Schedule of Current Base Rate Increase Requisition to Increase Annual Revenue

The following table shows, for each of PHI’s utility subsidiaries, the electric distribution base rate cases currently pending. Additional information concerning the filing is provided in the discussion below.

 

Jurisdiction/Company

   Requested Revenue
Requirement Increase
     Requested Return
on Equity
    Filing
Date
   Expected Timing
of Decision
     (millions of dollars)                  

NJ – ACE

   $  61.7         10.25   March 14, 2014    Q1, 2015
Schedule of Current Base Rate Approval to Increase Annual Revenue

The following table shows, for each of PHI’s utility subsidiaries, the distribution base rate cases completed to date in 2014. Additional information concerning each of these cases is provided in the discussion below.

 

Jurisdiction/Company

   Approved Revenue
Requirement Increase
     Approved Return
on Equity
    Completion
Date
   Rate Effective
Date
     (millions of dollars)                  

DC – Pepco

   $  23.4         9.40   March 26, 2014    April 16, 2014

DE – DPL (Electric)

   $  15.1         9.70   April 2, 2014    May 1, 2014

MD – Pepco

   $  8.8         9.62   July 2, 2014    July 4, 2014