XML 52 R31.htm IDEA: XBRL DOCUMENT v3.8.0.1
Property, Plant and Equipment (Tables)
12 Months Ended
Dec. 31, 2017
Property, Plant and Equipment [Abstract]  
Schedule of Property, Plant, and Equipment
SCE's property, plant and equipment included in the consolidated balance sheets is composed of the following:
 
December 31,
(in millions)
2017
 
2016
Distribution
$
23,633

 
$
22,332

Transmission
13,127

 
12,549

Generation
3,468

 
3,376

General plant and other
4,534

 
4,633

Accumulated depreciation
(9,355
)
 
(9,000
)
 
35,407

 
33,890

Construction work in progress
3,175

 
2,790

Nuclear fuel, at amortized cost
126

 
126

Total utility property, plant and equipment
$
38,708

 
$
36,806


Schedule of Jointly Owned Utility Projects
The following is SCE's investment in each asset as of December 31, 2017:
(in millions)
Plant in Service
Construction Work in Progress
Accumulated
Depreciation
Nuclear Fuel
(at amortized cost)
Net Book Value
Ownership
Interest
Transmission systems:
 
 
 
 
 
 
Eldorado
$
237

$
14

$
24

$

$
227

59
%
Pacific Intertie
192

41

78


155

50
%
Generating station:
 
 
 
 
 
 
Palo Verde (nuclear)
2,001

52

1,557

126

622

16
%
Total
$
2,430

$
107

$
1,659

$
126

$
1,004