XML 67 R25.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments And Contingencies
12 Months Ended
Dec. 31, 2012
Commitments And Contingencies

(16) COMMITMENTS AND CONTINGENCIES

General Litigation and Other Matters

In 1993, Pepco was served with Amended Complaints filed in the state Circuit Courts of Prince George’s County, Baltimore City and Baltimore County, Maryland in separate ongoing, consolidated proceedings known as “In re: Personal Injury Asbestos Case.” Pepco and other corporate entities were brought into these cases on a theory of premises liability. Under this theory, the plaintiffs argued that Pepco was negligent in not providing a safe work environment for employees or its contractors, who allegedly were exposed to asbestos while working on Pepco’s property. Initially, a total of approximately 448 individual plaintiffs added Pepco to their complaints. While the pleadings were not entirely clear, it appeared that each plaintiff sought $2 million in compensatory damages and $4 million in punitive damages from each defendant. In the intervening years, most of the cases were voluntarily dismissed by the plaintiffs prior to their respective trial dates. At the beginning of the first quarter of 2012, there were approximately 90 cases pending against Pepco in the Maryland State Courts (excluding those tendered to Mirant Corporation (Mirant) for defense and indemnification in connection with the sale by Pepco of its generation assets to Mirant in 2000), with an aggregate amount of monetary damages sought of approximately $360 million. In March 2012, the parties to these consolidated proceedings (each represented by the same law firm) filed a stipulation of dismissal, by which the plaintiffs voluntarily dismissed Pepco as a defendant, eliminating any reasonably possible liability Pepco may have had with respect to these proceedings.

In September 2011, an asbestos complaint was filed in the New Jersey Superior Court, Law Division, against ACE (among other defendants) asserting claims under New Jersey’s Wrongful Death and Survival statutes. The complaint, filed by the estate of a decedent who was the wife of a former employee of ACE, alleges that the decedent’s mesothelioma was caused by exposure to asbestos brought home by her husband on his work clothes. New Jersey courts have recognized a cause of action against a premise owner in a so-called “take home” case if it can be shown that the harm was foreseeable. In this case, the complaint seeks recovery of an unspecified amount of damages for, among other things, the decedent’s past medical expenses, loss of earnings, and pain and suffering between the time of injury and death, and asserts a punitive damage claim. At this time, ACE has concluded that a loss is reasonably possible with respect to this matter, but ACE was unable to estimate an amount or range of reasonably possible loss because (i) the damages sought are indeterminate, (ii) the proceedings are in the early stages, and (iii) the matter involves facts that ACE believes are distinguishable from the facts of the “take-home” cause of action recognized by the New Jersey courts. A trial date has been set for May 20, 2013.

During 2012, Pepco Energy Services received letters on behalf of two school districts in Maryland, which claim that invoices in connection with electricity supply contracts contained certain allegedly unauthorized charges, totaling approximately $7 million. The letters also claim compounded interest totaling an additional approximately $9 million. Pepco Energy Services disputes both the allegations regarding unauthorized charges and the claims of entitlement to compounded interest in their entirety, and has been in discussions with the school districts to attempt to resolve these claims. No litigation involving Pepco Energy Services related to these claims has commenced. At this time, Pepco Energy Services has concluded that a loss is reasonably possible with respect to this matter, but Pepco Energy Services cannot estimate an amount or range of reasonably possible loss associated with these claims because the discussions with the school districts are in the early stages.

Environmental Matters

PHI, through its subsidiaries, is subject to regulation by various federal, regional, state and local authorities with respect to the environmental effects of its operations, including air and water quality control, solid and hazardous waste disposal and limitations on land use. Although penalties assessed for violations of environmental laws and regulations are not recoverable from customers of PHI’s utility subsidiaries, environmental clean-up costs incurred by Pepco, DPL and ACE generally are included by each company in its respective cost of service for ratemaking purposes. The total accrued liabilities for the environmental contingencies described below of PHI and its subsidiaries at December 31, 2012 are summarized as follows:

 

            Legacy Generation         
     Transmission
and Distribution
     Regulated     Non-
Regulated
     Other      Total  
     (millions of dollars)  

Beginning balance as of January 1

   $ 15       $ 8     $ 5       $ 2       $ 30  

Accruals

     —           —         —           —           —     

Payments

     —          (1     —           —           (1
  

 

 

    

 

 

   

 

 

    

 

 

    

 

 

 

Ending balance as of December 31

     15        7       5        2         29  

Less amounts in Other current liabilities

     2        2       —           2         6  
  

 

 

    

 

 

   

 

 

    

 

 

    

 

 

 

Amounts in Other deferred credits

   $ 13      $ 5     $ 5      $  —         $ 23  
  

 

 

    

 

 

   

 

 

    

 

 

    

 

 

 

Conectiv Energy Wholesale Power Generation Sites

In July 2010, PHI sold the Conectiv Energy wholesale power generation business to Calpine. Under New Jersey’s Industrial Site Recovery Act (ISRA), the transfer of ownership triggered an obligation on the part of Conectiv Energy to remediate any environmental contamination at each of the nine Conectiv Energy generating facility sites located in New Jersey. Under the terms of the sale, Calpine has assumed responsibility for performing the ISRA-required remediation and for the payment of all related ISRA compliance costs up to $10 million. PHI is obligated to indemnify Calpine for any ISRA compliance remediation costs in excess of $10 million. According to preliminary estimates, the costs of ISRA-required remediation activities at the nine generating facility sites located in New Jersey are in the range of approximately $7 million to $18 million. The amount accrued by PHI for the ISRA-required remediation activities at the nine generating facility sites is included in the table above in the column entitled “Legacy Generation – Non-Regulated.”

