settlements.

The CPUC and FERC may not allow SCE to recover uninsured losses through electric rates if it is determined that such losses were not reasonably or prudently incurred. SCE will seek rate recovery of prudently incurred losses and related costs realized in connection with the 2017/2018 Wildfire/Mudslide Events in excess of available insurance, other than for any obligations under the SED Agreement (as defined below). See "Loss Estimates for Third Party Claims and Potential Recoveries from Insurance and through Electric Rates" below for additional information.

External Investigations and Internal Review

The VCFD and CAL FIRE have jointly issued reports concerning their findings regarding the causes of the Thomas Fire and the Koenigstein Fire. The reports did not address the causes of the Montecito Mudslides. SCE has also received a non-final redacted draft of a report from the VCFD regarding Woolsey Fire (the "Redacted Woolsey Report"). SCE cannot predict if or when the VCFD will release its final report regarding the Woolsey Fire. The VCFD and CAL FIRE findings do not determine legal causation of or assign legal liability for the Thomas, Koenigstein or Woolsey Fires; final determinations of legal causation and liability would only be made during lengthy and complex litigation.

The CPUC's Safety and Enforcement Division ("SED") conducted investigations to assess SCE's compliance with applicable rules and regulations in areas impacted by the Thomas, Koenigstein and Woolsey Fires. As discussed below, in October 2021, SCE and the SED executed the SED Agreement (as defined below) to resolve the SED's investigations into the 2017/2018 Wildfire/Mudslide Events.

The California Attorney General's Office has completed its separate investigations of the Thomas Fire and the Woolsey Fire without pursuing criminal charges.

SCE's internal review into the facts and circumstances of each of the 2017/2018 Wildfire/Mudslide Events is complex and time consuming. SCE expects to obtain and review additional information and materials in the possession of third parties during the course of its internal reviews and the litigation processes.

Thomas Fire

On March 13, 2019, the VCFD and CAL FIRE jointly issued a report concluding, after ruling out other possible causes, that the Thomas Fire was started by SCE power lines coming into contact during high winds, resulting in molten metal falling to the ground. However, the report does not state that their investigation found molten metal on the ground. At this time, based on available information, SCE has not determined whether its equipment caused the Thomas Fire. Based on publicly available radar data showing a smoke plume in the Anlauf Canyon area emerging in advance of the report's indicated start time, SCE believes that the Thomas Fire started at least 12 minutes prior to any issue involving SCE's system and at least 15 minutes prior to the start time indicated in the report. SCE is continuing to assess the extent of damages that may be attributable to the Thomas Fire.

Koenigstein Fire

On March 20, 2019, the VCFD and CAL FIRE jointly issued a report finding that the Koenigstein Fire was caused when an energized SCE electrical wire separated and fell to the ground along with molten metal particles and ignited the dry vegetation below. As previously disclosed, SCE believes that its equipment was associated with the ignition of the Koenigstein Fire. SCE is continuing to assess the extent of damages that may be attributable to the Koenigstein Fire.

Montecito Mudslides

SCE's internal review includes inquiry into whether the Thomas and/or Koenigstein Fires proximately caused or contributed to the Montecito Mudslides, whether, and to what extent, the Thomas and/or Koenigstein Fires were responsible for the damages in the Montecito area and other factors that potentially contributed to the losses that resulted from the Montecito Mudslides. Many other factors, including, but not limited to, weather conditions and insufficiently or improperly designed and maintained debris basins, roads, bridges and other channel crossings, could have proximately caused, contributed to or exacerbated the losses that resulted from the Montecito Mudslides.

At this time, based on available information, SCE has not been able to determine whether the Thomas Fire or the Koenigstein Fire, or both, were responsible for the damages in the Montecito area. In the event that SCE is determined to have caused the fire that spread to the Montecito area, SCE cannot predict whether, if fully litigated, the courts would conclude that the Montecito Mudslides were caused or contributed to by the Thomas and/or Koenigstein Fires or that SCE would be liable for some or all of the damages caused by the Montecito Mudslides.

Woolsey Fire

SCE's internal review into the facts and circumstances of the Woolsey Fire is ongoing. SCE has reported to the CPUC that there was an outage on SCE's electric system in the vicinity of where the Woolsey Fire reportedly began on November 8, 2018. SCE is aware of witnesses who saw fire in the vicinity of SCE's equipment at the time the fire was first reported. While SCE did not find evidence of downed electrical wires on the ground in the suspected area of origin, it observed a pole support wire in proximity to an electrical wire that was energized prior to the outage.

