EX-99 2 c46793_ex99.htm

Exhibit 99


Public Service Enterprise Group

NYC Investor Meeting

February 14, 2007




Forward-Looking Statement

The statements contained in this communication about our and our subsidiaries’
future performance, including, without limitation, future revenues, earnings,
strategies, prospects and all other statements that are not purely historical, are
forward-looking statements for purposes of the safe harbor provisions under The
Private Securities Litigation Reform Act of 1995.  Although we believe that our
expectations are based on information currently available and on reasonable
assumptions, we can give no assurance they will be achieved.  There are a
number of risks and uncertainties that could cause actual results to differ
materially from the forward-looking statements made herein. A discussion of
some of these risks and uncertainties is contained in our Annual Report on Form
10-K and subsequent reports on Form 10-Q and Form 8-K filed with the
Securities and Exchange Commission (SEC), and available on our website:
http://www.pseg.com.    These documents address in further detail our business,
industry issues and other factors that could cause actual results to differ
materially from those indicated in this communication. In addition, any forward-
looking statements included herein represent our estimates only as of today and
should not be relied upon as representing our estimates as of any subsequent
date.  While we may elect to update forward-looking statements from time to time,
we specifically disclaim any obligation to do so, even if our estimates change,
unless otherwise required by applicable securities laws.

1


Operations

PSE&G consistently demonstrates top reliability performance

Significant improvement in nuclear operations

Regulatory

PSE&G settlement demonstrates return to constructive environment

Environmental – achieved NJ coal solution

Energy Markets

Power benefiting from higher prices and lower risk through forward hedges

Utility customers benefit from staggered BGS – another auction complete

Financial

International – reduced exposure, improved stability

Improving cash flows and credit measures

Strong earnings growth in 2007 and 2008

We have made steady progress across a variety of areas.

Our objective is to build on these results to make a
strong company even stronger.

2


Much has been accomplished since the termination of
the merger…

September  2006

October

November

December

January 2007

9/14 – Merger Termination
Announced

11/16–

PSE&G named America’s Most
Reliable Electric Utility

1/2 – Sale of
Lawrenceburg
announced

11/9 –

PSE&G Rate
Settlements

12/20– PSEG resumes direct
management of Nuclear stations
and Exelon’s senior management
team joins PSEG.

11/30- PSEG
Power Consent
Decree

1/31 - Operating Earnings at
upper end of guidance;
Confirmed strong ’07-’08
outlook; Improved Balance
Sheet

9/25 –

CEO
Succession
Announced

Regulatory

Operations

Management

Financial /
Asset
Rationalization

12/7 –

New Senior Team
Announced

1/16 –

Dividend
Increase

Organizational Design
& Staffing in progress

12/31 – Power
completes 96%
2006 capacity
factor

3


0.00

0.25

0.50

0.75

1.00

Power

Re-contracting &
Higher Margins
$.22

Depreciation,
Interest & Other
$.06

O&M $.03

Nuclear Operations
$.02

BGSS ($.11)

Turbine Impairment
($.10)

New Assets ($.06)

NDT ($.05)

MTM ($.05)

Shares O/S ($.01)

PSE&G

O&M & Other
$.02

Transmission
$.02

Demand $.02

Effective Tax
Rate $.02

Weather ($.06)

Expiration of
Depreciation
Credit ($.03)

4Q 2006
Operating
Earnings**

    4Q 2005   
Operating
Earnings*

*Excludes ($.02) Merger Costs, Cumulative Effect of an Accounting Change ($.07) and ($.02) Discontinued Operations
**Excludes ($.87) Discontinued Operations

Holdings

Lower taxes $.08

Lower Interest &
Other $.04

Gain on sale of
Seminole lease in
2005 ($.18)

TIE – MTM &
Operations ($.08)

RGE Sale ($.04)

Turboven
Impairment ($.02)

Enterprise

Interest   
Savings $.01

4Q 2006 Results - Earnings Variance

$0.94

(.01)

(.05)

(.20)

.01

$0.69

4


2006 Results - Earnings Variance

1.00

1.50

2.00

2.50

3.00

3.50

4.00

Power

Re-contracting &
Higher Margins
$.84

Nuclear
Operations $.20

Depreciation,
Interest & Other
$.04

New Assets ($.23)

BGSS ($.22)

NDT ($.13)

Turbine
Impairment ($.10)

Shares O/S ($.07)

Environmental
Reserve ($.06)

O&M ($.06)

PSE&G

Transmission
$.06

Other $.01

Weather ($.19)

Expiration of
Depreciation
Credit ($.15)

O&M ($.04)

Depr./Amort.
($.04)

Shares O/S
($.03)