In September 2011, PHI received a request for data from the U.S. Environmental Protection Agency (EPA) regarding operations at the Deepwater generating facility in New Jersey (which was included in the sale to Calpine) between February 2004 and July 1, 2010, to demonstrate compliance with the Clean Air Act’s new source review permitting program. PHI responded to the data request. Under the terms of the Calpine sale, PHI is obligated to indemnify Calpine for any failure of PHI, on or prior to the closing date of the sale, to comply with environmental laws attributable to the construction of new, or modification of existing, sources of air emissions. At this time, PHI does not expect this inquiry to have a material adverse effect on its consolidated financial condition, results of operations or cash flows.

Franklin Slag Pile Site

In November 2008, ACE received a general notice letter from EPA concerning the Franklin Slag Pile site in Philadelphia, Pennsylvania, asserting that ACE is a potentially responsible party (PRP) that may have liability for clean-up costs with respect to the site and for the costs of implementing an EPA-mandated remedy. EPA’s claims are based on ACE’s sale of boiler slag from the B.L. England generating facility, then owned by ACE, to MDC Industries, Inc. (MDC) during the period June 1978 to May 1983. EPA claims that the boiler slag ACE sold to MDC contained copper and lead, which are hazardous substances under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), and that the sales transactions may have constituted an arrangement for the disposal or treatment of hazardous substances at the site, which could be a basis for liability under CERCLA. The EPA letter also states that, as of the date of the letter, EPA’s expenditures for response measures at the site have exceeded $6 million. EPA estimates the additional cost for future response measures will be approximately $6 million. ACE believes that EPA sent similar general notice letters to three other companies and various individuals.

ACE believes that the B.L. England boiler slag sold to MDC was a valuable material with various industrial applications and, therefore, the sale was not an arrangement for the disposal or treatment of any hazardous substances as would be necessary to constitute a basis for liability under CERCLA. ACE intends to contest any claims to the contrary made by EPA. In a May 2009 decision arising under CERCLA, which did not involve ACE, the U.S. Supreme Court rejected an EPA argument that the sale of a useful product constituted an arrangement for disposal or treatment of hazardous substances. While this decision supports ACE’s position, at this time ACE cannot predict how EPA will proceed with respect to the Franklin Slag Pile site, or what portion, if any, of the Franklin Slag Pile site response costs EPA would seek to recover from ACE. Costs to resolve this matter are not expected to be material and are expensed as incurred.

Peck Iron and Metal Site

EPA informed Pepco in a May 2009 letter that Pepco may be a PRP under CERCLA with respect to the cleanup of the Peck Iron and Metal site in Portsmouth, Virginia, and for costs EPA has incurred in cleaning up the site. The EPA letter states that Peck Iron and Metal purchased, processed, stored and shipped metal scrap from military bases, governmental agencies and businesses and that Peck’s metal scrap operations resulted in the improper storage and disposal of hazardous substances. EPA bases its allegation that Pepco arranged for disposal or treatment of hazardous substances sent to the site on information provided by former Peck Iron and Metal personnel, who informed EPA that Pepco was a customer at the site. Pepco has advised EPA by letter that its records show no evidence of any sale of scrap metal by Pepco to the site. Even if EPA has such records and such sales did occur, Pepco believes that any such scrap metal sales may be entitled to the recyclable material exemption from CERCLA liability. In a Federal Register notice published on November 4, 2009, EPA placed the Peck Iron and Metal site on the National Priorities List. The National Priorities List, among other things, serves as a guide to EPA in determining which sites warrant further investigation to assess the nature and extent of the human health and environmental risks associated with a site. In September 2011, EPA initiated a remedial investigation/feasibility study (RI/FS) using federal funds. Pepco cannot at this time estimate an amount or range of reasonably possible loss associated with the RI/FS, any remediation activities to be performed at the site or any other costs that EPA might seek to impose on Pepco.

Ward Transformer Site

In April 2009, a group of PRPs with respect to the Ward Transformer site in Raleigh, North Carolina, filed a complaint in the U.S. District Court for the Eastern District of North Carolina, alleging cost recovery and/or contribution claims against a number of entities, including ACE, DPL and Pepco, based on their alleged sale of transformers to Ward Transformer, with respect to past and future response costs incurred by the PRP group in performing a removal action at the site. In a March 2010 order, the court denied the defendants’ motion to dismiss. The litigation is moving forward with certain “test case” defendants (not including ACE, DPL and Pepco) filing summary judgment motions regarding liability. The case has been stayed as to the remaining defendants pending rulings upon the test cases. In a January 31, 2013 order, the district court granted summary judgment for the test case defendant whom plaintiffs alleged was liable based on its sale of transformers to Ward Transformer. The district court’s order addresses only the liability of the test case defendant. PHI has concluded that a loss is reasonably possible with respect to this matter, but PHI was unable to estimate an amount or range of reasonably possible losses to which it may be exposed. PHI does not believe that any of its three utility subsidiaries had extensive business transactions, if any, with the Ward Transformer site.

