Commitments and Contingencies
12 Months Ended
Dec. 31, 2011
Commitments and Contingencies Disclosure [Abstract]  
Commitments and Contingencies
Commitments and Contingencies
Third-Party Power Purchase Agreements
SCE enters into various agreements to purchase power and electric capacity, including:
Renewable Energy Contracts – California law requires retail sellers of electricity to comply with an RPS by delivering renewable energy, primarily through power purchase contracts. Renewable energy contract payments generally consist of payments based on a fixed price per megawatt hour. As of December 31, 2011, SCE had 68 renewable energy contracts that were approved by the CPUC and met critical contract provisions which expire at various dates between 2012 and 2035.
Qualifying Facility Power Purchase Agreements – Under the Public Utility Regulatory Policies Act of 1978 ("PURPA"), electric utilities are required, with exceptions, to purchase energy and capacity from independent power producers that are qualifying co-generation facilities and qualifying small power production facilities ("QFs"). As of December 31, 2011, SCE had 171 QF contracts which expire at various dates between 2012 and 2025.
Other Power Purchase Agreements – In accordance with the SCE's CPUC-approved long-term procurement plans, SCE has entered into capacity agreements with third parties, including 15 tolling arrangements, 40 power call options and 143 resource adequacy contracts. SCE's obligations under a portion of these agreements are limited to payments for the availability of such resources.
At December 31, 2011, the undiscounted future minimum expected payments for power purchase agreements that have been approved by the CPUC and have completed major milestones for construction were as follows:
(in millions)
Renewable
Energy
Contracts
 
QF Power
Purchase
Agreements
 
Other Purchase
Agreements1
2012
$
561

 
$
439

 
$
624

2013
616

 
438

 
828

2014
712

 
437

 
812

2015
751

 
426

 
705

2016
752

 
368

 
476

Thereafter
13,186

 
1,569

 
2,853

Total future commitments
$
16,578

 
$
3,677

 
$
6,298

1  
Includes power purchase agreements with SCE's consolidated affiliates.
Some of the power purchase agreements that SCE entered into with independent power producers are treated as operating and capital leases. The following table shows the future minimum expected payments due under the contracts that are treated as operating and capital leases (these amounts are also included in the table above). The future expected payments for capital
leases are discounted to their present value in the table below using SCE's incremental borrowing rate at the inception of the leases. The amount of this discount is shown in the table below as the amount representing interest.
(in millions)
Operating
Leases
 
Capital
Leases
2012
$
839

 
$
33

2013
966

 
33

2014
930

 
72

2015
916

 
109

2016
815

 
109

Thereafter
11,468

 
1,751

Total future commitments
$
15,934

 
$
2,107

Amount representing executory costs
 

 
(445
)
Amount representing interest
 

 
(773
)
Net commitments
 

 
$
889


Operating lease expense for these power purchase agreements was $1.4 billion in 2011, $1.3 billion in 2010 and $1.2 billion in 2009. The timing of SCE's recognition of the lease expense conforms to ratemaking treatment for SCE's recovery of the cost of electricity and is included in purchased power.
At December 31, 2011 and 2010, net capital leases reflected in "Utility plant" on the consolidated balance sheets were $222 million and $227 million, including accumulated amortization of $27 million and $22 million, respectively. SCE had $6 million and $5 million included in "Other current liabilities" and $216 million and $222 million included in "Other deferred credits and other liabilities," representing the present value of the minimum lease payments due under these contracts recorded on the consolidated balance sheets at December 31, 2011 and 2010, respectively. SCE has a power purchase contract, with net commitments totaling $667 million, that meet the requirements for capital lease treatment, but is not reflected on the consolidated balance sheets since the lease term begins in 2014.
Power Plant and Other Lease Commitments
The following summarizes the estimated minimum future commitments for noncancelable power plant (which are related to EMG's long-term leases primarily related to the Illinois power facilities and Homer City facilities) and other operating leases (excluding SCE's power purchase agreements discussed above):
(in millions)
Operating
Leases –
Power
Plants
 
