XML 35 R12.htm IDEA: XBRL DOCUMENT v3.8.0.1
Rate Filings
9 Months Ended
Sep. 30, 2017
Regulatory Assets [Line Items]  
Rate Filings
Rate Filings
This Note should be read in conjunction with Note 6. Regulatory Assets and Liabilities to the Consolidated Financial Statements in the Annual Report on Form 10-K for the year ended December 31, 2016.
In addition to items previously reported in the Annual Report on Form 10-K, significant regulatory orders received and currently pending rate filings with FERC and the BPU by PSE&G are as follows:
Transmission Formula Rate Filings—In June 2017, PSE&G filed its 2016 true-up adjustment pertaining to its transmission formula rates in effect for 2016. This resulted in an adjustment of $12 million more than the 2016 originally filed revenues.
In October 2017, the 2018 Annual Formula Rate update was filed with FERC and requests approximately $212 million in increased annual transmission revenue effective January 1, 2018, subject to true-up.
Gas System Modernization Program (GSMP)—In July of each year, PSE&G files with the BPU for base rate recovery of GSMP investments which include a return of and on its investment.
In October 2017, PSE&G submitted the planned update to its annual GSMP cost recovery petition, originally filed in July 2017, to include GSMP investments in service as of September 30, 2017. This filing seeks BPU approval to recover in gas base rates an annual revenue increase of $25 million effective January 1, 2018. This increase represents the return of and on investment for GSMP investments in service through September 30, 2017. This proceeding is ongoing.   
Energy Strong Recovery Filing—In March and September of each year, PSE&G files with the BPU for base rate recovery of Energy Strong investments which include a return of and on its investment.
In June 2017, PSE&G submitted the planned update to its March Energy Strong cost recovery petition, originally filed in March 2017, to include Energy Strong investments in service as of May 31, 2017. This filing requested estimated annual increases in electric and gas revenues of $16 million and $2 million, respectively. In August 2017, the BPU approved these rate increases effective September 1, 2017.
In September 2017, PSE&G filed its Energy Strong electric cost recovery petition seeking BPU approval to recover the revenue requirements associated with Energy Strong capitalized investment costs placed in service from June 1, 2017 through November 30, 2017. The petition requests rates to be effective March 1, 2018, consistent with the BPU Order of approval of the Energy Strong program. The annualized requested increase in electric revenue requirement is approximately $9 million. This proceeding is ongoing.   
Basic Gas Supply Services (BGSS)—In June 2017, PSE&G made its annual BGSS filing with the BPU requesting an increase in the BGSS rate from approximately 34 cents to 37 cents per therm effective October 1, 2017. In September 2017, the BPU approved a Stipulation in this matter on a provisional basis and the BGSS rate was increased.
Weather Normalization Clause—In April 2017, the BPU gave final approval to PSE&G’s petition to collect $54 million in net deficiency gas revenues as a result of the warmer than normal 2015-2016 Winter Period.
In June 2017, PSE&G filed a petition requesting approval to collect $55 million in total net deficiency revenues comprised of $31 million in net deficiency gas revenues as a result of the warmer than normal 2016-2017 Winter Period and the remaining carryover balance of $24 million in net deficiency gas revenue from the 2015-2016 Winter Period. The deficiency gas revenue would be collected from customers over the 2017-2018 and 2018-2019 Winter Periods (October 1 through May 31). In September 2017, the BPU approved this petition on a provisional basis with rates effective October 1, 2017, allowing recovery during the 2017-2018 Winter Period.
Green Program Recovery Charges (GPRC)—In August 2017, the BPU approved PSE&G’s petition for an Energy Efficiency 2017 Program (EE 2017) to extend three existing energy efficiency subprograms (multi-family, direct install and hospital efficiency) and establish two new residential energy efficiency offerings. The two new offerings include deployment of smart thermostats and a pilot program to provide residential customers with energy usage information enabling them to reduce consumption. The Order allows PSE&G to extend the subprogram offerings and establish the residential energy efficiency sub-programs under its existing energy efficiency clause recovery process. The EE 2017 allows for $69 million of additional investment and $16 million of additional administrative and information technology costs. The EE 2017 was added as the 11th component of the GPRC rate effective September 1, 2017.
Each year PSE&G files with the BPU for annual recovery for the 11 combined components of its electric and gas Green Program investments which include a return on its investment and recovery of expenses.
In March 2017, the BPU gave final approval to PSE&G’s 2016 GPRC cost recovery petition to recover approximately $37 million and $13 million in electric and gas revenues, respectively, on an annual basis associated with PSE&G’s implementation of these BPU approved GPRC programs for the period October 1, 2016 through September 30, 2017. The rates were effective May 1, 2017. This Order also included the return of approximately $5 million in remaining overcollections from the completed Securitization Transition Charge. 
In June 2017, PSE&G filed its 2017 GPRC cost recovery petition requesting recovery of approximately $47 million and $13 million in electric and gas revenues, respectively, on an annual basis associated with PSE&G's implementation of these BPU-approved programs for the period October 1, 2017 through September 30, 2018. This proceeding is ongoing.
Remediation Adjustment Charge (RAC)—In June 2017, the BPU approved PSE&G's filing with respect to its RAC 24 petition allowing recovery of $41 million effective July 10, 2017 related to net Manufactured Gas Plant expenditures from August 1, 2015 through July 31, 2016.