Benning Road Site

In September 2010, PHI received a letter from EPA stating that EPA and the District of Columbia Department of the Environment (DDOE) have identified the Benning Road location, consisting of a generation facility operated by Pepco Energy Services until the facility was deactivated in June 2012, and a transmission and distribution facility operated by Pepco, as one of six land-based sites potentially contributing to contamination of the lower Anacostia River. The letter stated that the principal contaminants of concern are polychlorinated biphenyls and polycyclic aromatic hydrocarbons. In December 2011, the U.S. District Court for the District of Columbia approved a consent decree entered into by Pepco and Pepco Energy Services with DDOE, which requires Pepco and Pepco Energy Services to conduct a RI/FS for the Benning Road site and an approximately 10-15 acre portion of the adjacent Anacostia River. The RI/FS will form the basis for DDOE’s selection of a remedial action for the Benning Road site and for the Anacostia River sediment associated with the site. The consent decree does not obligate Pepco or Pepco Energy Services to pay for or perform any remediation work, but it is anticipated that DDOE will look to the companies to assume responsibility for cleanup of any conditions in the river that are determined to be attributable to past activities at the Benning Road site. The court order entering the consent decree requires the parties to submit a written status report to the court on May 24, 2013 regarding the implementation of the requirements of the consent decree and any related plans for remediation. In addition, if the RI/FS has not been completed by May 24, 2013, the status report must provide an explanation and a showing of good cause for why the work has not been completed.

Pepco and Pepco Energy Services submitted a proposed RI/FS work plan in July 2012, and filed a revised work plan in December 2012 based on comments from DDOE and the public. DDOE approved the revised work plan on December 28, 2012 and RI/FS field work commenced in January 2013.

The remediation costs accrued for this matter are included in the table above in the columns entitled “Transmission and Distribution,” “Legacy Generation – Regulated,” and “Legacy Generation – Non-Regulated.”

Indian River Oil Release

In 2001, DPL entered into a consent agreement with the Delaware Department of Natural Resources and Environmental Control for remediation, site restoration, natural resource damage compensatory projects and other costs associated with environmental contamination resulting from an oil release at the Indian River generating facility, which was sold in June 2001. The amount of remediation costs accrued for this matter is included in the table above in the column entitled “Legacy Generation – Regulated.”

Potomac River Mineral Oil Release

In January 2011, a coupling failure on a transformer cooler pipe resulted in a release of non-toxic mineral oil at Pepco’s Potomac River substation in Alexandria, Virginia. An overflow of an underground secondary containment reservoir resulted in approximately 4,500 gallons of mineral oil flowing into the Potomac River.

The release falls within the regulatory jurisdiction of multiple federal and state agencies. Beginning in March 2011, DDOE issued a series of compliance directives requiring Pepco to prepare an incident report, provide certain records, and prepare and implement plans for sampling surface water and river sediments and assessing ecological risks and natural resources damages. Pepco completed field sampling during the fourth quarter of 2011 and submitted sampling results to DDOE during the second quarter of 2012. Pepco is continuing discussions with DDOE regarding the need for any further response actions but expects that additional monitoring of shoreline sediments may be required.

In June 2012, Pepco commenced discussions with DDOE regarding a possible consent decree that would resolve DDOE’s threatened claims for civil penalties for alleged violation of the District’s Water Pollution Control Law, as well as for damages to natural resources. Pepco and DDOE have reached an agreement in principle that would consist of a combination of a civil penalty and Supplemental Environmental Projects (SEPs) with a total cost to Pepco of approximately $1 million. Discussions with DDOE continue regarding the specific nature and scope of the SEPs, as well as the amount of DDOE’s and the federal resource trustees’ natural resource damage claim. This matter is expected to be resolved through the entry of a consent decree sometime in 2013. Based on discussions to date, PHI and Pepco do not believe that the resolution of these claims will have a material adverse effect on their respective financial conditions, results of operations or cash flows.

In March 2011, the Virginia Department of Environmental Quality (VADEQ) requested documentation regarding the release and the preparation of an emergency response report, which Pepco submitted to the agency in April 2011. In March 2011, Pepco received a notice of violation from VADEQ and in December 2011, entered into a consent decree with VADEQ, pursuant to which Pepco paid a civil penalty of approximately $40,000. The U.S. Coast Guard assessed a $5,000 penalty against Pepco for the release of oil into the waters of the United States, which Pepco has paid.

During March 2011, EPA conducted an inspection of the Potomac River substation to review compliance with federal regulations regarding Spill Prevention, Control, and Countermeasure (SPCC) plans for facilities using oil-containing equipment in proximity to surface waters. EPA identified several potential violations of the SPCC regulations relating to SPCC plan content, recordkeeping, and secondary containment. As a result of the oil release, Pepco submitted a revised SPCC plan to EPA in August 2011 and implemented certain interim operational changes to the secondary containment systems at the facility which involve pumping accumulated storm water to an aboveground holding tank for off-site disposal. In December 2011, Pepco completed the installation of a treatment system designed to allow automatic discharge of accumulated storm water from the secondary containment system. Pepco currently is seeking DDOE’s and EPA’s approval to commence operation of the new system and, after receiving such approval, will submit a further revised SPCC plan to EPA. In the meantime, Pepco is continuing to use the aboveground holding tank to manage storm water from the secondary containment system. In April 2012, EPA advised Pepco that it is not seeking civil penalties at this time for alleged non-compliance with SPCC regulations.

The amounts accrued for these matters are included in the table above in the column entitled “Transmission and Distribution.”

Fauquier County Landfill Site

In October 2011, Pepco Energy Services received a notice of violation from the VADEQ, which advised Pepco Energy Services of information on which VADEQ may rely to institute an administrative or judicial enforcement action in connection with alleged violation of Virginia air pollution control laws and regulations at the facility of Pepco Energy Services’ subsidiary Fauquier County Landfill Gas, L.L.C. in Warrenton, Virginia. The notice of violation was based on an on-site VADEQ inspection during which VADEQ observed certain alleged deficiencies relating to the facility’s permit to construct and operate. In February 2012, Pepco Energy Services signed a proposed consent order sent by VADEQ, pursuant to which Pepco Energy Services agreed to perform certain remedial actions and agreed to pay a civil charge of approximately $10,000.