The Redacted Woolsey Report states that the VCFD investigation team determined that electrical equipment owned and operated by SCE was the cause of the Woolsey Fire. Absent additional evidence, SCE believes that it is likely that its equipment was associated with the ignition of the Woolsey Fire. SCE expects to obtain and review additional information and materials in the possession of CAL FIRE and others during the course of its internal review and the Woolsey Fire litigation process, including SCE equipment that has been retained by CAL FIRE.

Litigation

Multiple lawsuits related to the 2017/2018 Wildfire/Mudslide Events naming SCE as a defendant have been filed by three categories of plaintiffs: individual plaintiffs, subrogation plaintiffs and public entity plaintiffs. A number of the lawsuits also name Edison International as a defendant and some of the lawsuits were filed as purported class actions. The litigation could take a number of years to be resolved because of the complexity of the matters and number of plaintiffs.

On October 4, 2018, the Los Angeles Superior Court denied Edison International's and SCE's challenge to the application of inverse condemnation to SCE with respect to the Thomas and Koenigstein Fires and, on February 26, 2019, the California Supreme Court denied SCE's petition to review the Superior Court's decision. In April 2022, following a stipulated judgment entered against SCE in the TKM litigation, SCE filed an appeal related to inverse condemnation in the California Court of Appeal.

In January 2019, SCE filed a cross-complaint against certain local public entities alleging that failures by these entities, such as failure to adequately plan for flood hazards and build and maintain adequate debris basins, roads, bridges and other channel crossings, among other things, caused, contributed to or exacerbated the losses that resulted from the Montecito Mudslides. These cross-claims in the Montecito Mudslides litigation were not released as part of the Local Public Entity Settlements (as defined below).

Settlements

In the fourth quarter of 2019, SCE paid $360 million to a number of local public entities to resolve those parties' collective claims arising from the 2017/2018 Wildfire/Mudslide Events (the "Local Public Entity Settlements").

In the third quarter of 2020, Edison International and SCE entered into an agreement (the "TKM Subrogation Settlement") under which all of the insurance subrogation plaintiffs' in the Thomas Fire, Koenigstein Fire and Montecito Mudslides litigation (the "TKM Subrogation Plaintiffs") collective claims arising from the Thomas Fire, Koenigstein Fire or Montecito Mudslides have been resolved. Under the TKM Subrogation Settlement, SCE paid the TKM Subrogation Plaintiffs an aggregate of $1.2 billion in October 2020 and also agreed to pay $0.555 for each dollar in claims to be paid by the TKM Subrogation Plaintiffs to their policy holders on or before July 15, 2023, up to an agreed upon cap.

In January 2021, Edison International and SCE entered into an agreement (the "Woolsey Subrogation Settlement") under which all of the insurance subrogation plaintiffs' in the Woolsey Fire litigation (the "Woolsey Subrogation Plaintiffs") collective claims arising from the Woolsey Fire have been resolved. Under the Woolsey Subrogation Settlement, SCE paid the Woolsey Subrogation Plaintiffs an aggregate of $2.2 billion in March and April 2021. SCE has also agreed to pay $0.67 for each dollar in claims to be paid by the Woolsey Subrogation Plaintiffs to their policy holders on or before July 15, 2023, up to an agreed upon cap.

As of September 30, 2022, SCE has also entered into settlements with approximately 8,500 individual plaintiffs in the 2017/2018 Wildfire/Mudslide Events litigation. In 2020 and 2021, SCE entered into settlements with individual plaintiffs in the 2017/2018 Wildfire/Mudslide Events litigation under which it agreed to pay an aggregate of approximately $300 million and $1.7 billion, respectively, to those individual plaintiffs. In the first, second and third quarters of 2022 SCE entered into settlements with individual plaintiffs in the 2017/2018 Wildfire/Mudslide Events litigation under which it agreed to pay an aggregate of approximately $700 million, $400 million and $350 million, respectively, to those individual plaintiffs. The statutes of limitations for individual plaintiffs in the 2017/2018 Wildfire/Mudslide Events litigation have expired.

Edison International and SCE did not admit wrongdoing or liability as part of any of the settlements described above. Other claims and potential claims related to the 2017/2018 Wildfire/Mudslide Events remain. SCE continues to explore reasonable settlement opportunities with other plaintiffs in the outstanding 2017/2018 Wildfire/Mudslide Events litigation.