Operating
Leases –
Other
2012
$
311

 
$
99

2013
300

 
100

2014
289

 
83

2015
174

 
75

2016
115

 
65

Thereafter
1,412

 
469

Total future commitments
$
2,601

 
$
891


The minimum commitments above do not include EMG's contingent rentals with respect to the wind projects which may be paid under certain leases on the basis of a percentage of sales calculation if this is in excess of the stipulated minimum amount.
Operating lease expense for power plants and other leases (primarily related to vehicles, office space and other equipment) were $279 million in 2011, $279 million in 2010 and $256 million in 2009.
Sale-Leaseback Transactions
On December 7, 2001, a subsidiary of EMG completed a sale-leaseback of EMG's Homer City plant to third-party lessors. Under the terms of the 33.67-year leases, EMG's subsidiary is obligated to make semi-annual lease payments on each April 1 and October 1. If an owner-lessor intends to sell its interest in the Homer City plant, EMG has a right of first refusal to acquire the interest at fair market value. The gain on the sale of the facilities has been deferred and is being amortized over the term of the leases.
Under the sale-leaseback documents, Homer City rent payments are comprised of two components, senior rent and equity rent. Senior rent is used exclusively for debt service to secured lease obligation bondholders, while equity rent is paid to the owner-lessors. In order to pay equity rent, among other requirements, Homer City must meet historical and projected senior rent service coverage ratios of 1.7 to 1 (subject to reduction to 1.3 to 1 under certain circumstances). The senior rent service coverage ratio of 1.18 to 1 for the 12 months ended December 31, 2011 was below the covenant threshold and Homer City also did not meet the threshold for the prospective two 12-month periods, which currently precludes Homer City from making distributions, including repayment of certain intercompany loans and from paying the equity portion of the rent payment. A failure to pay equity rent does not entitle the owner-lessors to foreclose upon Homer City's leasehold interest, but it does result in the suspension of Homer City's ability to make permitted distributions. Moreover, Homer City would be permanently restricted in its ability to make permitted distributions if a failure to pay equity rent when due was not cured within nine months, or even if cured, occurred more than one additional time during the term of the lease. Homer City is not subject to any minimum historical and projected senior rent service coverage ratios except as conditions to distributions and equity rent payments. Also, failure by Homer City to pay equity rent when due in April 2012 could trigger termination of the $48 million senior rent reserve letter of credit. Homer City would then be required to fund the senior rent reserve, and failure to do so could entitle counterparties to seek available remedies under the sale-leaseback documents, including termination or foreclosure upon the leasehold interest. As a result of the expectation that EMG is likely to lose substantially all beneficial economic interest in and material control of the Homer City plant, EMG recorded an impairment charge of $1.03 billion for the fourth quarter of 2011. For further discussion, see Note 16. Asset Impairments, Lease Terminations and Other.
On August 24, 2000, a subsidiary of EMG completed a sale-leaseback of EMG's Powerton and Joliet power stations located in Illinois to third-party lessors. Under the terms of the leases (33.75 years for Powerton and 30 years for Joliet), EMG's subsidiary makes semi-annual lease payments on each January 2 and July 2, which began January 2, 2001. EMG guarantees its subsidiary's payments under the leases. If a lessor intends to sell its interest in the Powerton or Joliet power station, EMG has a right of first refusal to acquire the interest at fair market value. The gain on the sale of the power stations has been deferred and is being amortized over the term of the leases.
Under the terms of the foregoing sale-leaseback transactions, distributions are restricted by EMG's subsidiaries unless specified financial covenants are met. At December 31, 2011, Midwest Generation met these covenants. In addition, the lease agreements and the Midwest Generation credit agreement contain covenants that include restrictions on the ability of these subsidiaries to, among other things, incur debt, create liens on its property, merge or consolidate, sell assets, make investments, engage in transactions with affiliates, make distributions, make capital expenditures, enter into agreements restricting its ability to make distributions, engage in other lines of business, enter into swap agreements, or engage in transactions for any speculative purpose.
Nuclear Decommissioning Commitment
SCE has collected in rates amounts for the future costs of removal of its nuclear assets, and has placed those amounts in independent trusts. The recorded liability to decommission SCE's nuclear power facilities is $2.5 billion as of December 31, 2011, based on site-specific studies performed in 2008 for San Onofre and 2007 for Palo Verde. Changes in the estimated costs, timing of decommissioning or the assumptions underlying these estimates could cause material revisions to the estimated total cost to decommission. SCE estimates that it will spend approximately $8.6 billion through 2053 to decommission its active nuclear facilities. This estimate is based on SCE's decommissioning cost methodology used for ratemaking purposes, escalated at rates ranging from 1.8% to 6.9% (depending on the cost element) annually. These costs are expected to be funded from independent decommissioning trusts, which received contributions of $23 million in both 2011 and 2010 and $46 million in 2009. SCE estimates annual after-tax earnings on the decommissioning funds of 4.2% to 5.7%. If the assumed return on trust assets is not earned, it is probable that additional funds needed for decommissioning will be recoverable through rates in the future. If the assumed return on trust assets is greater than estimated, funding amounts may be reduced through future decommissioning proceedings.
All of SCE's San Onofre Unit 1 decommissioning costs will be paid from its nuclear decommissioning trust funds and are subject to CPUC review. The estimated remaining cost to decommission San Onofre Unit 1 is recorded as an ARO liability of
$65 million at December 31, 2011. Total expenditures for the decommissioning of San Onofre Unit 1 were $597 million from the beginning of the project in 1998 through December 31, 2011.
Decommissioning expense under the ratemaking method was $23 million, $30 million and $46 million in 2011, 2010 and 2009, respectively. The ARO for decommissioning SCE's active nuclear facilities was $2.5 billion and $2.4 billion at December 31, 2011 and 2010, respectively. See Note 4 and Note 15 for discussion on the nuclear decommissioning trusts.
Other Commitments
Certain other commitments for the years 2012 through 2016 are estimated below:
(in millions)
2012
 