PHI’s Cross-Border Energy Lease Investments

As discussed in Note (8), “Leasing Activities,” PHI has a portfolio of cross-border energy lease investments involving public utility assets located outside of the United States with a net investment value of approximately $1.2 billion as of December 31, 2012. Each of these investments is comprised of multiple leases and each investment is structured as a sale and leaseback transaction commonly referred to by the IRS as a sale-in, lease-out, or SILO, transaction.

Since 2005, PHI’s cross-border energy lease investments have been under examination by the IRS as part of the PHI federal income tax audits. In connection with the audit of PHI’s 2001-2002 income tax returns, the IRS disallowed the depreciation and interest deductions in excess of rental income claimed by PHI for six of the eight lease investments and, in connection with the audits of PHI’s 2003-2005 and 2006-2008 income tax returns, the IRS disallowed such deductions in excess of rental income for all eight of the lease investments. In addition, the IRS has sought to recharacterize each of the leases as a loan transaction in each of the years under audit as to which PHI would be subject to original issue discount income. PHI has disagreed with the IRS’ proposed adjustments to the 2001-2008 income tax returns and has filed protests of these findings for each year with the Office of Appeals of the IRS. In November 2010, PHI entered into a settlement agreement with the IRS for the 2001 and 2002 tax years solely for the purpose of commencing litigation associated with this matter and subsequently filed refund claims in July 2011 for the disallowed tax deductions relating to the leases for these years. In January 2011, as part of this settlement, PHI paid $74 million of additional tax for 2001 and 2002, penalties of $1 million, and $28 million in interest associated with the disallowed deductions. Since the July 2011 refund claims were not approved by the IRS within the statutory six-month period, in January 2012 PHI filed complaints in the U.S. Court of Federal Claims seeking recovery of the tax payment, interest and penalties. The 2003-2005 and 2006-2008 income tax return audits continue to be in process with the IRS Office of Appeals and the IRS case manager, respectively, and are not presently a part of the U.S. Court of Federal Claims litigation discussed above.

PHI’s current annual tax benefits from these lease investments are approximately $43 million. After taking into consideration the $74 million paid with the 2001-2002 audit (as discussed above), the net federal and state tax benefits received for the remaining leases from January 1, 2001, the earliest year that remains open to audit, to December 31, 2012, has been approximately $489 million. In the event that the IRS were to be successful in disallowing 100% of the tax benefits associated with these lease investments and recharacterizing these lease investments as loans, PHI estimates that, as of December 31, 2012, it would be obligated to pay approximately $600 million in additional federal and state taxes (net of the $74 million tax payment described above) and approximately $144 million of interest on the remaining leases. These amounts have been estimated without consideration of certain tax benefits arising from matters unrelated to the leases that would offset the taxes and interest due, including PHI’s best estimate of the expected resolution of other uncertain and effectively settled tax positions, the carrying back and carrying forward of any existing net operating losses, and the application of certain amounts on deposit with the IRS. After consideration of these benefits, PHI would be obligated to pay between $170 million and $200 million in additional federal and state taxes and between $50 million and $60 million of interest on the additional federal and state taxes as of March 31, 2013. In addition, the IRS could require PHI to pay a penalty of up to 20% of the amount of additional taxes due.

See Note (20), “Subsequent Event,” for further information on PHI’s cross-border energy lease investments.

District of Columbia Tax Legislation

In 2011, the Council of the District of Columbia approved the Budget Support Act which requires that corporate taxpayers in the District of Columbia calculate taxable income allocable or apportioned to the District of Columbia by reference to the income and apportionment factors applicable to commonly controlled entities organized within the United States that are engaged in a unitary business. In the aggregate, this new tax reporting method reduced pre-tax earnings for the year ended December 31, 2011 by $7 million ($5 million after-tax) as further discussed in Note (8), “Leasing Activities,” and Note (12), “Income Taxes.” During 2012, the District of Columbia Office of Tax and Revenue adopted regulations to implement this reporting method. PHI has analyzed these regulations and determined that the regulations did not impact PHI’s results of operations for the year ended December 31, 2012.

Third Party Guarantees, Indemnifications, and Off-Balance Sheet Arrangements

PHI and certain of its subsidiaries have various financial and performance guarantees and indemnification obligations that they have entered into in the normal course of business to facilitate commercial transactions with third parties as discussed below.

As of December 31, 2012, PHI and its subsidiaries were parties to a variety of agreements pursuant to which they were guarantors for standby letters of credit, energy procurement obligations, and other commitments and obligations. The commitments and obligations, in millions of dollars, were as follows:

 

     Guarantor  
     PHI      Pepco      DPL      ACE      Total  

Energy procurement obligations of Pepco Energy Services (a)

   $ 90      $  —        $  —        $  —        $ 90  

Guarantees associated with disposal of Conectiv Energy assets (b)

     13        —          —          —          13  

Guaranteed lease residual values (c)

     2        5        6        4        17  
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

Total

   $ 105       $ 5      $ 6      $ 4      $ 120  
  

 

 

    

 

 

    

 

 

    

 

 

    

 

 

 

 

(a) PHI has contractual commitments for performance and related payments of Pepco Energy Services to counterparties under routine energy sales and procurement obligations.
(b) Represents guarantees by PHI of Conectiv Energy’s derivatives portfolio transferred in connection with the disposition of Conectiv Energy’s wholesale business. The derivative portfolio guarantee is currently $13 million and covers Conectiv Energy’s performance prior to the assignment. This guarantee will remain in effect until the end of 2015.
(c) Represents the maximum potential obligation in the event that the fair value of certain leased equipment and fleet vehicles is zero at the end of the maximum lease term. The maximum lease term associated with these assets ranges from 3 to 8 years. The maximum potential obligation at the end of the minimum lease term would be $54 million, $9 million of which is a guaranty by PHI, $15 million by Pepco, $18 million by DPL and $12 million by ACE. The minimum lease term associated with these assets ranges from 1 to 4 years. Historically, payments under the guarantees have not been made and PHI believes the likelihood of payments being required under the guarantees is remote.

