XML 73 R62.htm IDEA: XBRL DOCUMENT v3.5.0.2
Commitments and Contingencies (Details)
1 Months Ended 6 Months Ended 12 Months Ended
Jul. 14, 2016
USD ($)
Apr. 30, 2016
USD ($)
Mar. 31, 2016
USD ($)
Oct. 31, 2013
USD ($)
Jun. 30, 2010
USD ($)
Jun. 30, 2016
USD ($)
site
invoice
Jun. 30, 2015
USD ($)
Dec. 31, 2012
USD ($)
Sep. 30, 2015
USD ($)
Schedule Of Commitments And Contingencies [Line Items]                  
Damages sought     $ 39,900,000            
Nuclear Insurance                  
Schedule Of Commitments And Contingencies [Line Items]                  
Federal limit on public liability claims from nuclear incident, approximate           $ 13,400,000,000      
Southern California Edison                  
Schedule Of Commitments And Contingencies [Line Items]                  
Damages sought         $ 112,000,000        
Identified material sites for environmental remediation (in number of sites) | site           19      
Minimum costs to be identified site           $ 1,000,000      
Minimum liability for environmental remediation for material sites           $ 130,000,000      
Immaterial sites for environmental remediation (in number of sites) | site           39      
Environmental remediation liability           $ 134,000,000      
Regulatory assets related to environmental remediation           128,000,000      
Portion of recorded liability recoverable from incentive mechanism           $ 46,000,000      
Percentage of environmental remediation costs recoverable through an incentive mechanism (as a percent)           90.00%      
Liability incurred at majority of the remaining sites through customer rates           $ 82,000,000      
Environmental remediation costs to be recovered (as a percent)           100.00%      
Amount that cleanup costs could exceed recorded liability for identified material sites           $ 165,000,000      
Amount that cleanup costs could exceed recorded liability for immaterial sites           $ 7,000,000      
Maximum expected period for cleanup of identified sites (in years)           30 years      
Remediation cost estimates (period)           4 years      
Expected annual environmental remediation costs, low end of range           $ 7,000,000      
Expected annual environmental remediation costs, high end of range           23,000,000      
Environmental remediation costs           1,000,000 $ 3,000,000    
Threshold for wildfire claims (new lines for additional coverage)           910,000,000      
Increase in self-insurance           90,000,000      
Combined threshold for wildfire claims           1,000,000,000      
Self-insured retention per wildfire occurrence           10,000,000      
Damage award   $ 124,000,000              
Southern California Edison | San Onofre                  
Schedule Of Commitments And Contingencies [Line Items]                  
Minimum liability for environmental remediation for material sites           $ 79,000,000      
Southern California Edison | San Onofre | Mitsubishi Heavy Industries Ltd                  
Schedule Of Commitments And Contingencies [Line Items]                  
Damages sought       $ 4,000,000,000          
Number of invoices for reimbursement | invoice           7      
Invoiced amount for reimbursement           $ 149,000,000      
Invoiced amount paid for reimbursement           $ 45,000,000      
Share of invoice paid               $ 35,000,000  
Southern California Edison | San Onofre | Mitsubishi Heavy Industries Ltd                  
Schedule Of Commitments And Contingencies [Line Items]                  
Ratepayer allocation of recovery from recoveries           50.00%      
Entity allocation of recovery from recoveries           50.00%      
Ratepayer allocation of recovery from recoveries, initial amount of settlement           $ 282,000,000      
Southern California Edison | San Onofre | Replacement Steam Generators                  
Schedule Of Commitments And Contingencies [Line Items]                  
Warranty period           20 years      
Southern California Edison | Nuclear Insurance                  
Schedule Of Commitments And Contingencies [Line Items]                  
Limit on assessment of retrospective premium adjustments, per year, approximate           $ 52,000,000      
Maximum assessment per each nuclear incident           255,000,000      
Maximum yearly assessment per nuclear incident           38,000,000      
Mitsubishi Heavy Industries Ltd | San Onofre                  
Schedule Of Commitments And Contingencies [Line Items]                  
Maximum liability per purchase agreement for damages           138,000,000      
Asserted counterclaim       $ 41,000,000          
SCE and other owners of San Onofre and Palo Verde                  
Schedule Of Commitments And Contingencies [Line Items]                  
Damages sought         $ 142,000,000        
Damage award   $ 162,000,000              
SCE and other owners of San Onofre and Palo Verde | Nuclear Insurance | San Onofre and Palo Verde                  
Schedule Of Commitments And Contingencies [Line Items]                  
Loss limit, property damage insurance, federal minimum requirement           1,060,000,000      
Maximum                  
Schedule Of Commitments And Contingencies [Line Items]                  
Minimum liability for environmental remediation for immaterial sites                 $ 74,500,000
Maximum | Subsequent Event                  
Schedule Of Commitments And Contingencies [Line Items]                  
Penalties per day per violation $ 50,000                
Minimum | Subsequent Event                  
Schedule Of Commitments And Contingencies [Line Items]                  
Penalties per day per violation $ 500                
Minimum | Southern California Edison                  
Schedule Of Commitments And Contingencies [Line Items]                  
Minimum liability for environmental remediation for immaterial sites           $ 4,000,000