2013
 
2014
 
2015
 
2016
Nuclear fuel supply contracts
$
190

 
$
135

 
$
78

 
$
78

 
$
128

Other fuel supply contracts
479

 
237

 
208

 
83

 
46

Coal transportation agreements1
386

 
326

 
333

 
315

 
315

Gas transportation agreements
7

 
7

 
7

 
7

 
8

Capital expenditures
286

 
19

 

 

 

Other contractual obligations
114

 
73

 
43

 
37

 
19


1 
In years 2013 through 2016, represents contracts for minimum volumes without regard to payment of alternative liquidated damages or plant closures.
Fuel Supply Contracts and Coal Transportation Agreements
SCE has fuel supply contracts which require payment only if the fuel is made available for purchase. SCE has a coal fuel contract that requires payment of certain fixed charges whether or not coal is delivered.
At December 31, 2011, Midwest Generation and Homer City had commitments to purchase coal from third-party suppliers at fixed prices, subject to adjustment clauses. In addition, Midwest Generation had contractual agreements for the transportation of coal. The commitments under these contracts are based on either actual coal purchases derived from committed coal volumes set forth in fuel supply contracts or minimum quantities as set forth in the transportation agreements. The transportation agreements have provisions that address the financial exposure of Midwest Generation related to a plant closure under certain circumstances as specified in the agreements.
Gas Transportation Agreements
At December 31, 2011, EMG had a contractual commitment to transport natural gas. EMG's share of the commitment to pay minimum fees under its gas transportation agreement, which has a remaining contract length of six years, is estimated to aggregate $36 million in the next five years. EMG has entered into agreements to re-sell the transportation under this agreement which aggregates $45 million over the same period.
Capital Commitments
At December 31, 2011, EMG's subsidiaries had firm commitments for capital expenditures primarily related to the Walnut Creek project and the construction of wind projects. EMG intends to fund these expenditures through project-level financing, U.S. Treasury grants, Midwest Generation and EME lines of credit, if available, cash on hand and cash generated from operations.
Other Contractual Obligations
At December 31, 2011, EMG and its subsidiaries were party to turbine operations and maintenance agreements, agreements for the purchase of materials used in the operation of environmental controls equipment and a coal cleaning agreement.
Guarantees and Indemnities
Edison International's subsidiaries have various financial and performance guarantees and indemnity agreements which are issued in the normal course of business. The contracts discussed below included performance guarantees.
Environmental Indemnities Related to the Midwest Generation Plants
In connection with the acquisition of the Midwest Generation plants, EME agreed to indemnify Commonwealth Edison Company (Commonwealth Edison) with respect to specified environmental liabilities before and after December 15, 1999, the date of sale. The indemnification obligations are reduced by any insurance proceeds and tax benefits related to such indemnified claims and are subject to a requirement that Commonwealth Edison takes all reasonable steps to mitigate losses related to any such indemnification claim. Also, in connection with the sale-leaseback transaction related to the Powerton and Joliet Stations in Illinois, EME agreed to indemnify the owner-lessors for specified environmental liabilities. These indemnities are not limited in term or amount. Due to the nature of the obligations under these indemnities, a maximum potential liability cannot be determined. Commonwealth Edison has advised EME that Commonwealth Edison believes it is entitled to indemnification for all liabilities, costs, and expenses that it may be required to bear as a result of the litigation discussed below under "—Contingencies—Midwest Generation New Source Review and Other Litigation." Except as discussed below, EME has not recorded a liability related to these environmental indemnities.
Midwest Generation entered into a supplemental agreement with Commonwealth Edison and Exelon Generation Company LLC on February 20, 2003 to resolve a dispute regarding interpretation of Midwest Generation's reimbursement obligation for asbestos claims under the environmental indemnities set forth in the Asset Sale Agreement. Under this supplemental agreement, Midwest Generation agreed to reimburse Commonwealth Edison and Exelon Generation for 50% of specific asbestos claims pending as of February 2003 and related expenses less recovery of insurance costs, and agreed to a sharing arrangement for liabilities and expenses associated with future asbestos-related claims as specified in the agreement. The obligations under this agreement are not subject to a maximum liability. The supplemental agreement had an initial five-year term with an automatic renewal provision for subsequent one-year terms (subject to the right of either party to terminate); pursuant to the automatic renewal provision, it has been extended until February 2013. There were approximately 226 cases for which Midwest Generation was potentially liable that had not been settled and dismissed at December 31, 2011. While the range of this liability is between $46 million and $64 million, Midwest Generation had recorded an estimated liability of $54 million and $56 million at December 31, 2011 and 2010, respectively, related to this contractual indemnity.