PHI and certain of its subsidiaries have entered into various indemnification agreements related to purchase and sale agreements and other types of contractual agreements with vendors and other third parties. These indemnification agreements typically cover environmental, tax, litigation and other matters, as well as breaches of representations, warranties and covenants set forth in these agreements. Typically, claims may be made by third parties under these indemnification agreements over various periods of time depending on the nature of the claim. The maximum potential exposure under these indemnification agreements can range from a specified dollar amount to an unlimited amount depending on the nature of the claim and the particular transaction. The total maximum potential amount of future payments under these indemnification agreements is not estimable due to several factors, including uncertainty as to whether or when claims may be made under these indemnities.

Energy Services Performance Contracts

Pepco Energy Services has a diverse portfolio of energy savings services performance contracts that are associated with the installation of energy savings equipment or combined heat and power facilities for federal, state and local government customers. As part of the energy savings contracts, Pepco Energy Services typically guarantees that the equipment or systems it installs will generate a specified amount of energy savings on an annual basis over a multi-year period. As of December 31, 2012, the remaining notional amount of Pepco Energy Services’ energy savings guarantees on both completed projects and projects under construction totaled $446 million over the life of the multi-year performance contracts with the longest guarantee having a remaining term of 13 years. On an annual basis, Pepco Energy Services undertakes a measurement and verification process to determine the amount of energy savings for the year and whether there is any shortfall in the annual energy savings compared to the guaranteed amount.

As of December 31, 2012, Pepco Energy Services had a performance guarantee contract associated with the production at a combined heat and power facility that is under construction totaling $15 million in notional value over the life of the multi-year contracts, with the longest guarantee having a remaining term of 20 years.

Pepco Energy Services recognizes a liability for the value of the estimated energy savings or production shortfalls when it is probable that the guaranteed amounts will not be achieved and the amount is reasonably estimable. As of December 31, 2012, Pepco Energy Services had an accrued liability of $1 million for its energy savings or combined heat and power performance contracts that it established during 2012. There was no significant change in the type of contracts issued during the year ended December 31, 2012 as compared to the year ended December 31, 2011.

Dividends

On January 24, 2013, Pepco Holdings’ Board of Directors declared a dividend on common stock of 27 cents per share payable March 28, 2013, to stockholders of record on March 11, 2013.

Contractual Obligations

As of December 31, 2012, Pepco Holdings’ contractual obligations under non-derivative fuel and purchase power contracts were $355 million in 2013, $707 million in 2014 to 2015, $653 million in 2016 to 2017, and $1,911 million in 2018 and thereafter.

Potomac Electric Power Co [Member]
 
Commitments And Contingencies

(13) COMMITMENTS AND CONTINGENCIES

General Litigation

In 1993, Pepco was served with Amended Complaints filed in the state Circuit Courts of Prince George’s County, Baltimore City and Baltimore County, Maryland in separate ongoing, consolidated proceedings known as “In re: Personal Injury Asbestos Case.” Pepco and other corporate entities were brought into these cases on a theory of premises liability. Under this theory, the plaintiffs argued that Pepco was negligent in not providing a safe work environment for employees or its contractors, who allegedly were exposed to asbestos while working on Pepco’s property. Initially, a total of approximately 448 individual plaintiffs added Pepco to their complaints. While the pleadings were not entirely clear, it appeared that each plaintiff sought $2 million in compensatory damages and $4 million in punitive damages from each defendant. In the intervening years, most of the cases were voluntarily dismissed by the plaintiffs prior to their respective trial dates. At the beginning of the first quarter of 2012, there were approximately 90 cases pending against Pepco in the Maryland State Courts (excluding those tendered to Mirant Corporation (Mirant) for defense and indemnification in connection with the sale by Pepco of its generation assets to Mirant in 2000), with an aggregate amount of monetary damages sought of approximately $360 million. In March 2012, the parties to these consolidated proceedings (each represented by the same law firm) filed a stipulation of dismissal, by which the plaintiffs voluntarily dismissed Pepco as a defendant, eliminating any reasonably possible liability Pepco may have had with respect to these proceedings.

Environmental Matters

Pepco is subject to regulation by various federal, regional, state, and local authorities with respect to the environmental effects of its operations, including air and water quality control, solid and hazardous waste disposal, and limitations on land use. Although penalties assessed for violations of environmental laws and regulations are not recoverable from Pepco’s customers, environmental clean-up costs incurred by Pepco generally are included in its cost of service for ratemaking purposes. The total accrued liabilities for the environmental contingencies of Pepco described below at December 31, 2012 are summarized as follows:

 

    Transmission
and Distribution
    Legacy
Generation -
Regulated
        Total      
    (millions of dollars)  

Beginning balance as of January 1

  $ 14     $ 4      $ 18   

Accruals

    —          —          —     

Payments

    —          (1     (1
 

 

 

   

 

 

   

 

 

 

Ending balance as of December 31

    14       3        17   

Less amounts in Other current liabilities

    1       —          1   
 

 

 

   

 

 

   

 

 

 

