Commitments and Contingencies (Schedule of Settlement Agreement) (Details) - USD ($)
$ in Millions
12 Months Ended
Dec. 31, 2017
Dec. 31, 2016
Dec. 31, 2015
Loss Contingencies [Line Items]      
Total pre-tax charge $ 738 $ 21 $ 5
SCE      
Loss Contingencies [Line Items]      
Total pre-tax charge 716 $ 0 $ 0
Total after-tax charge 448    
SCE | Utility Shareholder Agreement      
Loss Contingencies [Line Items]      
Total pre-tax charge 143    
SCE | DOE litigation regulatory liability      
Loss Contingencies [Line Items]      
Total pre-tax charge (72)    
SCE | Arbitration with Mitsubishi Heavy Industries      
Loss Contingencies [Line Items]      
Total pre-tax charge (47)    
SCE | GHG Reduction Program      
Loss Contingencies [Line Items]      
Total pre-tax charge (10)    
SCE | San Onofre base regulatory asset      
Loss Contingencies [Line Items]      
Total pre-tax charge 696    
SCE | Other      
Loss Contingencies [Line Items]      
Total pre-tax charge $ 6