2006
Operating
Earnings**

  2005   
Operating
Earnings*

      Holdings

Texas Ops $.21,
including MTM of
$.13

Lower Interest &
Taxes $.18

2005 UAL Write-
off $.05

FX Gains/Losses
$.03

Prior Year Gains:
Eagle Point,
Seminole,
SEGS, MPC
($.31)

RGE Sale ($.06)

Turboven
Impairment
($.02)

Enterprise

Interest   
Savings $.03

.21

.08

(.38)

.03

$3.77

$3.71

*Excludes ($.14) Merger Costs, Cumulative Effect of an Accounting Change ($.07) and ($.85) Discontinued Operations
**Excludes ($.03) Merger Costs, ($.70) Loss on Sale of RGE and ($.05) Discontinued Operations

5


PSEG 2007 Earnings Outlook & Drivers

2006 EPS

Power

PSE&G

Holdings

2007 Guidance

2008

$3.71

Excess of
10% Growth

Forward
Hedging

Re-contracting

        - PJM/NE

Capacity   
Market Design

Gas Rate
Case

Electric
Financial
Review

Weather

Texas

Asset Sales

New
Accounting
Standard

Increase/(Decrease) vs.
2006 Operating Earnings

2007 Forecast Operating
Earnings Ranges

$232 - $357

($97) – ($82)

$68 - $88

$255 - $335

$1170 - $1295

$130 - $145

$330 - $350

$770 - $850

$4.60 - $5.00

2006
Operating
Earnings:
$938M*

*Excludes Loss on Sale of RGE of $178M ($.70 per share), Merger Costs of $8M ($.03 per share) and Discontinued
Operations of $13M ($.05 per share)

6


PSE&G


PSE&G Overview

Electric

  Distribution

$3.2B

Gas Distribution

$2.1B

Electric

Transmission

$0.7B

Rate Base

(As of December 31, 2006)

2.1 M electric customers

1.7 M gas customers

2,600 sq miles in service
territory

8


Fair outcomes on recent gas and electric cases will
help ensure…

Settlement agreement with BPU staff, Public Advocate, and other parties

Gas Base Rate case provides for $79M of gas margin

$40M increase in rates

$39M decrease in non-cash expenses

Electric Distribution financial review provides $47M of additional revenues

Base rates remain effective until November 2009

New Jersey regulatory climate providing a fair return to investors

Opportunity to earn a ROE of 10%

…our continued ability to provide safe, reliable
service to customers and fair returns to shareholders.

9


Rate relief and normal weather…

$0

$100

$200

$300

$400

2006 Operating
Earnings*

Gas Rate Relief

Electric Financial
Review

Weather

2007 Guidance

$262M

$30M - $40M

$20M - $25M

$330M
to
$350M

$20M - $30M

… provide opportunity to earn allowed returns.

*  Excludes $1M of Merger Costs

10


Looking Forward PSE&G…

Continues to invest in its assets for the future

Distribution System Reinforcements

Transmission Investments

Customer Service

Is committed to meeting customer needs and
expectations

Is supporting NJ’s Energy Master Plan process, which
may create opportunities for additional investments

Advanced Metering, Solar Installations/other renewables and Energy
Efficiency

Endeavors to maintain constructive regulatory relations
regarding traditional utility matters

11


PSEG Power


PSEG Power Overview

Diverse asset mix mitigates risk
and provides strong returns

13,600* MW of nuclear, coal, gas,
oil and hydro facilities

Low-cost portfolio

Strong cash generator

Regional focus with demonstrated
BGS success

Assets favorably located

Many units east of PJM constraint

Southern NEPOOL/Connecticut
constraint

Near customers/load centers

Integrated generation and portfolio
management optimizes asset-
based revenues

18 %

47 %

8 %

26 %

Fuel Diversity – 2007*

Coal

Gas

Oil

Nuclear

Pumped

Storage

1%

(MWs)

* After sale of Lawrenceberg

Energy Produced - 2006

(MWhrs)

55%

27%

16%

Oil 1%

Pumped
Storage
1%

Nuclear

Coal

Gas

Total MWhrs: 53,617

13


Capacity Factors

82%

90%

96%

77%

89%

96%

2004

2005

2006

*Uprate of 127MW scheduled for Fall 2007

Strong operational performance

Capacity factors: Year -end ~96%

                                     Summer ~100%

Outage management

Site records achieved, including most
recent 21 day refueling outage at
Salem 2

  Nuclear Operating Services            
Agreement (NOSA)

PSEG to resume direct management of
Salem and Hope Creek

Exelon’s senior management team
joins PSEG

Hope Creek*

Salem

1 & 2

Peach Bottom
2 & 3

PSEG MW
Owned

1,059MW*

1,323MW

1,112MW

Ownership

PSEG Owned

Jointly Owned

Jointly Owned

Operations

PSEG
Operated
(NOSA)