Amounts in Other deferred credits

  $ 13     $ 3      $ 16   
 

 

 

   

 

 

   

 

 

 

Peck Iron and Metal Site

The U.S. Environmental Protection Agency (EPA) informed Pepco in a May 2009 letter that Pepco may be a potentially responsible party (PRP) under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) with respect to the cleanup of the Peck Iron and Metal site in Portsmouth, Virginia, and for costs EPA has incurred in cleaning up the site. The EPA letter states that Peck Iron and Metal purchased, processed, stored and shipped metal scrap from military bases, governmental agencies and businesses and that Peck’s metal scrap operations resulted in the improper storage and disposal of hazardous substances. EPA bases its allegation that Pepco arranged for disposal or treatment of hazardous substances sent to the site on information provided by former Peck Iron and Metal personnel, who informed EPA that Pepco was a customer at the site. Pepco has advised EPA by letter that its records show no evidence of any sale of scrap metal by Pepco to the site. Even if EPA has such records and such sales did occur, Pepco believes that any such scrap metal sales may be entitled to the recyclable material exemption from CERCLA liability. In a Federal Register notice published on November 4, 2009, EPA placed the Peck Iron and Metal site on the National Priorities List. The National Priorities List, among other things, serves as a guide to EPA in determining which sites warrant further investigation to assess the nature and extent of the human health and environmental risks associated with a site. In September 2011, EPA initiated a remedial investigation/feasibility study (RI/FS) using federal funds. Pepco cannot at this time estimate an amount or range of reasonably possible loss associated with the RI/FS, any remediation activities to be performed at the site or any other costs that EPA might seek to impose on Pepco.

Ward Transformer Site

In April 2009, a group of PRPs with respect to the Ward Transformer site in Raleigh, North Carolina, filed a complaint in the U.S. District Court for the Eastern District of North Carolina, alleging cost recovery and/or contribution claims against a number of entities, including Pepco, based on their alleged sale of transformers to Ward Transformer, with respect to past and future response costs incurred by the PRP group in performing a removal action at the site. In a March 2010 order, the court denied the defendants’ motion to dismiss. The litigation is moving forward with certain “test case” defendants (not including Pepco) filing summary judgment motions regarding liability. The case has been stayed as to the remaining defendants pending rulings upon the test cases. In a January 31, 2013 order, the district court granted summary judgment for the test case defendant whom plaintiffs alleged were liable based on its sale of transformers to Ward Transformer. The district court’s order addresses only the liability of the test case defendant. Pepco has concluded that a loss is reasonably possible with respect to this matter, but Pepco was unable to estimate an amount or range of reasonably possible losses to which it may be exposed. Pepco does not believe that it had extensive business transactions, if any, with the Ward Transformer site.

Benning Road Site

In September 2010, PHI received a letter from EPA stating that EPA and the District of Columbia Department of the Environment (DDOE) have identified the Benning Road location, consisting of a generation facility operated by Pepco Energy Services until the facility was deactivated in June 2012, and a transmission and distribution facility operated by Pepco, as one of six land-based sites potentially contributing to contamination of the lower Anacostia River. The letter stated that the principal contaminants of concern are polychlorinated biphenyls and polycyclic aromatic hydrocarbons. In December 2011, the U.S. District Court for the District of Columbia approved a consent decree entered into by Pepco and Pepco Energy Services with DDOE, which requires Pepco and Pepco Energy Services to conduct a RI/FS for the Benning Road site and an approximately 10-15 acre portion of the adjacent Anacostia River. The RI/FS will form the basis for DDOE’s selection of a remedial action for the Benning Road site and for the Anacostia River sediment associated with the site. The consent decree does not obligate Pepco or Pepco Energy Services to pay for or perform any remediation work, but it is anticipated that DDOE will look to the companies to assume responsibility for cleanup of any conditions in the river that are determined to be attributable to past activities at the Benning Road site. The court order entering the consent decree requires the parties to submit a written status report to the court on May 24, 2013 regarding the implementation of the requirements of the consent decree and any related plans for remediation. In addition, if the RI/FS has not been completed by May 24, 2013, the status report must provide an explanation and a showing of good cause for why the work has not been completed.

 

Pepco and Pepco Energy Services submitted a proposed RI/FS work plan in July 2012, and filed a revised work plan in December 2012 based on comments from DDOE and the public. DDOE approved the revised work plan on December 28, 2012 and RI/FS field work commenced in January 2013.

The remediation costs accrued for this matter are included in the table above in the columns entitled “Transmission and Distribution” and “Legacy Generation – Regulated.”

Potomac River Mineral Oil Release

In January 2011, a coupling failure on a transformer cooler pipe resulted in a release of non-toxic mineral oil at Pepco’s Potomac River substation in Alexandria, Virginia. An overflow of an underground secondary containment reservoir resulted in approximately 4,500 gallons of mineral oil flowing into the Potomac River.

The release falls within the regulatory jurisdiction of multiple federal and state agencies. Beginning in March 2011, DDOE issued a series of compliance directives requiring Pepco to prepare an incident report, provide certain records, and prepare and implement plans for sampling surface water and river sediments and assessing ecological risks and natural resources damages. Pepco completed field sampling during the fourth quarter of 2011 and submitted sampling results to DDOE during the second quarter of 2012. Pepco is continuing discussions with DDOE regarding the need for any further response actions but expects that additional monitoring of shoreline sediments may be required.

