Commitments and Contingencies (Details)
1 Months Ended 9 Months Ended 12 Months Ended
Oct. 26, 2015
USD ($)
communication
Aug. 05, 2015
USD ($)
May. 06, 2015
USD ($)
Apr. 17, 2015
USD ($)
Oct. 31, 2015
USD ($)
claims
Oct. 31, 2013
USD ($)
Sep. 30, 2015
USD ($)
site
invoices
Sep. 30, 2014
USD ($)
Dec. 31, 2012
USD ($)
Jun. 01, 2015
USD ($)
Aug. 31, 2014
USD ($)
Subsequent Event                      
Schedule Of Commitments And Contingencies [Line Items]                      
Number of claims | claims         2            
Nuclear Insurance                      
Schedule Of Commitments And Contingencies [Line Items]                      
Federal limit on public liability claims from nuclear incident, approximate             $ 13,400,000,000        
Nuclear Insurance | San Onofre                      
Schedule Of Commitments And Contingencies [Line Items]                      
Estimated settlement amount                     $ 433,000,000
Nuclear Insurance | Subsequent Event | San Onofre                      
Schedule Of Commitments And Contingencies [Line Items]                      
Claims paid         $ 400,000,000            
Southern California Edison                      
Schedule Of Commitments And Contingencies [Line Items]                      
Damages sought     $ 38,200,000 $ 648,000,000     182,000,000        
Number of communications that should have been reported   9                  
Minimum damages   $ 500         $ 4,000,000        
Maximum damages   $ 50,000                  
Identified material sites for environmental remediation (in number of sites) | site             19        
Minimum costs to be Identified Site             $ 1,000,000        
Minimum liability for environmental remediation for material sites             $ 137,000,000        
Immaterial sites for environmental remediation (in number of sites) | site             39        
Environmental remediation liability             $ 140,000,000        
Regulatory assets related to environmental remediation             135,000,000        
Portion of recorded liability recoverable from incentive mechanism             $ 50,000,000        
Percentage of environmental remediation costs recoverable through an incentive mechanism (as a percent)             90.00%        
Liability incurred at majority of the remaining sites through customer rates             $ 84,000,000        
Environmental remediation costs to be recovered (as a percent)             100.00%        
Amount that cleanup costs could exceed recorded liability for identified material sites             $ 163,000,000        
Amount that cleanup costs could exceed recorded liability for immaterial sites             $ 8,000,000        
Maximum expected period for cleanup of identified sites (in years)             30 years        
Remediation cost estimates (period)             5 years        
Expected annual environmental remediation costs, low end of range             $ 7,000,000        
Expected annual environmental remediation costs, high end of range             24,000,000        
Environmental remediation costs             5,000,000 $ 3,000,000      
Insurance coverage for wildfire liabilities Limit             390,000,000     $ 610,000,000  
Self insurance retention per wildfire occurrence                   $ 10,000,000  
Threshold for wildfire claims (new lines for additional coverage)             610,000,000        
Southern California Edison | San Onofre                      
Schedule Of Commitments And Contingencies [Line Items]                      
Minimum liability for environmental remediation for material sites             $ 82,000,000        
Southern California Edison | San Onofre | Mitsubishi Heavy Industries Ltd                      
Schedule Of Commitments And Contingencies [Line Items]                      
Damages sought           $ 4,000,000,000          
Number of invoices for reimbursement | invoices             7        
Invoiced amount for reimbursement             $ 149,000,000        
Invoiced amount paid for reimbursement             $ 45,000,000        
Share of invoice paid                 $ 35,000,000    
Southern California Edison | San Onofre | Mitsubishi Heavy Industries Ltd                      
Schedule Of Commitments And Contingencies [Line Items]                      
Ratepayer allocation of recovery from recoveries             50.00%        
Entity allocation of recovery from recoveries             50.00%        
Ratepayer allocation of recovery from recoveries, initial amount of settlement             $ 282,000,000        
Southern California Edison | San Onofre | Replacement Steam Generators                      
Schedule Of Commitments And Contingencies [Line Items]                      
Warranty period             20 years        
Southern California Edison | Subsequent Event                      
Schedule Of Commitments And Contingencies [Line Items]                      
Number of communications that should have been reported | communication 8                    
Estimated settlement amount $ 16,740,000                    
Southern California Edison | Nuclear Insurance                      
Schedule Of Commitments And Contingencies [Line Items]                      
Limit on assessment of retrospective premium adjustments, per year, approximate             $ 52,000,000        
Maximum assessment per each nuclear incident             255,000,000        
Maximum yearly assessment per nuclear incident             38,000,000        
Southern California Edison | Nuclear Insurance | San Onofre                      
Schedule Of Commitments And Contingencies [Line Items]                      
Estimated settlement amount                     $ 339,000,000
Southern California Edison | Nuclear Insurance | Subsequent Event | San Onofre                      
Schedule Of Commitments And Contingencies [Line Items]                      
Claims paid         $ 313,000,000            
Ratepayer allocation of recovery from recoveries         95.00%            
Entity allocation of recovery from recoveries         5.00%            
Mitsubishi Heavy Industries Ltd | San Onofre                      
Schedule Of Commitments And Contingencies [Line Items]                      
Maximum liability per purchase agreement for damages             138,000,000        
Asserted counterclaim           $ 41,000,000          
SCE and other owners of San Onofre and Palo Verde | Nuclear Insurance | San Onofre and Palo Verde                      
Schedule Of Commitments And Contingencies [Line Items]                      
Loss limit, property damage insurance, federal minimum requirement             1,060,000,000        
Power Purchase Contracts | Southern California Edison                      
Schedule Of Commitments And Contingencies [Line Items]                      
2015 additional commitments             21,000,000        
2016 additional commitments             142,000,000        
2017 additional commitments             303,000,000        
2018 additional commitments             352,000,000        
2019 additional commitments             391,000,000        
Additional commitments due after 2019             $ 5,200,000,000