Environmental Indemnity Related to the Homer City Plant
In connection with the acquisition of the Homer City plant, Homer City agreed to indemnify the sellers with respect to specified environmental liabilities before and after the date of sale. EME guaranteed this obligation of Homer City. Also, in connection with the sale-leaseback transaction related to the Homer City plant, Homer City agreed to indemnify the owner-lessors for specified environmental liabilities. Due to the nature of the obligations under these indemnity provisions, they are not subject to a maximum potential liability and do not have expiration dates. EME has not recorded a liability related to this indemnity. For discussion of the New Source Review lawsuit filed against Homer City, see "—Contingencies—Homer City New Source Review and Other Litigation."
Indemnities Provided under Asset Sale and Sale-Leaseback Agreements
The asset sale agreements for the sale of EME's international assets contain indemnities from EME to the purchasers, including indemnification for taxes imposed with respect to operations of the assets prior to the sale and for pre-closing environmental liabilities. Not all indemnities under the asset sale agreements have specific expiration dates. At December 31, 2011 and 2010, EME had recorded a liability of $36 million and $42 million, respectively, related to these matters.
In connection with the sale of various domestic assets, EME has from time to time provided indemnities to the purchasers, including for taxes imposed with respect to operations of the assets prior to the sale. Not all indemnities under the asset sale agreements have specific expiration dates. Due to the nature of these potential obligations, EME cannot determine a range of estimates and has not recorded a liability related to these indemnities.
In connection with the sale-leaseback transactions related to the Homer City plant in Pennsylvania, the Powerton and Joliet Stations in Illinois and, previously, the Collins Station in Illinois, EME and several of its subsidiaries entered into tax indemnity agreements. Under certain of these tax indemnity agreements, Homer City and Midwest Generation, as the lessees in the sale-leaseback transactions agreed to indemnify the respective owner-lessors for specified adverse tax consequences that could result from certain situations set forth in each tax indemnity agreement, including specified defaults under the respective leases. Although the Collins Station lease terminated in April 2004, Midwest Generation's indemnities in favor of its former lease equity investors are still in effect. EME provided similar indemnities in the sale-leaseback transactions related to the Powerton and Joliet Stations in Illinois. The potential indemnity obligations under these tax indemnity agreements could be significant. Due to the nature of these potential obligations, EME cannot determine a range of estimated obligation which would be triggered by a valid claim from the owner-lessors. EME has not recorded a liability for these matters.
In addition to the indemnity provided by Homer City, EME agreed to indemnify the owner-lessors in the sale-leaseback transaction related to the Homer City plant for certain negative federal income tax consequences should the rent payments be "levelized" for tax purposes and for potential foreign tax credit losses in the event that the owner-lessor's debt is characterized as recourse, rather than nonrecourse. This indemnity covers a limited range of possible tax consequences that are unrelated to performance under the lease.
Indemnity Provided as Part of the Acquisition of Mountainview
In connection with the acquisition of the Mountainview power plant, SCE agreed to indemnify the seller with respect to specific environmental claims related to SCE's previously owned San Bernardino Generating Station, divested by SCE in 1998 and reacquired as part of the Mountainview acquisition. SCE retained certain responsibilities with respect to environmental claims as part of the original divestiture of the station. The aggregate liability for either party to the purchase agreement for damages and other amounts is a maximum of $60 million. This indemnification for environmental liabilities expires on or before March 12, 2033. SCE has not recorded a liability related to this indemnity.
Mountainview Filter Cake Indemnity
SCE has indemnified the City of Redlands, California in connection with Mountainview's California Energy Commission permit for cleanup or associated actions related to groundwater contaminated by perchlorate due to the disposal of filter cake at the City's solid waste landfill. The obligations under this agreement are not limited to a specific time period or subject to a maximum liability. SCE has not recorded a liability related to this indemnity.