In June 2012, Pepco commenced discussions with DDOE regarding a possible consent decree that would resolve DDOE’s threatened claims for civil penalties for alleged violation of the District’s Water Pollution Control Law, as well as for damages to natural resources. Pepco and DDOE have reached an agreement in principle that would consist of a combination of a civil penalty and Supplemental Environmental Projects (SEPs) with a total cost to Pepco of approximately $1 million. Discussions with DDOE continue regarding the specific nature and scope of the SEPs, as well as the amount of DDOE’s and the federal resource trustees’ natural resource damage claim. This matter is expected to be resolved through the entry of a consent decree sometime in 2013. Based on discussions to date, PHI and Pepco do not believe that the resolution of these claims will have a material adverse effect on their respective financial conditions, results of operations or cash flows.

In March 2011, the Virginia Department of Environmental Quality (VADEQ) requested documentation regarding the release and the preparation of an emergency response report, which Pepco submitted to the agency in April 2011. In March 2011, Pepco received a notice of violation from VADEQ and in December 2011, entered into a consent decree with VADEQ, pursuant to which Pepco paid a civil penalty of approximately $40,000. The U.S. Coast Guard assessed a $5,000 penalty against Pepco for the release of oil into the waters of the United States, which Pepco has paid.

During March 2011, EPA conducted an inspection of the Potomac River substation to review compliance with federal regulations regarding Spill Prevention, Control, and Countermeasure (SPCC) plans for facilities using oil-containing equipment in proximity to surface waters. EPA identified several potential violations of the SPCC regulations relating to SPCC plan content, recordkeeping, and secondary containment. As a result of the oil release, Pepco submitted a revised SPCC plan to EPA in August 2011 and implemented certain interim operational changes to the secondary containment systems at the facility which involve pumping accumulated storm water to an aboveground holding tank for off-site disposal. In December 2011, Pepco completed the installation of a treatment system designed to allow automatic discharge of accumulated storm water from the secondary containment system. Pepco currently is seeking DDOE’s and EPA’s approval to commence operation of the new system and, after receiving such approval, will submit a further revised SPCC plan to EPA. In the meantime, Pepco is continuing to use the aboveground holding tank to manage storm water from the secondary containment system. In April 2012, EPA advised Pepco that it is not seeking civil penalties at this time for alleged non-compliance with SPCC regulations.

 

The amounts accrued for these matters are included in the table above in the column entitled “Transmission and Distribution.”

District of Columbia Tax Legislation

In 2011, the Council of the District of Columbia approved the Budget Support Act which requires that corporate taxpayers in the District of Columbia calculate taxable income allocable or apportioned to the District of Columbia by reference to the income and apportionment factors applicable to commonly controlled entities organized within the United States that are engaged in a unitary business. In the aggregate, this new tax reporting method reduced pre-tax earnings for the year ended December 31, 2011 by less than $1 million. During 2012, the District of Columbia Office of Tax and Revenue adopted regulations to implement this reporting method. PHI has analyzed these regulations and determined that the regulations did not impact PHI’s results of operations for the year ended December 31, 2012.

Contractual Obligations

As of December 31, 2012, Pepco had no contractual obligations under non-derivative fuel and power purchase contracts.

Delmarva Power & Light Co/De [Member]
 
Commitments And Contingencies

(15) COMMITMENTS AND CONTINGENCIES

Environmental Matters

DPL is subject to regulation by various federal, regional, state, and local authorities with respect to the environmental effects of its operations, including air and water quality control, solid and hazardous waste disposal, and limitations on land use. Although penalties assessed for violations of environmental laws and regulations are not recoverable from DPL’s customers, environmental clean-up costs incurred by DPL generally are included in its cost of service for ratemaking purposes. The total accrued liabilities for the environmental contingencies of DPL described below at December 31, 2012 are summarized as follows:

 

     Transmission and
Distribution
     Legacy
Generation -
Regulated
    Other      Total  
     (millions of dollars)  

Beginning balance as of January 1

   $ 1       $ 4     $ 2       $ 7  

Accruals

     —           —          —           —     

Payments

     —           (1     —           (1
  

 

 

    

 

 

   

 

 

    

 

 

 

Ending balance as of December 31

     1         3       2         6   

Less amounts in Other Current Liabilities

     1         1       2         4   
  

 

 

    

 

 

   

 

 

    

 

 

 

Amounts in Other Deferred Credits

   $ —         $ 2     $ —         $ 2   
  

 

 

    

 

 

   

 

 

    

 

 

 

Ward Transformer Site

In April 2009, a group of potentially responsible parties (PRPs) with respect to the Ward Transformer site in Raleigh, North Carolina, filed a complaint in the U.S. District Court for the Eastern District of North Carolina, alleging cost recovery and/or contribution claims against a number of entities, including DPL, based on their alleged sale of transformers to Ward Transformer, with respect to past and future response costs incurred by the PRP group in performing a removal action at the site. In a March 2010 order, the court denied the defendants’ motion to dismiss. The litigation is moving forward with certain “test case” defendants (not including DPL) filing summary judgment motions regarding liability. The case has been stayed as to the remaining defendants pending rulings upon the test cases. In a January 31, 2013 order, the district court granted summary judgment for the test case defendant whom plaintiffs alleged was liable based on its sale of transformers to Ward Transformer. The district court’s order addresses only the liability of the test case defendant. DPL has concluded that a loss is reasonably possible with respect to this matter, but DPL was unable to estimate an amount or range of reasonably possible losses to which it may be exposed. DPL does not believe that it had extensive business transactions, if any, with the Ward Transformer site.

Indian River Oil Release

In 2001, DPL entered into a consent agreement with the Delaware Department of Natural Resources and Environmental Control for remediation, site restoration, natural resource damage compensatory projects and other costs associated with environmental contamination resulting from an oil release at the Indian River generating facility, which was sold in June 2001. The amount of remediation costs accrued for this matter is included in the table above in the column entitled “Legacy Generation – Regulated.”

