XML 52 R32.htm IDEA: XBRL DOCUMENT v3.3.1.900
Property, Plant and Equipment (Tables)
12 Months Ended
Dec. 31, 2015
Property, Plant and Equipment [Abstract]  
Schedule of Property, Plant, and Equipment
SCE's property, plant and equipment included in the consolidated balance sheets is composed of the following:
 
December 31,
(in millions)
2015
 
2014
Transmission
$
11,592

 
$
10,391

Distribution
20,871

 
19,255

Generation
3,138

 
2,986

General plant and other
4,543

 
4,889

Accumulated depreciation
(8,548
)
 
(8,132
)
 
31,596

 
29,389

Construction work in progress
3,218

 
3,339

Nuclear fuel, at amortized cost
131

 
131

Total utility property, plant and equipment
$
34,945

 
$
32,859


Schedule of Jointly Owned Utility Projects
The following is SCE's investment in each asset as of December 31, 2015:
(in millions)
Plant in Service
Construction Work in Progress
Accumulated
Depreciation
Nuclear Fuel
(at amortized cost)
Net Book Value
 
Ownership
Interest
Transmission systems:
 
 
 
 
 
 
 
Eldorado
$
186

$
38

$
20

$

$
204

 
59%
Pacific Intertie
191

11

79


123

 
50%
Generating station:
 
 
 
 
 
 
 
Palo Verde (nuclear)
1,928

62

1,538

131

583

 
16%
Total
$
2,305

$
111

$
1,637

$
131

$
910