Commitments And Contingent Liabilities (New Generation And Development) (Details) (USD $)
In Millions, unless otherwise specified
9 Months Ended12 Months Ended9 Months Ended9 Months Ended12 Months Ended9 Months Ended
Sep. 30, 2011
Sep. 30, 2010
Dec. 31, 2011
mW
Sep. 30, 2011
Power [Member]
Period 2012-2013 [Member]
Kearny Site [Member]
PJM Interconnection Capital Additions [Member]
mW
Sep. 30, 2011
Power [Member]
Period 2013-2015 [Member]
PJM Interconnection Capital Additions [Member]
mW
Sep. 30, 2011
Power [Member]
Peach Bottom Units [Member]
Nuclear Up Rate Capital Additions [Member]
mW
Sep. 30, 2011
PSE&G [Member]
Solar Capital Additions [Member]
Sep. 30, 2011
Power [Member]
PJM Interconnection Capital Additions [Member]
Sep. 30, 2011
Power [Member]
Connecticut Capital Additions [Member]
Mar. 31, 2011
Power [Member]
Connecticut Capital Additions [Member]
mW
Sep. 30, 2011
Power [Member]
Nuclear Steam Path Capital Additions [Member]
Dec. 31, 2011
Power [Member]
Nuclear Steam Path Capital Additions [Member]
mW
Sep. 30, 2011
Power [Member]
Sep. 30, 2010
Power [Member]
Sep. 30, 2011
PSE&G [Member]
mW
cubicFeet
Sep. 30, 2010
PSE&G [Member]
Long-term Purchase Commitment [Line Items]                
Approximate amount committed$ 896    $ 400    $ 192     
Increase of MW nominal capacity after completion of upgrades     133     18    
Total expenditures to date1,4791,517   2816414899 94 530579939871
Number of MW of gas fired peaking capacity to be built   178267    130      
Number of MW of solar generation on existing utility poles being installed              40 
Number of MW of installation of solar generation on land and building              40 
Approximately amount of MW's already installed              23 
Estimated solar project cost, total264               
Estimated total cost of land and buildings owned phase189               
Number of MW of solar capacity placed into service  23             
Long term purchase commitment amount low range       250140       
Approximate amount committed-high end of range       300150       
Investment in projects, amount      $ 116