Other Edison International Indemnities
Edison International provides other indemnifications through contracts entered into in the normal course of business. These are primarily indemnifications against adverse litigation outcomes in connection with underwriting agreements, and indemnities for specified environmental liabilities and income taxes with respect to assets sold. Edison International's obligations under these agreements may or may not be limited in terms of time and/or amount, and in some instances Edison International may have recourse against third parties. Edison International has not recorded a liability related to these indemnities. The overall maximum amount of the obligations under these indemnifications cannot be reasonably estimated.
Contingencies
In addition to the matters disclosed in these Notes, Edison International is involved in other legal, tax and regulatory proceedings before various courts and governmental agencies regarding matters arising in the ordinary course of business. Edison International believes the outcome of these other proceedings will not materially affect its results of operations or liquidity.
Midwest Generation New Source Review and Other Litigation
In August 2009, the United States Environmental Protection Agency ("US EPA") and the State of Illinois filed a complaint in the Northern District of Illinois alleging that Midwest Generation or Commonwealth Edison performed repair or replacement projects at six Illinois coal-fired electric generating stations in violation of the Prevention of Significant Deterioration ("PSD") requirements and of the New Source Performance Standards of the Clean Air Act ("CAA"), including alleged requirements to obtain a construction permit and to install controls sufficient to meet best available control technology ("BACT") emission rates. The US EPA also alleged that Midwest Generation and Commonwealth Edison violated certain operating permit requirements under Title V of the CAA. Finally, the US EPA alleged violations of certain opacity and particulate matter standards at the Midwest Generation plants. In addition to seeking penalties ranging from $25,000 to $37,500 per violation, per day, the complaint called for an injunction ordering Midwest Generation to install controls sufficient to meet BACT emission rates at all units subject to the complaint; and other remedies. The remedies sought by the plaintiffs in the lawsuit could go well beyond the requirements of the Combined Pollutant Standard ("CPS"). Several Chicago-based environmental action groups intervened in the case.
Nine of ten PSD claims have been dismissed, along with claims related to alleged violations of Title V of the CAA to the extent based on the dismissed PSD claims. The court has also dismissed all claims asserted against Commonwealth Edison and EME. The court denied a motion to dismiss a claim by the Chicago-based environmental action groups for civil penalties in the remaining PSD claim, but noted that the plaintiffs will be required to convince the court that the statute of limitations should be equitably tolled. The court did not address other counts in the complaint that allege violations of opacity and particulate matter limitations under the Illinois State Implementation Plan and Title V of the CAA. The dismissals have been certified as “partial final judgments” capable of appeal, and an appeal is pending before the Seventh Circuit Court of Appeals. The remaining claims are stayed pending the appeal.
In January 2012, two complaints were filed against Midwest Generation in Illinois state court by residents living near the Crawford and Fisk Stations on behalf of themselves and all others similarly situated, each asserting claims of nuisance, negligence, trespass, and strict liability. The plaintiffs seek to have their suits certified as a class action and request injunctive relief, as well as compensatory and punitive damages. The complaints are similar to two complaints previously filed in the Northern District of Illinois, which were dismissed in October 2011 for lack of federal jurisdiction.
Adverse decisions in these cases could involve penalties, remedial actions and damages that could have a material impact on the financial condition and results of operations of Midwest Generation and EME. EME cannot predict the outcome of these matters or estimate the impact on the Midwest Generation plants, or its and Midwest Generation's results of operations, financial position or cash flows. EME has not recorded a liability for this matter.
Homer City New Source Review and Other Litigation