PSEG
Operated
(NOSA)

Exelon
Operated

Total
Fleet:
3,494 MW

Strong Nuclear Operations

NJ Fleet:
2,382MW

14


Strong Fossil Operations round out a diverse portfolio…

0

5,000

10,000

15,000

20,000

25,000

2002

2003

2004

2005

2006

Coal

Combined Cycle

Peaking & Other

Total Fossil Output (Gwh)

A Diverse 10,000 MW Fleet

2,400 MW coal

3,200 MW combined cycle

4,400 MW peaking and other

Strong Performance

Continued growth in output

Improved fleet performance

Achieved resolution regarding
Hudson / Mercer

…in which over 80% of fleet output is from low cost coal
and nuclear facilities.

15


Strengthening of capacity market design…

Total Generating Capacity

PSEG Power

PJM

NY

NE

Total Capacity 13,600MW

(1,500MW under RMR)

New England

Forward Capacity Market (FCM) began 12/1/06

Transition period prices have been established

Grows from $37/kw-yr to $49/kw-yr

through 2010

First auction scheduled in 2008 for June 2010

        delivery

PJM

FERC Approved 12/22/06

Locational pricing

4 zones initally, 23 in 2010

Anticipated implementation 6/1/07

Auction schedule:

2007-2008      April 2007

2008-2009         July 2007

2009-2010         October 2007

2010-2011         January 2008

…provides meaningful market signals, and enhances
margin for Power’s generating fleet.

16


The 1st RPM-year spans June 2007 through May 2008,
and will cover similar one year (BGS) intervals
thereafter.  Recent market activity has shown
considerable price increases for the 2007/2008 year.

PJM’s Reliability Pricing Model

RPM reflects a change in                     
market design

- More structured, forward-
looking, transparent pricing model

- Gives prospective investors in
new generating facilities more

clarity on future value of capacity

- Sends pricing signal to
encourage expansion of capacity
where needed for future market
demands

Capacity Prices

Capacity revenues, driven by RPM, provide a meaningful increase in Power’s

margin - $100 - $150 million for 2007 - and is anticipated to increase in future

years due to full year PJM impact and as more capacity

comes off existing contracts

$0

$20

$40

$60

2001

2002

2003

2004

2005

2006

2007

Feb 2007

Sept 2006

Range of
recent prices
for ’07 – ’08
year

17


20,000

4,000

8,000

12,000

16,000

2002

2003

2004

2005

2006

2007

2008

2002 FP
  Auction   

1 Year

170
Tranches

2003 FP
Auction
10
months

104
Tranches

2003 FP Auction
34 months

51 Tranches

2004 FP   
Auction - 1 Yr.

50 Tranches

2004 FP Auction - 3 Years

51 Tranches

2006 FP Auction Load

54 Tranches

2005 FP Auction Load  
50 Tranches

2007 FP Auction Load
(projected)

New Jersey BGS Auction Structure

The BGS structure in New Jersey successfully mitigates
risk for both suppliers and for customers.

18


2003 Auction

2004 Auction

2005 Auction

2006 Auction

2007 Auction

Market Viewpoint - BGS Auction Results

Capacity

Load shape

Transmission

Congestion

Ancillary services

Risk premium

Full Requirements

Round the Clock
PJM West
Forward Energy
Price

$33 - $34

$36 - $37

$55.59

$55.05            

$65.91

$44 - $46

~ $21

~ $18

~ $21

$102.21

$67 - $70

~ $32

Increase in Full Requirements Component Due to:

Increased Congestion (East/West Basis)

Increase in Capacity Markets/RPM

Volatility in Market Increases Risk Premium

$98.88

~ $41

$58-$60

Power has been a successful participant in each BGS auction.

19


$250

$500

$750

$1,000

2006

2007

2008

The year over year improvements…

Energy

Capacity

Other

drive growth in PSEG’s 2007 earnings guidance
with further improvements in 2008.

$515M

Power drives 2008 earnings
guidance in excess of 10%

over 2007

Full year of capacity

Recontracting of 2005 BGS

$200M - $240M

$50M - $80M

$770M
to
$850M

$5M - $15M

20


Looking Forward PSEG Power…

Transitions its New Jersey nuclear plants to independent
operations

Moves forward to enhance environmental profile through
Consent Decree compliance

Anticipates energy markets to provide attractive growth

Energy hedges roll with increased margin

Capacity markets increasing – RPM auctions will provide visibility

Positions balance sheet for growth

21


PSEG Energy Holdings


6%

15%

3%

45%

31%

PSEG Energy Holdings Overview

Other Resources Investments

TOTAL ASSETS $6.2 B – 12/31/06

PSEG Global

Domestic
Generation

PSEG Resources

Leveraged Leases

Other International Generation

Chile & Peru
Generation and
Distribution

Two businesses with redirected strategy to maximize value of existing
investments

Balance and diversity: over 60 total investments; no single investment
more than 11% of Holdings assets

            23


Improved risk profile by opportunistically reducing
capital invested in non-strategic assets…

…while increasing returns and sharpening focus on G&A.

