Early Plant Retirements/Asset Dispositions Early Plant Retirements/Asset Dispositions
9 Months Ended
Sep. 30, 2019
Early Plant Retirements/Asset Dispositions [Line Items]  
Early Plant Retirements/Asset Dispositions Early Plant Retirements/Asset Dispositions
Nuclear
In April 2019, PSEG Power’s Salem 1, Salem 2 and Hope Creek nuclear plants were awarded Zero Emission Certificates (ZECs) by the BPU. Pursuant to a process established by the BPU, ZECs are purchased from selected nuclear plants and recovered through a non-bypassable distribution charge in the amount of $0.004 per kilowatt-hour (which is equivalent to approximately $10 per megawatt hour (MWh) in payments to selected nuclear plants (ZEC payment)). These nuclear plants are expected to receive ZEC revenue for approximately three years, through May 2022, and will be obligated to maintain operations, subject to exceptions specified in the ZEC legislation. PSEG Power anticipates it will recognize revenue monthly as the nuclear plants generate electricity and satisfy their performance obligations. The ZEC legislation requires nuclear plants to reapply for any subsequent three year periods. The ZEC payment may be adjusted by the BPU (a) at any time to offset environmental or fuel diversity payments that a selected nuclear plant may receive from another source or (b) at certain times specified in the ZEC legislation if the BPU determines that the purposes of the ZEC legislation can be achieved through a reduced charge that will nonetheless be sufficient to achieve the state’s air quality and other environmental objectives by preventing the retirement of nuclear plants. The BPU’s decision awarding ZECs has been appealed by the Division of Rate Counsel. The financial condition of the plants may nonetheless be materially adversely impacted by potential changes to the capacity market construct being considered by FERC (absent sufficient capacity revenues provided under a program approved by the BPU in accordance with a FERC- authorized capacity mechanism), and, in the case of the Salem nuclear plants, decisions by the EPA and state environmental regulators regarding the implementation of Section 316(b) of the Clean Water Act and related state regulations, or other factors. Absent a material financial change, these adverse impacts could still result in PSEG Power taking all necessary steps to retire all of these plants following the end of the initial three year term of the ZECs program. Retirement of these plants would result in a material adverse impact on PSEG’s and PSEG Power’s financial results.
Fossil
In September 2019, PSEG Power completed the sale of its ownership interests in the Keystone and Conemaugh generation plants and related assets and liabilities. PSEG Power recorded a pre-tax loss on disposition of approximately $400 million in the second quarter of 2019 as the sale price was less than book value.
PSEG Power [Member]  
Early Plant Retirements/Asset Dispositions [Line Items]  
Early Plant Retirements/Asset Dispositions Early Plant Retirements/Asset Dispositions
Nuclear
In April 2019, PSEG Power’s Salem 1, Salem 2 and Hope Creek nuclear plants were awarded Zero Emission Certificates (ZECs) by the BPU. Pursuant to a process established by the BPU, ZECs are purchased from selected nuclear plants and recovered through a non-bypassable distribution charge in the amount of $0.004 per kilowatt-hour (which is equivalent to approximately $10 per megawatt hour (MWh) in payments to selected nuclear plants (ZEC payment)). These nuclear plants are expected to receive ZEC revenue for approximately three years, through May 2022, and will be obligated to maintain operations, subject to exceptions specified in the ZEC legislation. PSEG Power anticipates it will recognize revenue monthly as the nuclear plants generate electricity and satisfy their performance obligations. The ZEC legislation requires nuclear plants to reapply for any subsequent three year periods. The ZEC payment may be adjusted by the BPU (a) at any time to offset environmental or fuel diversity payments that a selected nuclear plant may receive from another source or (b) at certain times specified in the ZEC legislation if the BPU determines that the purposes of the ZEC legislation can be achieved through a reduced charge that will nonetheless be sufficient to achieve the state’s air quality and other environmental objectives by preventing the retirement of nuclear plants. The BPU’s decision awarding ZECs has been appealed by the Division of Rate Counsel. The financial condition of the plants may nonetheless be materially adversely impacted by potential changes to the capacity market construct being considered by FERC (absent sufficient capacity revenues provided under a program approved by the BPU in accordance with a FERC- authorized capacity mechanism), and, in the case of the Salem nuclear plants, decisions by the EPA and state environmental regulators regarding the implementation of Section 316(b) of the Clean Water Act and related state regulations, or other factors. Absent a material financial change, these adverse impacts could still result in PSEG Power taking all necessary steps to retire all of these plants following the end of the initial three year term of the ZECs program. Retirement of these plants would result in a material adverse impact on PSEG’s and PSEG Power’s financial results.
Fossil
In September 2019, PSEG Power completed the sale of its ownership interests in the Keystone and Conemaugh generation plants and related assets and liabilities. PSEG Power recorded a pre-tax loss on disposition of approximately $400 million in the second quarter of 2019 as the sale price was less than book value.