In January 2011, the US EPA filed a complaint in the Western District of Pennsylvania against Homer City, the sale-leaseback owner participants of the Homer City plant, and two prior owners of the Homer City plant. The complaint alleged violations of the PSD and Title V provisions of the CAA, as a result of projects in the 1990s performed by prior owners without PSD permits and the subsequent failure to incorporate emissions limitations that meet BACT into the station's Title V operating permit. In addition to seeking penalties ranging from $32,500 to $37,500 per violation, per day, the complaint called for an injunction ordering Homer City to install controls sufficient to meet BACT emission rates at all units subject to the complaint and for other remedies. The Pennsylvania Department of Environmental Protection, the State of New York and the State of New Jersey intervened in the lawsuit. In October 2011, all of the claims in the US EPA's lawsuit were dismissed with prejudice. An appeal of the dismissal is pending before the Third Circuit Court of Appeals.
Also in January 2011, two residents filed a complaint in the Western District of Pennsylvania, on behalf of themselves and all others similarly situated, against Homer City, the sale-leaseback owner participants of the Homer City plant, two prior owners of the Homer City plant, EME, and Edison International, claiming that emissions from the Homer City plant had adversely affected their health and property values. The plaintiffs sought to have their suit certified as a class action and requested injunctive relief, the funding of a health assessment study and medical monitoring, as well as compensatory and punitive damages. In October 2011, the claims in the purported class action lawsuit that were based on the federal CAA were dismissed with prejudice, while state law statutory and common law claims were dismissed without prejudice to re-file in state court should the plaintiffs choose to do so. EME does not know whether the plaintiffs will file a complaint in state court.
In February 2012, Homer City received a 60-day Notice of Intent to Sue indicating the Sierra Club’s intent to file a citizen lawsuit alleging violations of emissions standards and limitations under the CAA and the Pennsylvania Air Pollution Control Act.
Adverse decisions in these cases could involve penalties, remedial actions and damages that could have a material impact on the financial condition and results of operations of Homer City and EME. EME cannot predict the outcome of these matters or estimate the impact on the Homer City plant, or its and Homer City's results of operations, financial position or cash flows. EME has not recorded a liability for this matter.
CPSD Investigations
San Gabriel Valley Windstorm Investigation
In November 2011, a windstorm resulted in significant damage to SCE’s electric system and service outages for SCE customers primarily in the San Gabriel Valley. The CPUC directed its Consumer Protection and Safety Division (“CPSD”) to conduct an investigation focused on the cause of the outages, SCE’s service restoration effort, and SCE’s customer communications during the outages. The CPSD issued its preliminary report on February 1, 2012. The report asserts that SCE and others with whom SCE shares utility poles violated certain CPUC safety rules applicable to overhead line construction, maintenance and operation, which may have caused the failures of affected poles and supporting cables. The report also concludes that SCE’s restoration time was not adequate and makes other assertions. Additionally, the report contends that SCE violated CPUC rules by failing to preserve evidence relevant to the investigation when it did not retain damaged poles that were replaced following the windstorm. If the CPUC issues an Order Instituting Investigation ("OII") regarding this matter and SCE is found to have violated any CPUC rules, it could face penalties. In addition, the cost of any large scale review of poles or other equipment for safety compliance could be significant. SCE is unable to estimate a possible loss or range of loss associated with any penalties that may be imposed by the CPUC on SCE.
Malibu Fire Order Instituting Investigation
Following a 2007 wildfire in Malibu, California, the CPUC issued an OII to determine if any statutes, CPUC general orders, rules or regulations were violated by SCE or telecomm providers (“OII Respondents”) that shared the use of three failed power poles in the wildfire area. The CPSD has alleged, among other things, that the poles were overloaded, that the OII Respondents violated the CPUC's rules governing the design, construction and inspection of poles and misled the CPUC during its investigation of the fire, and that SCE failed to preserve evidence relevant to the investigation. In October 2011, the CPSD proposed that the OII Respondents be assessed penalties of approximately $99 million, with SCE being allocated approximately $50 million of the total. SCE has denied the allegations and believes the proposed penalties are excessive.
Four Corners New Source Review Litigation