SED Agreement

In October 2021, SCE and the SED executed an agreement (the "SED Agreement") to resolve the SED's investigations into the 2017/2018 Wildfire/Mudslide Events and three other 2017 wildfires for, among other things, aggregate costs of $550 million. The $550 million in costs is comprised of a $110 million fine to be paid to the State of California General Fund, $65 million of shareholder-funded safety measures, and an agreement by SCE to waive its right to seek cost recovery in CPUC-jurisdictional rates for $375 million of third-party uninsured claims payments. The SED Agreement provides that SCE may, on a permanent basis, exclude from its ratemaking capital structure any after-tax charges to equity or debt borrowed to finance costs incurred under the SED Agreement. The SED Agreement also imposes other obligations on SCE, including reporting requirements and safety-focused studies. SCE's obligations under the SED Agreement commenced on August 15, 2022, when CPUC approval of the SED Agreement became final and non-appealable. SCE did not admit imprudence, negligence or liability with respect to the 2017/2018 Wildfire/Mudslide Events in the SED Agreement.

Loss Estimates for Third Party Claims and Potential Recoveries from Insurance and through Electric Rates

At September 30, 2022 and December 31, 2021, Edison International's and SCE's consolidated balance sheets include fixed payments to be made under executed settlement agreements and accrued estimated losses of $1.4 billion and $1.7 billion, respectively, for the 2017/2018 Wildfire/Mudslide Events. The following table presents changes in estimated losses since December 31, 2021:

(in millions)

    

Balance at December 31, 20211

$

1,734

Increase in accrued estimated losses

 

1,296

Amounts paid

 

(1,583)

Balance at September 30, 20222

$

1,447

1At December 31, 2021, $131 million in current liabilities, wildfire-related claims, on Edison International's and SCE's consolidated balance sheets consists of settlements executed in connection with the 2017/2018 Wildfire/Mudslide Events. At December 31, 2021, the $1,733 million included in deferred credits and other liabilities, wildfire-related claims, on Edison International's and SCE's consolidated balance sheets includes Edison International's and SCE's best estimate of expected losses for the 2017/2018 Wildfire/Mudslide Events of $1,603 million and other wildfire-related claims estimates of $130 million.
2At September 30, 2022, $173 million in current liabilities, wildfire-related claims, on Edison International's and SCE's consolidated balance sheets consists of $62 million of settlements executed and $111 million of a short term payables under the SED Agreement in connection with the 2017/2018 Wildfire/Mudslide Events. At September 30, 2022, the $1,962 million included in deferred credits and other liabilities, wildfire-related claims, on Edison International's and SCE's consolidated balance sheets includes Edison International's and SCE's best estimate of expected losses for remaining alleged and potential claims related to the 2017/2018 Wildfire/Mudslide Events of $1,210 million, $64 million of a long term payables under the SED Agreement and other wildfire-related claims estimates of $688 million.

For the three and nine months ended September 30, 2022 and 2021, Edison International's and SCE's income statements include charges for the estimated losses, net of expected recoveries from insurance and FERC customers, related to the 2017/2018 Wildfire/Mudslide Events as follows:

Three months ended September 30, 

Nine months ended September 30, 

(in millions)

    

2022

    

2021

    

2022

    

2021

Charge for wildfire-related claims

$

880

$

1,265

$

1,296

$

1,265

Expected revenue from FERC customers

 

(50)

(67)

 

(76)

 

(67)

Total pre-tax charge

 

830

 

1,198

 

1,220

 

1,198

Income tax benefit

 

(232)

(304)

 

(341)

(304)

Total after-tax charge

$

598

$

894

$

879

$

894

For events that occurred in 2017 and early 2018, principally the Thomas and Koenigstein Fires and Montecito Mudslides, SCE had $1.0 billion of wildfire-specific insurance coverage, subject to a self-insured retention of $10 million per occurrence. For the Woolsey Fire, SCE had an additional $1.0 billion of wildfire-specific insurance coverage, subject to a self-insured retention of $10 million per occurrence.

In total, through September 30, 2022, SCE has accrued estimated losses of $8.8 billion, has paid or agreed to pay approximately $7.6 billion in settlements, including $175 million to be paid under the SED Agreement, and has recovered $2.0 billion from its insurance carriers in relation to the 2017/2018 Wildfire/Mudslide Events.

