XML 31 R14.htm IDEA: XBRL DOCUMENT v3.23.2
Rate Filings
6 Months Ended
Jun. 30, 2023
Regulatory Assets [Line Items]  
Rate Filings Rate Filings
This Note should be read in conjunction with Note 7. Regulatory Assets and Liabilities to the Consolidated Financial Statements in the Annual Report on Form 10-K for the year ended December 31, 2022.
In addition to items previously reported in the Annual Report on Form 10-K, significant regulatory orders received and currently pending rate filings with the BPU or FERC are as follows:
BGSS—In January and February 2023, PSE&G filed with the BPU two self-implementing BGSS rate reductions of 15 cents and 3 cents per therm, effective February 1, 2023 and March 1, 2023, respectively. These reductions resulted in a new BGSS rate of approximately 47 cents per therm effective March 1, 2023. In April 2023, the BPU gave final approval to PSE&G’s BGSS rate of 47 cents per therm.
In June 2023, PSE&G made its annual BGSS filing with the BPU requesting a decrease to its BGSS rate to approximately 40 cents per therm, effective October 1, 2023. This matter is pending.
CIPIn February 2023, the BPU gave final approval for PSE&G to recover approximately $52 million of deficient electric revenues that resulted from the 12-month period ended May 31, 2022, with approximately $18 million approved for recovery for the first year starting on the effective date of June 15, 2022 and the remaining $34 million to be recovered starting in June 2023.
In April 2023, the BPU gave final approval for PSE&G to recover approximately $53 million of deficient gas revenues that resulted from the 12-month period ended September 30, 2022, over one year effective October 1, 2022.
In May 2023, the BPU provisionally approved PSE&G's updated annual electric CIP petition to recover approximately $72 million of deficient electric revenues over two years that resulted from the 12-month period ended May 31, 2023, with new rates effective June 1, 2023.
In June 2023, PSE&G filed a gas CIP recovery petition seeking BPU approval to recover estimated deficient gas revenues of approximately $99 million for the 12-month period ending September 30, 2023, and an additional $11 million carryover underrecovery from the prior CIP period for a total request of $110 million. The revenue deficiency is the result of lower actual and estimated revenues as compared to a baseline established in PSE&G’s most recent distribution base rate proceeding. New rates are proposed to be effective October 1, 2023 and PSE&G expects to recover its deficiency over a one year period. This matter is pending.
COVID-19 Deferral—In May and June 2023, the BPU issued two Orders to all public utilities in New Jersey that stipulated a filing deadline for recovery of COVID-19 Regulatory Asset balances, and set forth certain filing requirements primarily related to recovery proposals to be included by each utility in their COVID-19 filings.
In July 2023, PSE&G filed a petition with the BPU in compliance with those Orders requesting recovery of its incremental costs associated with the COVID-19 pandemic. This matter is pending.
As of June 30, 2023, PSE&G has deferred approximately $131 million as a Regulatory Asset for its net incremental costs, including $68 million for incremental gas bad debt expense associated with customer accounts receivable. PSE&G expects its COVID-19 Regulatory Asset balance is probable of recovery under the BPU orders.
Energy Strong II—In April 2023, the BPU approved PSE&G’s updated filing for annual electric and gas revenue increases of $16 million and $4 million, respectively, effective May 1, 2023. These increases represent the return on and of Energy Strong II investments placed in service through January 2023.
In May 2023, PSE&G filed a petition seeking BPU approval to recover an annualized increase in electric revenue requirement of approximately $15 million associated with capitalized electric investment costs of the Energy Strong II program. This increase represents the return on and of actual and forecasted investments through July 31, 2023. This matter is pending.
Gas System Modernization Program II (GSMP II)—In May 2023, the BPU approved PSE&G’s updated GSMP II cost recovery filing to recover an annual gas revenue increase of approximately $11 million effective June 1, 2023. This increase represents the return on and of GSMP II investments placed in service through February 2023.
Green Program Recovery Charges (GPRC)—In May 2023, the BPU approved PSE&G’s 2022 updated GPRC filing for annual electric and gas revenue increases of $87 million and $5 million, respectively, with new rates effective June 1, 2023.
Additionally in May 2023, the BPU approved PSE&G’s petition to increase its Clean Energy Future-EE sub program investment (a component of GPRC) by $280 million and approved a nine-month extension to make investments.