2004

2006

$2.6B

$2.0B

Chile & Peru

US

Other

$900M

$400M

$1.3B

$160M

$500M

$1.4B

34%

16%

50%

8%

24%

68%

$104

$108

$41

$168

$57

$20

$(40)

$(35)

$(25)

  

  

  

$296M

48%

45%

2004

2006

2007 Est.

$202M

$210M-$230M

Composition of Global’s Pre-tax
        Equity-in-Earnings

G&A

Chile
& Peru

US

Other

28%

20%

51%

6%

57%

37%

7%

Global’s Invested Capital

            24


Holdings has provided meaningful earnings and
cash flow…

…which has supported debt reduction and return
of capital to PSEG.

Sources & Uses of Cash from 2004 - 2006

$0.0

$0.5

$1.0

$1.5

$2.0

$2.5

Sources

Uses

Asset
Sales

Cash Ops/
Cash on
Hand

Reduced
Debt

Return
Capital/
Dividends

Significant de-capitalization
totaling $2.3B from 2004 -
2006

$609M

-

$311M

Net Debt
Reduction

47%

3.4x

$491M

2004

36%

41%

Recourse
Debt/Capital

4.5x

2.5x

FFO/Interest

$520M

$412M

Dividends & ROC

2006

2005

Debt Reduction & Dividends from 2004 - 2006

            25


PSEG Energy Holdings – 2007 Drivers

$0

$100

$200

$300

2006 Operating
Earnings
*

Texas

FIN 48

Taxes

Asset Sales

2007 Guidance

$227M

$25M - $35M

$10M - $20M

$130M
to
$145M

$5M - $10M

$35M - $45M

*Excludes $178M Loss on Sale of RGE

            26


Looking Forward Energy Holdings…

Global’s Portfolio – Allocation of Invested Capital

Improved risk profile

Chile - Investment Grade; Peru - approaching

US – Texas is merchant; others are contracted

Stable earnings and cash distributions

Continue opportunistic monetization of non-strategic assets

Optimizes returns on Global’s current portfolio

Attractive market opportunities for Texas assets

Continue to seek increased returns in Chile and Peru

Other opportunities (eg. G&A)

Monitors Resources’ lease portfolio

Lessee credit risks exist, but has subsided                   

Current weighted average rating: A-/A3

Adoption of FIN 48 decreases earnings

Continue to monitor tax landscape

            27


Looking Forward PSEG…


Financial
Strength

We will focus on the basics of operational excellence...

…to produce financial strength that will be deployed
through disciplined investment.

Operational
Excellence

Disciplined
Investment

            29


Strong earnings and cash flows will be used to
further de-lever the balance sheet.

Improving our credit profile will enable us to
maximize growth opportunities.

$2.00

$3.00

$4.00

$5.00

$6.00

2005 Actual

2006 Guidance

2007 Guidance

2008 Est.

10%

15%

20%

25%

30%

Excess
of 10%
Growth

FFO/  
Total Debt

EPS

YE ‘06
EPS:
$3.71

              Guidance range: ’06: $3.45 - $3.75                                                   
                                              ’07: $4.60 - $5.00                              

YE ‘05
EPS:
$3.77

            30


…and capitalize on multiple alternatives to grow the generation and
delivery business.

From a position of financial strength, we will make
disciplined investments…

Near-term:

Capitalize on opportunities for rate base growth

Distribution, transmission, customer service

Optimize our existing generation portfolio

Environmental improvements at NJ coal stations

Nuclear uprate

Take a hard look at international assets

Longer-term:

Flexibility to pursue growth in core businesses and regions

PSE&G integrating with NJ Energy Master Plan initiatives

Advanced metering

Renewables

Demand side management

Power well positioned for growth in attractive Northeast markets

Strong and improving operations

Site expansion capability

Attractive cash flow

Consider a range of strategic alternatives

            31


$50.00

$100.00

$150.00

$200.00

$250.00

2001

2002

2003

2004

2005

2006

PSEG

S&P 500

DJ Utilities

S&P Electrics

Creating Shareholder Value

Focused on producing superior shareholder return

5-Year Cumulative Total Comparative Returns

(as of December 31, 2006)

            32