Recovery of SCE's losses realized in connection with the 2017/2018 Wildfire/Mudslide Events in excess of available insurance is subject to approval by regulators. Under accounting standards for rate-regulated enterprises, SCE defers costs as regulatory assets when it concludes that such costs are probable of future recovery in electric rates. SCE utilizes objectively determinable evidence to form its view on probability of future recovery. The only directly comparable precedent in which a California investor-owned utility has sought recovery for uninsured wildfire-related costs is San Diego Gas & Electric's ("SDG&E") requests for cost recovery related to 2007 wildfire activity, where the FERC allowed recovery of all FERC-jurisdictional wildfire-related costs while the CPUC rejected recovery of all CPUC-jurisdictional wildfire-related costs based on a determination that SDG&E did not meet the CPUC's prudency standard. As a result, while SCE does not agree with the CPUC's decision, it believes that the CPUC's interpretation and application of the prudency standard to SDG&E creates substantial uncertainty regarding how that standard will be applied to an investor-owned utility in wildfire cost-recovery proceedings for fires ignited prior to July 12, 2019. SCE will continue to evaluate the probability of recovery based on available evidence, including judicial, legislative and regulatory decisions, including any CPUC decisions illustrating the interpretation and/or application of the prudency standard when making determinations regarding recovery of uninsured wildfire-related costs. While the CPUC has not made a determination regarding SCE's prudency relative to any of the 2017/2018 Wildfire/Mudslide Events, SCE is unable to conclude, at this time, that uninsured CPUC-jurisdictional wildfire-related costs are probable of recovery through electric rates. SCE would record a regulatory asset at the time it obtains sufficient information to support a conclusion that recovery is probable.

Through the operation of its FERC Formula Rate, and based upon the precedent established in SDG&E's recovery of FERC-jurisdictional wildfire-related costs, SCE believes it is probable it will recover its FERC-jurisdictional wildfire and mudslide related costs and has recorded total expected recoveries of $376 million within the FERC balancing account. This was the FERC portion of the total estimated losses accrued. As of September 30, 2022, collections have reduced the regulatory assets remaining in the FERC balancing account to $163 million.

In July 2019, SCE filed a CEMA application with the CPUC to seek recovery of, among other things, approximately $60 million of capital expenditures and capital related expenses incurred to restore service to customers and to repair, replace and restore buildings and SCE's facilities damaged or destroyed as a result of six 2017 fires, primarily the Thomas and Koenigstein Fires. In August 2021, the CPUC issued a final decision which denied without prejudice SCE's application to recover a revenue requirement of $8 million for all six 2017 wildfires on the basis that SCE did not demonstrate that it was prudent in relation to the Thomas and Rye fires and had failed to segregate the costs attributable to the other four fires. Of the $8 million revenue requirement that was denied, $6 million was for the Thomas and Rye fires. CAL FIRE has determined that the Thomas and Rye fires were caused by SCE equipment. The decision allows SCE to submit additional applications

with the CPUC to recover the costs associated with the Thomas and Rye fires, does not specify a deadline for any such applications, and directs that SCE must prove it was prudent in relation to the Thomas and/or Rye fires, as applicable, in any such future applications. As required by the final decision with respect to the other four fires, SCE filed supplemental testimony in November 2021 segregating the restoration costs attributable to each such fire. In June 2022, the CPUC approved SCE's entire request with respect to the other four fires. As of September 30, 2022, SCE has $180 million in assets recorded in property, plant and equipment in relation to restoration costs related to the 2017/2018 Wildfire/Mudslide Events which may not be recoverable. These assets would be impaired if the restoration costs are permanently disallowed by the CPUC in future cost recovery proceedings. SCE continues to incur costs for reconstructing its system and restoring service to structures that were damaged or destroyed by the Thomas, Koenigstein and Woolsey Fires and plans to seek to recover these costs in future applications with the CPUC.

Post-2018 Wildfires

Several wildfires have significantly impacted portions of SCE's service territory after 2018 (the wildfires that originated in Southern California after 2018 where SCE's equipment may be alleged to be associated with the fire's ignition are referred to collectively as the "Post-2018 Wildfires").

Through September 30, 2022, SCE has recorded total estimated losses (established at the lower end of the estimated range of reasonably possible losses) of $689 million, and expected recoveries from insurance of $467 million and expected recoveries through electric rates of $166 million related to the Post-2018 Wildfires. The after-tax net charges to earnings recorded through September 30, 2022 have been $40 million. Expected recoveries from insurance recorded for the Post-2018 Wildfires are supported by SCE’s insurance coverage for multiple policy years.

While Edison International and SCE may incur material losses in excess of the amounts accrued for certain of the Post-2018 Wildfires, Edison International and SCE expect that any losses incurred in connection with any such fire will be covered by insurance, subject to self-insured retentions and co-insurance, and expect that any such losses after expected recoveries from insurance will not be material.

2019 Saddle Ridge Fire

The "Saddle Ridge Fire," originated in Los Angeles county in October 2019 and burned approximately 9,000 acres, destroyed an estimated 19 structures, damaged an estimated 88 structures, and resulted in one fatality and injuries to 8 fire fighters. An investigation into the cause of the Saddle Ridge Fire is being led by the Los Angeles Fire Department. Based on pending litigation and without considering insurance recoveries, it is reasonably possible that SCE will incur a material loss in connection with the Saddle Ridge Fire, but the range of reasonably possible losses that could be incurred cannot be estimated at this time. SCE has not accrued a charge for potential losses relating to the Saddle Ridge Fire.