In June 2023, PSE&G filed its 2023 GPRC cost recovery petition requesting BPU approval for recovery of increases of $38 million and $20 million in annual electric and gas revenues, respectively. This matter is pending.
Pension—In February 2023, the BPU approved an accounting order authorizing PSE&G to modify its method for calculating the amortization of the net actuarial gain or loss component of pension expense for ratemaking purposes. This methodology change for ratemaking purposes is effective for the calendar year ending December 31, 2023 and forward. As of June 30, 2023, PSE&G has deferred $30 million as a Regulatory Asset under this methodology.
Remediation Adjustment Charge (RAC)—In January 2023, PSE&G filed its RAC 30 petition with the BPU seeking recovery of approximately $44 million of net Manufactured Gas Plant (MGP) expenditures incurred from August 1, 2021 through July 31, 2022. This matter is pending.
SBC—In January 2023, PSE&G filed a petition to increase its annual electric and gas rates by approximately $52 million and $32 million, respectively, in order to recover electric and gas costs incurred or expected to be incurred through February 2024 under its EE and Renewable Energy and Social Programs. The increase to electric rates includes the impact of increased bad debt expense as a result of the negative economic impact of the coronavirus pandemic and the resulting impact of moratoriums on collections. This matter is pending.
Tax Adjustment Credit (TAC)—In July 2023, the BPU approved PSE&G’s updated 2022 TAC filing to increase annual electric revenues by approximately $17 million and decrease annual gas revenues by approximately $42 million, with new rates effective August 1, 2023.
Transmission Formula Rates—In June 2023, PSE&G filed with FERC its 2022 true-up adjustment pertaining to its transmission formula rates in effect for calendar year 2022, as established by its 2022 annual forecast filing. The June 2023 true-up filing resulted in a decrease in the 2022 annual revenue requirement of approximately $21 million less than the revenue
requirement numbers contained in the forecast filing. PSE&G had previously recognized the majority of the lower revenue requirement in its 2022 Consolidated Statement of Operations.ZEC Program—In January 2023, the BPU approved PSE&G’s petition to set the ZEC refund component of the tariff rate to zero effective February 1, 2023 as overcollections for the ZEC Energy Year ended May 31, 2022 totaling $1.3 million, including interest, were refunded to customers in 2022 through January 2023.
Public Service Electric and Gas Company [Member]  
Regulatory Assets [Line Items]  
Rate Filings Rate Filings
This Note should be read in conjunction with Note 7. Regulatory Assets and Liabilities to the Consolidated Financial Statements in the Annual Report on Form 10-K for the year ended December 31, 2022.
In addition to items previously reported in the Annual Report on Form 10-K, significant regulatory orders received and currently pending rate filings with the BPU or FERC are as follows:
BGSS—In January and February 2023, PSE&G filed with the BPU two self-implementing BGSS rate reductions of 15 cents and 3 cents per therm, effective February 1, 2023 and March 1, 2023, respectively. These reductions resulted in a new BGSS rate of approximately 47 cents per therm effective March 1, 2023. In April 2023, the BPU gave final approval to PSE&G’s BGSS rate of 47 cents per therm.
In June 2023, PSE&G made its annual BGSS filing with the BPU requesting a decrease to its BGSS rate to approximately 40 cents per therm, effective October 1, 2023. This matter is pending.
CIPIn February 2023, the BPU gave final approval for PSE&G to recover approximately $52 million of deficient electric revenues that resulted from the 12-month period ended May 31, 2022, with approximately $18 million approved for recovery for the first year starting on the effective date of June 15, 2022 and the remaining $34 million to be recovered starting in June 2023.
In April 2023, the BPU gave final approval for PSE&G to recover approximately $53 million of deficient gas revenues that resulted from the 12-month period ended September 30, 2022, over one year effective October 1, 2022.
In May 2023, the BPU provisionally approved PSE&G's updated annual electric CIP petition to recover approximately $72 million of deficient electric revenues over two years that resulted from the 12-month period ended May 31, 2023, with new rates effective June 1, 2023.
In June 2023, PSE&G filed a gas CIP recovery petition seeking BPU approval to recover estimated deficient gas revenues of approximately $99 million for the 12-month period ending September 30, 2023, and an additional $11 million carryover underrecovery from the prior CIP period for a total request of $110 million. The revenue deficiency is the result of lower actual and estimated revenues as compared to a baseline established in PSE&G’s most recent distribution base rate proceeding. New rates are proposed to be effective October 1, 2023 and PSE&G expects to recover its deficiency over a one year period. This matter is pending.