In October 2011, four private environmental organizations filed a CAA citizen lawsuit against the co-owners of Four Corners. The complaint alleges that certain work performed at the Four Corners generating units 4 and 5, over the approximate periods of 1985-1986 and 2007-present, constituted plant “major modifications” for which the plant should have, but did not, obtain permits and install BACT in violation of the PSD requirements and of the New Source Performance Standards of the CAA. The complaint also alleges subsequent and continuing violation of BACT air emissions limits. The lawsuit seeks injunctive and declaratory relief, civil penalties, including a mitigation project and litigation costs. In November 2010, SCE entered into an agreement to sell its ownership interest in generating units 4 and 5 to APS. The sale is subject to regulatory approvals and is expected to close in late 2012. Under the agreement SCE would remain responsible for its pro rata share of certain environmental liabilities, including penalties arising from environmental violations prior to the sale, but SCE would not be liable for any costs of installing BACT or other costs related to continuing or extending Four Corners operations. SCE is unable to estimate a possible loss or range of loss associated with this matter.
Concurrently, the US EPA has proposed a regional haze federal implementation plan based on an APS proposal that would require shut down of units 1, 2 and 3 by 2016 and the installation of selective catalytic reduction technology on units 4 and 5 by 2018. APS' proposal contemplated that these actions would both satisfy the federal regional haze requirements and resolve any New Source Review claims the US EPA might have. A final federal implementation plan is expected in 2012.
Environmental Remediation
Edison International records its environmental remediation liabilities when site assessments and/or remedial actions are probable and a range of reasonably likely cleanup costs can be estimated. Edison International reviews its sites and measures the liability quarterly, by assessing a range of reasonably likely costs for each identified site using currently available information, including existing technology, presently enacted laws and regulations, experience gained at similar sites, and the probable level of involvement and financial condition of other potentially responsible parties. These estimates include costs for site investigations, remediation, operations and maintenance, monitoring and site closure. Unless there is a single probable amount, Edison International records the lower end of this reasonably likely range of costs (reflected in "Other long-term liabilities") at undiscounted amounts as timing of cash flows is uncertain.
At December 31, 2011, Edison International's recorded estimated minimum liability to remediate its 26 identified material sites (sites in which the upper end of the range of the costs is at least $1 million) at SCE (24 sites) and EMG (2 sites related to Midwest Generation) was $56 million, of which $49 million was related to SCE, including $14 million related to San Onofre. In addition to its identified material sites, SCE also has 33 immaterial sites for which the total minimum recorded liability was $3 million. Of the $52 million total environmental remediation liability for SCE, $49 million has been recorded as a regulatory asset. SCE expects to recover $31 million through an incentive mechanism that allows SCE to recover 90% of its environmental remediation costs at certain sites (SCE may request to include additional sites) and $18 million through a mechanism that allows SCE to recover 100% of the costs incurred at certain sites through customer rates. Edison International's identified sites include several sites for which there is a lack of currently available information, including the nature and magnitude of contamination, and the extent, if any, that Edison International may be held responsible for contributing to any costs incurred for remediating these sites. Thus, no reasonable estimate of cleanup costs can be made for these sites.
The ultimate costs to clean up Edison International's identified sites may vary from its recorded liability due to numerous uncertainties inherent in the estimation process, such as: the extent and nature of contamination; the scarcity of reliable data for identified sites; the varying costs of alternative cleanup methods; developments resulting from investigatory studies; the possibility of identifying additional sites; and the time periods over which site remediation is expected to occur. Edison International believes that, due to these uncertainties, it is reasonably possible that cleanup costs at the identified material sites and immaterial sites could exceed its recorded liability by up to $197 million and $6 million, respectively, all of which is related to SCE. The upper limit of this range of costs was estimated using assumptions least favorable to Edison International among a range of reasonably possible outcomes.
SCE expects to clean up its identified sites over a period of up to 30 years. Remediation costs in each of the next five years are expected to range from $7 million to $17 million. Costs incurred for the years ended December 31, 2011, 2010 and 2009 were $16 million, $17 million and $11 million, respectively.