2020 Bobcat Fire

The "Bobcat Fire" was reported in the vicinity of Cogswell Dam in Los Angeles County, California in September 2020. The United States Forest Service ("USFS") has reported that the Bobcat Fire burned approximately 116,000 acres in Los Angeles County, destroyed an estimated 87 homes, 1 commercial property and 83 minor structures, damaged an estimated 28 homes and 19 minor structures, and resulted in injuries to 6 firefighters. In addition, fire authorities have estimated suppression costs at $80 million. While SCE’s investigation remains ongoing, SCE’s information reflects that a camera in the vicinity of Cogswell Dam captured the initial stages of a fire with the first observed smoke approximately six minutes before a SCE circuit in the area experienced an anomaly (a relay). An investigation into the cause of the Bobcat Fire is being led by the USFS, and the USFS has taken a specific section of an SCE overhead conductor in the vicinity of Cogswell Dam into possession as part of its investigation. SCE understands that the USFS has also taken three tree branches in the area into possession. The SED is also conducting an investigation of the Bobcat Fire. SCE expects to obtain and review additional information and materials in the possession of third parties during the course of its internal reviews and the litigation process.

SCE has accrued material charges for potential losses relating to the Bobcat Fire. The accrued charges correspond to the lower end of the estimated range of reasonably possible losses that may be incurred in connection with the Bobcat Fire and is subject to change as additional information becomes available. While Edison International and SCE may incur a material loss in excess of the amount accrued, they cannot estimate the upper end of the range of reasonably possible losses that may be incurred.

2022 Coastal Fire

The "Coastal Fire" originated in Orange County in May 2022 and burned approximately 200 acres. The Orange County Fire Authority ("OCFA") has reported that the Coastal Fire destroyed 20 residential structures and damaged 11 residential structures. Two firefighters also reportedly sustained minor injuries. In addition, fire authorities have estimated suppression costs at approximately $3 million. While SCE's investigation remains ongoing, SCE's information reflects that a SCE circuit in the area experienced an anomaly (a relay) approximately 2 minutes prior to the reported time of the fire. An investigation into the cause of the Coastal Fire is being led by the OCFA. The OCFA has retained SCE equipment in connection with its investigation. SCE expects to obtain and review additional information and materials in the possession of third parties during the course of its internal reviews and the litigation process. SCE has accrued material charges for potential losses relating to the Coastal Fire. The accrued charges correspond to the lower end of the estimated range of reasonably possible losses that may be incurred in connection with the Coastal Fire and is subject to change as additional information becomes available. While Edison International and SCE may incur a material loss in excess of the amount accrued, they cannot estimate the upper end of the range of reasonably possible losses that may be incurred.

2022 Fairview Fire

The "Fairview Fire" originated in Riverside County in September 2022 and burned approximately 28,000 acres. CAL FIRE has reported that the Fairview Fire destroyed 22 residential structures, damaged 5 residential structures, and destroyed or damaged 17 minor structures. CAL FIRE also reported 2 civilian fatalities, 1 civilian injury and 2 injuries to responding fire personnel. In addition, fire authorities have estimated suppression costs at $39 million. While SCE's investigation remains ongoing, SCE's information reflects that a SCE circuit in the area experienced an anomaly (relay) approximately 8 minutes prior to the reported start time of the fire. An investigation into the cause of the Fairview Fire is being led by the CAL FIRE. CAL FIRE has retained SCE equipment in connection with its investigation. SCE expects to obtain and review additional information and materials in the possession of third parties during the course of its internal reviews and the litigation process. SCE has accrued material charges for potential losses relating to the Fairview Fire. The accrued charges correspond to the lower end of the estimated range of reasonably possible losses that may be incurred in connection with the Fairview Fire and is subject to change as additional information becomes available. While Edison International and SCE may incur a material loss in excess of the amount accrued, they cannot estimate the upper end of the range of reasonably possible losses that may be incurred.

Loss Estimates for Third Party Claims and Potential Recoveries from Insurance and through Electric Rates

At September 30, 2022 and December 31, 2021, Edison International's and SCE's consolidated balance sheets include accrued estimated losses of $683 million and $123 million, respectively, for the Post-2018 Wildfires.