COVID-19 Deferral—In May and June 2023, the BPU issued two Orders to all public utilities in New Jersey that stipulated a filing deadline for recovery of COVID-19 Regulatory Asset balances, and set forth certain filing requirements primarily related to recovery proposals to be included by each utility in their COVID-19 filings.
In July 2023, PSE&G filed a petition with the BPU in compliance with those Orders requesting recovery of its incremental costs associated with the COVID-19 pandemic. This matter is pending.
As of June 30, 2023, PSE&G has deferred approximately $131 million as a Regulatory Asset for its net incremental costs, including $68 million for incremental gas bad debt expense associated with customer accounts receivable. PSE&G expects its COVID-19 Regulatory Asset balance is probable of recovery under the BPU orders.
Energy Strong II—In April 2023, the BPU approved PSE&G’s updated filing for annual electric and gas revenue increases of $16 million and $4 million, respectively, effective May 1, 2023. These increases represent the return on and of Energy Strong II investments placed in service through January 2023.
In May 2023, PSE&G filed a petition seeking BPU approval to recover an annualized increase in electric revenue requirement of approximately $15 million associated with capitalized electric investment costs of the Energy Strong II program. This increase represents the return on and of actual and forecasted investments through July 31, 2023. This matter is pending.
Gas System Modernization Program II (GSMP II)—In May 2023, the BPU approved PSE&G’s updated GSMP II cost recovery filing to recover an annual gas revenue increase of approximately $11 million effective June 1, 2023. This increase represents the return on and of GSMP II investments placed in service through February 2023.
Green Program Recovery Charges (GPRC)—In May 2023, the BPU approved PSE&G’s 2022 updated GPRC filing for annual electric and gas revenue increases of $87 million and $5 million, respectively, with new rates effective June 1, 2023.
Additionally in May 2023, the BPU approved PSE&G’s petition to increase its Clean Energy Future-EE sub program investment (a component of GPRC) by $280 million and approved a nine-month extension to make investments.
In June 2023, PSE&G filed its 2023 GPRC cost recovery petition requesting BPU approval for recovery of increases of $38 million and $20 million in annual electric and gas revenues, respectively. This matter is pending.
Pension—In February 2023, the BPU approved an accounting order authorizing PSE&G to modify its method for calculating the amortization of the net actuarial gain or loss component of pension expense for ratemaking purposes. This methodology change for ratemaking purposes is effective for the calendar year ending December 31, 2023 and forward. As of June 30, 2023, PSE&G has deferred $30 million as a Regulatory Asset under this methodology.
Remediation Adjustment Charge (RAC)—In January 2023, PSE&G filed its RAC 30 petition with the BPU seeking recovery of approximately $44 million of net Manufactured Gas Plant (MGP) expenditures incurred from August 1, 2021 through July 31, 2022. This matter is pending.
SBC—In January 2023, PSE&G filed a petition to increase its annual electric and gas rates by approximately $52 million and $32 million, respectively, in order to recover electric and gas costs incurred or expected to be incurred through February 2024 under its EE and Renewable Energy and Social Programs. The increase to electric rates includes the impact of increased bad debt expense as a result of the negative economic impact of the coronavirus pandemic and the resulting impact of moratoriums on collections. This matter is pending.
Tax Adjustment Credit (TAC)—In July 2023, the BPU approved PSE&G’s updated 2022 TAC filing to increase annual electric revenues by approximately $17 million and decrease annual gas revenues by approximately $42 million, with new rates effective August 1, 2023.
Transmission Formula Rates—In June 2023, PSE&G filed with FERC its 2022 true-up adjustment pertaining to its transmission formula rates in effect for calendar year 2022, as established by its 2022 annual forecast filing. The June 2023 true-up filing resulted in a decrease in the 2022 annual revenue requirement of approximately $21 million less than the revenue
requirement numbers contained in the forecast filing. PSE&G had previously recognized the majority of the lower revenue requirement in its 2022 Consolidated Statement of Operations.ZEC Program—In January 2023, the BPU approved PSE&G’s petition to set the ZEC refund component of the tariff rate to zero effective February 1, 2023 as overcollections for the ZEC Energy Year ended May 31, 2022 totaling $1.3 million, including interest, were refunded to customers in 2022 through January 2023.