Based upon the CPUC's regulatory treatment of environmental remediation costs incurred at SCE, Edison International believes that costs ultimately recorded will not materially affect its results of operations, financial position or cash flows. There can be no assurance, however, that future developments, including additional information about existing sites or the identification of new sites, will not require material revisions to estimates.
Nuclear Insurance
Federal law limits public liability claims from a nuclear incident to the amount of available financial protection, which is currently approximately $12.6 billion. SCE and other owners of San Onofre and Palo Verde have purchased the maximum private primary insurance available ($375 million). The balance is covered by a loss sharing program among nuclear reactor licensees. If a nuclear incident at any licensed reactor in the United States results in claims and/or costs which exceed the primary insurance at that plant site, all nuclear reactor licensees could be required to contribute their share of the liability in the form of a deferred premium.
Based on its ownership interests, SCE could be required to pay a maximum of approximately $235 million per nuclear incident. However, it would have to pay no more than approximately $35 million per incident in any one year. If the public liability limit above is insufficient, federal law contemplates that additional funds may be appropriated by Congress. This could include an additional assessment on all licensed reactor operators as a measure for raising further federal revenue.
Property damage insurance covers losses up to $500 million, including decontamination costs, at San Onofre and Palo Verde. Decontamination liability and excess property damage coverage exceeding the primary $500 million also has been purchased in amounts greater than the federal requirement of a minimum of approximately $1.1 billion. Property damage insurance also covers damages caused by acts of terrorism up to specified limits. Additional insurance covers part of replacement power expenses during an accident-related nuclear unit outage. A mutual insurance company owned by entities with nuclear facilities issues these policies. If losses at any nuclear facility covered by the arrangement were to exceed the accumulated funds for these insurance programs, SCE could be assessed retrospective premium adjustments of up to approximately $48 million per year. Insurance premiums are charged to operating expense.
Wildfire Insurance
Severe wildfires in California have given rise to large damage claims against California utilities for fire-related losses alleged to be the result of the failure of electric and other utility equipment. Invoking a California Court of Appeal decision, plaintiffs pursuing these claims have relied on the doctrine of inverse condemnation, which can impose strict liability (including liability for a claimant's attorneys' fees) for property damage. On September 1, 2011, SCE's parent, Edison International, renewed its insurance coverage, which included coverage for SCE's wildfire liabilities up to a $575 million limit (with a self-insured retention of $10 million per wildfire occurrence). Various coverage limitations within the policies that make up the insurance coverage could result in additional self-insured costs in the event of multiple wildfire occurrences during the policy period (September 1, 2011 to August 31, 2012). SCE may experience coverage reductions and/or increased insurance costs in future years. No assurance can be given that future losses will not exceed the limits of SCE's insurance coverage.
Spent Nuclear Fuel
Under federal law, the Department of Energy ("DOE") is responsible for the selection and construction of a facility for the permanent disposal of spent nuclear fuel and high-level radioactive waste. The DOE did not meet its contractual obligation to begin acceptance of spent nuclear fuel by January 31, 1998. Extended delays by the DOE have led to the construction of costly alternatives and associated siting and environmental issues. Currently, both San Onofre and Palo Verde have interim storage for spent nuclear fuel on site sufficient for the current license period.
In June 2010, the United States Court of Federal Claims issued a decision granting SCE and the San Onofre co-owners damages of approximately $142 million to recover costs incurred through December 31, 2005 for the DOE's failure to meet its obligation to begin accepting spent nuclear fuel from San Onofre. SCE received payment from the federal government in the amount of the damage award in November 2011. SCE has returned to the San Onofre co-owners their respective share of the damage award paid. SCE, as operating agent, filed a lawsuit against the DOE in the Court of Federal Claims in December 2011 seeking damages for the period from January 1, 2006 to December 31, 2010 for the DOE's failure to meet its obligation to begin accepting spent nuclear fuel. Additional legal action would be necessary to recover damages incurred after December 31, 2010. Any damages recovered by SCE are subject to CPUC review as to what amounts would be returned to SCE customers or used to offset past or future fuel decommissioning or storage costs for the benefit of customers.