The following table presents changes in estimated losses since December 31, 2021:

(in millions)

    

Balance at December 31, 2021

$

123

Increase in accrued estimated losses

 

565

Amounts paid

 

(5)

Balance at September 30, 2022

$

683

For the three and nine months ended September 30, 2022 and 2021, Edison International's and SCE's income statements include charges for the estimated losses, net of expected recoveries from insurance and customers, related to the Post-2018 Wildfires as follows, respectively:

Three months ended September 30, 

Nine months ended September 30, 

(in millions)

    

2022

    

2021

    

2022

    

2021

Edison International:

Charge for wildfire-related claims1

$

415

$

5

$

565

$

7

Expected insurance recoveries2

 

(244)

 

(383)

 

Expected revenue from CPUC and FERC customers

 

(162)

 

(162)

 

Total pre-tax charge

 

9

 

5

 

20

 

7

Income tax benefit

 

(3)

(1)

(6)

(2)

Total after-tax charge

$

6

$

4

$

14

$

5

Three months ended September 30, 

Nine months ended September 30, 

(in millions)

    

2022

    

2021

    

2022

    

2021

SCE:

Charge for wildfire-related claims1

$

415

$

5

$

565

$

7

Expected insurance recoveries

 

(253)

 

(392)

 

Expected revenue from CPUC and FERC customers

 

(162)

 

(162)

 

Total pre-tax charge

 

 

5

 

11

 

7

Income tax benefit

 

(1)

(3)

(2)

Total after-tax charge

$

$

4

$

8

$

5

1Includes estimated co-insurance payments recorded as operations and maintenance expense.
2For the three and nine months ended September 30, 2022, Edison Insurance Services, Inc. ("EIS"), a wholly-owned subsidiary of Edison International, paid $9 million insurance, which was included in the insurance recovery of SCE but was excluded in Edison International.

Recovery of SCE's losses realized in connection with the Post-2018 Wildfires in excess of available insurance is subject to approval by regulators. The CPUC and FERC may not allow SCE to recover uninsured losses through electric rates if it is determined that such losses were not reasonably or prudently incurred. Under accounting standards for rate-regulated enterprises, SCE defers costs as regulatory assets when it concludes that such costs are probable of future recovery in electric rates. SCE utilizes objectively determinable evidence to form its view on probability of future recovery. As discussed above, there is evidence of a California investor-owned utility seeking recovery for uninsured wildfire-related costs and FERC allowing recovery of all FERC-jurisdictional wildfire-related costs while the CPUC rejected recovery of all CPUC-jurisdictional wildfire-related costs based on a determination that the utility did not meet the CPUC's prudency standard. This evidence was prior to the adoption of AB 1054 on July 12, 2019, after which date AB 1054 clarified that the CPUC must find a utility to be prudent if the utility's conduct related to the ignition was consistent with actions that a reasonable utility would have undertaken in good faith under similar circumstances, at the relevant point in time, and based on the information available at that time. Further, utilities with a valid safety certification at the time of the relevant wildfire will be presumed to have acted prudently related to a wildfire ignition unless a party in the cost recovery proceeding creates serious doubt as to the reasonableness of the utility's conduct, at which time, the burden shifts back to the utility to prove its conduct was prudent. Each of the Post-2018 Wildfires was ignited after July 12, 2019, and SCE has held a valid safety certificate since July 15, 2019. While a California investor-owned utility has not yet sought recovery for uninsured claims and other costs related to wildfires ignited after the adoption of AB 1054, SCE believes that for fires ignited after July 12, 2019, and investor-owned utilities holding a safety certificate at the time of the fire, the CPUC will apply a standard of review similar to that applied by the FERC which presumes all costs requested by an investor-owned utility are reasonable and prudent unless

serious doubt as to the reasonableness of the utility’s conduct is raised. As such, SCE has concluded, at this time, that both uninsured CPUC-jurisdictional and uninsured FERC-jurisdictional wildfire-related costs related to the Post-2018 Wildfires, other than for those already authorized for inclusion in electric rates, are probable of recovery through electric rates. As of September 30, 2022, SCE has recorded total expected recoveries related to the Post-2018 Wildfires of $152 million within the WEMA and risk management balancing account and $10 million within the FERC balancing account. SCE will continue to evaluate the probability of recovery based on available evidence, including regulatory decisions, including any CPUC decisions illustrating the interpretation and/or application of the prudency standard under AB 1054, and, for each applicable fire, evidence that could cast serious doubt as to the reasonableness of SCE's conduct relative to that fire.