Contractual Obligations

As of December 31, 2012, DPL’s contractual obligations under non-derivative fuel and power purchase contracts were $62 million in 2013, $126 million in 2014 to 2015, $127 million in 2016 to 2017, and $293 million in 2018 and thereafter.

Atlantic City Electric Co [Member]
 
Commitments And Contingencies

(14) COMMITMENTS AND CONTINGENCIES

General Litigation

In September 2011, an asbestos complaint was filed in the New Jersey Superior Court, Law Division, against ACE (among other defendants) asserting claims under New Jersey’s Wrongful Death and Survival statutes. The complaint, filed by the estate of a decedent who was the wife of a former employee of ACE, alleges that the decedent’s mesothelioma was caused by exposure to asbestos brought home by her husband on his work clothes. New Jersey courts have recognized a cause of action against a premise owner in a so-called “take home” case if it can be shown that the harm was foreseeable. In this case, the complaint seeks recovery of an unspecified amount of damages for, among other things, the decedent’s past medical expenses, loss of earnings, and pain and suffering between the time of injury and death, and asserts a punitive damage claim. At this time, ACE has concluded that a loss is reasonably possible with respect to this matter, but ACE was unable to estimate an amount or range of reasonably possible loss because (i) the damages sought are indeterminate, (ii) the proceedings are in the early stages, and (iii) the matter involves facts that ACE believes are distinguishable from the facts of the “take-home” cause of action recognized by the New Jersey courts. A trial date has been set for May 20, 2013.

Environmental Matters

ACE is subject to regulation by various federal, regional, state and local authorities with respect to the environmental effects of its operations, including air and water quality control, solid and hazardous waste disposal and limitations on land use. Although penalties assessed for violations of environmental laws and regulations are not recoverable from ACE’s customers, environmental clean-up costs incurred by ACE generally are included in its cost of service for ratemaking purposes. The total accrued liabilities for the environmental contingencies described below of ACE at December 31, 2012 are summarized as follows:

 

     Legacy Generation
-Regulated
 
     (millions of dollars)  

Beginning balance as of January 1

   $ 1   

Accruals

     —     

Payments

     —     
  

 

 

 

Ending balance as of December 31

     1   

Less amounts in Other Current

Liabilities

     —     
  

 

 

 

Amounts in Other Deferred Credits

   $ 1   
  

 

 

 

Franklin Slag Pile Site

In November 2008, ACE received a general notice letter from the U.S Environmental Protection Agency (EPA) concerning the Franklin Slag Pile site in Philadelphia, Pennsylvania, asserting that ACE is a potentially responsible party (PRP) that may have liability for clean-up costs with respect to the site and for the costs of implementing an EPA-mandated remedy. EPA’s claims are based on ACE’s sale of boiler slag from the B.L. England generating facility, then owned by ACE, to MDC Industries, Inc. (MDC) during the period June 1978 to May 1983. EPA claims that the boiler slag ACE sold to MDC contained copper and lead, which are hazardous substances under the Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA), and that the sales transactions may have constituted an arrangement for the disposal or treatment of hazardous substances at the site, which could be a basis for liability under CERCLA. The EPA letter also states that, as of the date of the letter, EPA’s expenditures for response measures at the site have exceeded $6 million. EPA estimates the additional cost for future response measures will be approximately $6 million. ACE believes that EPA sent similar general notice letters to three other companies and various individuals.

ACE believes that the B.L. England boiler slag sold to MDC was a valuable material with various industrial applications and, therefore, the sale was not an arrangement for the disposal or treatment of any hazardous substances as would be necessary to constitute a basis for liability under CERCLA. ACE intends to contest any claims to the contrary made by EPA. In a May 2009 decision arising under CERCLA, which did not involve ACE, the U.S. Supreme Court rejected an EPA argument that the sale of a useful product constituted an arrangement for disposal or treatment of hazardous substances. While this decision supports ACE’s position, at this time ACE cannot predict how EPA will proceed with respect to the Franklin Slag Pile site, or what portion, if any, of the Franklin Slag Pile site response costs EPA would seek to recover from ACE. Costs to resolve this matter are not expected to be material and are expensed as incurred.

Ward Transformer Site

In April 2009, a group of PRPs with respect to the Ward Transformer site in Raleigh, North Carolina, filed a complaint in the U.S. District Court for the Eastern District of North Carolina, alleging cost recovery and/or contribution claims against a number of entities, including ACE, based on their alleged sale of transformers to Ward Transformer, with respect to past and future response costs incurred by the PRP group in performing a removal action at the site. In a March 2010 order, the court denied the defendants’ motion to dismiss. The litigation is moving forward with certain “test case” defendants (not including ACE) filing summary judgment motions regarding liability. The case has been stayed as to the remaining defendants pending rulings upon the test cases. In a January 31, 2013 order, the district court granted summary judgment for the test case defendant whom plaintiffs alleged was liable based on its sale of transformers to Ward Transformer. The district court’s order addresses only the liability of the test case defendant. ACE has concluded that a loss is reasonably possible with respect to this matter, but ACE was unable to estimate an amount or range of reasonably possible losses to which it may be exposed. ACE does not believe that it had extensive business transactions, if any, with the Ward Transformer site.

Contractual Obligations

As of December 31, 2012, ACE’s contractual obligations under non-derivative fuel and power purchase contracts were $213 million in 2013, $575 million in 2014 to 2015, $526 million in 2016 to 2017 and $1,618 million in 2018 and thereafter.