Wildfire Insurance Coverage

SCE has approximately $1.0 billion of wildfire-specific insurance coverage for events that may occur during the period July 1, 2022 through June 30, 2023, subject to up to $100 million of self-insured retention and co-insurance per fire, which results in aggregate net coverage of approximately $937 million. Of this coverage, approximately $102 million is provided by EIS) and approximately $835 million is provided by other commercial insurance carriers (commercial insurance carriers other than EIS are referred to herein as "Third-Party Commercial Insurers"). SCE has approximately $1.0 billion of wildfire-specific insurance coverage for events that occurred during the period July 1, 2021 through June 30, 2022, subject to up to $100 million of self-insured retention and co-insurance per fire, as well as additional co-insurance of up to $63 million for the policy year, which resulted in net coverage of approximately $875 million provided by Third-Party Commercial Insurers and $28 million provided by EIS for part of the policy year.

SCE believes that its insurance coverage for the July 1, 2022 through June 30, 2023 period meets its obligation to maintain reasonable insurance coverage under AB 1054. Edison International and SCE record a receivable for insurance recoveries when recovery of a recorded loss is determined to be probable.

SCE's wildfire insurance expense for the July 1, 2022 through June 30, 2023 policy period, prior to any regulatory deferrals, will be approximately $450 million, of which $357 million is paid to Third-Party Commercial Insurers. SCE's wildfire insurance expense for the July 1, 2021 through June 30, 2022 policy period, prior to any regulatory deferrals, was approximately $437 million, of which $413 million was paid to Third-Party Commercial Insurers. The difference between the Third-Party Commercial Insurer cost and total cost in both policy years was paid in premiums to EIS. Wildfire insurance premiums paid for the July 1, 2021 through June 30, 2022 and July 1, 2022 through June 30, 2023 policy periods are being recovered through customer rates. See Note 17 for further information.

While SCE's cost of obtaining wildfire insurance coverage from Third-Party Commercial Insurers was lower in 2022 compared to 2021, SCE's cost of obtaining wildfire insurance coverage in recent years is significantly higher than costs incurred prior to the 2017/2018 Wildfire/Mudslide Events due to, among other things, the number of significant wildfire events throughout California and the application of inverse condemnation to investor-owned utilities. While SCE is required to maintain reasonable insurance coverage under AB 1054, SCE may not be able to obtain a reasonable amount of wildfire insurance, at a reasonable cost, from Third-Party Commercial Insurers for future policy periods.

Employment Litigation Matter

In August 2017, Justin Page and Alfredo Martinez, brought a lawsuit against SCE and Edison International in Los Angeles Superior Court ("Page/Martinez Matter"). Both Mr. Page and Mr. Martinez brought claims of retaliation and failure to prevent retaliation based on allegations that while they were employees of SCE they were retaliated against for reporting harassment of various female employees of SCE. Mr. Page additionally claimed that he was subjected to sexual harassment during the course of his employment. In June 2022, a jury found in favor of Mr. Page and Mr. Martinez and awarded them aggregate compensatory damages of $24.6 million and aggregate punitive damages of $440 million. In July 2022, the parties entered into agreements to resolve Mr. Page's and Mr. Martinez's collective claims in the Page/Martinez Matter. Edison International and SCE did not admit wrongdoing or liability as part of the settlement. SCE has paid the amounts due under

the agreements and recorded an expense, net of expected recoveries from insurance, of $23 million, related to the Page/Martinez Matter.

Environmental Remediation

SCE records its environmental remediation and restoration liabilities when site assessments and/or remedial actions are probable and a range of reasonably likely cleanup costs can be estimated. SCE reviews its sites and measures the liability quarterly, by assessing a range of reasonably likely costs for each identified site using currently available information, including existing technology, presently enacted laws and regulations, experience gained at similar sites, and the probable level of involvement and financial condition of other potentially responsible parties. These estimates include costs for site investigations, remediation, operation and maintenance, monitoring, and site closure. Unless there is a single probable amount, SCE records the lower end of this reasonably likely range of costs (reflected in "Other long-term liabilities") at undiscounted amounts as timing of cash flows is uncertain.

At September 30, 2022, SCE's recorded estimated minimum liability to remediate its 26 identified material sites (sites with a liability balance at September 30, 2022, in which the upper end of the range of expected costs is at least $1 million) was $259 million, including $166 million related to San Onofre. In addition to these sites, SCE also has 14 immaterial sites with a liability balance as of September 30, 2022, for which the total minimum recorded liability was $3 million. Of the $262 million total environmental remediation liability for SCE, $242 million has been recorded as a regulatory asset. SCE expects to recover $37 million through an incentive mechanism that allows SCE to recover 90% of its environmental remediation costs at certain sites (SCE may request to include additional sites in this mechanism) and $205 million through proceedings that allow SCE to recover up to 100% of the costs incurred at certain sites through customer rates. SCE's identified sites include several sites for which there is a lack of currently available information, including the nature and magnitude of contamination, and the extent, if any, that SCE may be held responsible for contributing to any costs incurred for remediating these sites. Thus, no reasonable estimate of cleanup costs can be made for these sites.

The ultimate costs to clean up SCE's identified sites may vary from its recorded liability due to numerous uncertainties inherent in the estimation process, such as: the extent and nature of contamination; the scarcity of reliable data for identified sites; the varying costs of alternative cleanup methods; developments resulting from investigatory studies; the possibility of identifying additional sites; and the time periods over which site remediation is expected to occur. SCE believes that, due to these uncertainties, it is reasonably possible that cleanup costs at the identified material sites and immaterial sites could exceed its recorded liability by up to $120 million and $8 million, respectively. The upper limit of this range of costs was estimated using assumptions least favorable to SCE among a range of reasonably possible outcomes.

SCE expects to clean up and mitigate its identified sites over a period of up to 40 years. Remediation costs for each of the next five years are expected to range from $8 million to $30 million. Costs incurred for the nine months ended September 30, 2022 and 2021 were $5 million and $6 million, respectively.

Based upon the CPUC's regulatory treatment of environmental remediation costs incurred at SCE, SCE believes that costs ultimately recorded will not materially affect its results of operations, financial position, or cash flows. There can be no assurance, however, that future developments, including additional information about existing sites or the identification of new sites, will not require material revisions to estimates.

Nuclear Insurance

SCE is a member of Nuclear Electric Insurance Limited ("NEIL"), a mutual insurance company owned by entities with nuclear facilities. NEIL provides insurance for nuclear property damage, including damages caused by acts of terrorism up to specified limits, and for accidental outages for active facilities. The amount of nuclear property damage insurance purchased for San Onofre and Palo Verde exceeds the minimum federal requirement of $50 million and $1.1 billion, respectively. If

NEIL losses at any nuclear facility covered by the arrangement were to exceed the accumulated funds for these insurance programs, SCE could be assessed retrospective premium adjustments of up to approximately $30 million per year.

Federal law limits public offsite liability claims for bodily injury and property damage from a nuclear incident to the amount of available financial protection, which is currently approximately $13.7 billion for Palo Verde and $560 million for San Onofre. SCE and other owners of San Onofre and Palo Verde have purchased the maximum private primary insurance available through a Facility Form issued by American Nuclear Insurers. SCE withdrew from participation in the secondary insurance pool for San Onofre for offsite liability insurance effective January 5, 2018. Based on its ownership interests in Palo Verde, SCE could be required to pay a maximum of approximately $65 million per nuclear incident for future incidents. However, it would have to pay no more than approximately $10 million per future incident in any one year. Based on its ownership interests in San Onofre and Palo Verde prior to January 5, 2018, SCE could be required to pay a maximum of approximately $255 million per nuclear incident and a maximum of $38 million per year per incident for liabilities arising from events prior to January 5, 2018, although SCE is not aware of any such events.

Upstream Lighting Program

From 2017 – 2019, SCE administered the Upstream Lighting Program, part of a statewide program administered by investor-owned utilities that offered discounted energy efficient light bulbs to customers through incentives to lighting manufacturers. The CPUC began investigating the programs administered by the investor-owned utilities based on reports that investor-owned utilities, including SCE, shipped a significant number of bulbs under the program that could not be tracked to customers. Beginning in January 2020, the CPUC has sought comments on remedies related to SCE's implementation of the Upstream Lighting Program from 2017 through 2019 program years.

In May 2022, the CPUC issued an order directing SCE to show cause as to why SCE should not be required to: (i) refund ratepayer funding for the portion of the program budget associated with light bulbs that were unaccounted for, (ii) refund energy efficiency incentive mechanism ("ESPI") awards associated with unaccounted-for light bulbs, and (iii) pay penalties for misrepresenting program progress and results to the CPUC. In September 2022, a Presiding Officer’s Decision ("POD") was issued in the proceeding finding that SCE mismanaged its Upstream Lighting Program from 2017 through 2019 and failed to ensure that efficient light bulbs were tracked and sold as intended by the program design. The POD requires SCE to (i) refund to ratepayers $76.1 million, representing the portion of the program budget associated with light bulbs that could not be accounted for, (ii) refund to ratepayers $6.8 million, representing ESPI awards associated with light bulbs that could not be accounted for, (iii) pay $19.06 million in fines; and (iv) bear the cost of SCE's investigation, approximately $900,000. SCE filed an appeal of the POD in October 2022. The POD will become the final decision of the CPUC when the CPUC makes a decision on the appeal. As of September 30, 2022, SCE has accrued liabilities of $102 million for losses relating to the Upstream Lighting Program.