PSE And G [Member]  
Regulatory Assets [Line Items]  
Rate Filings
Rate Filings
This Note should be read in conjunction with Note 6. Regulatory Assets and Liabilities to the Consolidated Financial Statements in the Annual Report on Form 10-K for the year ended December 31, 2016.
In addition to items previously reported in the Annual Report on Form 10-K, significant regulatory orders received and currently pending rate filings with FERC and the BPU by PSE&G are as follows:
Transmission Formula Rate Filings—In June 2017, PSE&G filed its 2016 true-up adjustment pertaining to its transmission formula rates in effect for 2016. This resulted in an adjustment of $12 million more than the 2016 originally filed revenues.
In October 2017, the 2018 Annual Formula Rate update was filed with FERC and requests approximately $212 million in increased annual transmission revenue effective January 1, 2018, subject to true-up.
Gas System Modernization Program (GSMP)—In July of each year, PSE&G files with the BPU for base rate recovery of GSMP investments which include a return of and on its investment.
In October 2017, PSE&G submitted the planned update to its annual GSMP cost recovery petition, originally filed in July 2017, to include GSMP investments in service as of September 30, 2017. This filing seeks BPU approval to recover in gas base rates an annual revenue increase of $25 million effective January 1, 2018. This increase represents the return of and on investment for GSMP investments in service through September 30, 2017. This proceeding is ongoing.   
Energy Strong Recovery Filing—In March and September of each year, PSE&G files with the BPU for base rate recovery of Energy Strong investments which include a return of and on its investment.
In June 2017, PSE&G submitted the planned update to its March Energy Strong cost recovery petition, originally filed in March 2017, to include Energy Strong investments in service as of May 31, 2017. This filing requested estimated annual increases in electric and gas revenues of $16 million and $2 million, respectively. In August 2017, the BPU approved these rate increases effective September 1, 2017.
In September 2017, PSE&G filed its Energy Strong electric cost recovery petition seeking BPU approval to recover the revenue requirements associated with Energy Strong capitalized investment costs placed in service from June 1, 2017 through November 30, 2017. The petition requests rates to be effective March 1, 2018, consistent with the BPU Order of approval of the Energy Strong program. The annualized requested increase in electric revenue requirement is approximately $9 million. This proceeding is ongoing.   
Basic Gas Supply Services (BGSS)—In June 2017, PSE&G made its annual BGSS filing with the BPU requesting an increase in the BGSS rate from approximately 34 cents to 37 cents per therm effective October 1, 2017. In September 2017, the BPU approved a Stipulation in this matter on a provisional basis and the BGSS rate was increased.
Weather Normalization Clause—In April 2017, the BPU gave final approval to PSE&G’s petition to collect $54 million in net deficiency gas revenues as a result of the warmer than normal 2015-2016 Winter Period.
In June 2017, PSE&G filed a petition requesting approval to collect $55 million in total net deficiency revenues comprised of $31 million in net deficiency gas revenues as a result of the warmer than normal 2016-2017 Winter Period and the remaining carryover balance of $24 million in net deficiency gas revenue from the 2015-2016 Winter Period. The deficiency gas revenue would be collected from customers over the 2017-2018 and 2018-2019 Winter Periods (October 1 through May 31). In September 2017, the BPU approved this petition on a provisional basis with rates effective October 1, 2017, allowing recovery during the 2017-2018 Winter Period.
Green Program Recovery Charges (GPRC)—In August 2017, the BPU approved PSE&G’s petition for an Energy Efficiency 2017 Program (EE 2017) to extend three existing energy efficiency subprograms (multi-family, direct install and hospital efficiency) and establish two new residential energy efficiency offerings. The two new offerings include deployment of smart thermostats and a pilot program to provide residential customers with energy usage information enabling them to reduce consumption. The Order allows PSE&G to extend the subprogram offerings and establish the residential energy efficiency sub-programs under its existing energy efficiency clause recovery process. The EE 2017 allows for $69 million of additional investment and $16 million of additional administrative and information technology costs. The EE 2017 was added as the 11th component of the GPRC rate effective September 1, 2017.
Each year PSE&G files with the BPU for annual recovery for the 11 combined components of its electric and gas Green Program investments which include a return on its investment and recovery of expenses.
In March 2017, the BPU gave final approval to PSE&G’s 2016 GPRC cost recovery petition to recover approximately $37 million and $13 million in electric and gas revenues, respectively, on an annual basis associated with PSE&G’s implementation of these BPU approved GPRC programs for the period October 1, 2016 through September 30, 2017. The rates were effective May 1, 2017. This Order also included the return of approximately $5 million in remaining overcollections from the completed Securitization Transition Charge. 
In June 2017, PSE&G filed its 2017 GPRC cost recovery petition requesting recovery of approximately $47 million and $13 million in electric and gas revenues, respectively, on an annual basis associated with PSE&G's implementation of these BPU-approved programs for the period October 1, 2017 through September 30, 2018. This proceeding is ongoing.
Remediation Adjustment Charge (RAC)—In June 2017, the BPU approved PSE&G's filing with respect to its RAC 24 petition allowing recovery of $41 million effective July 10, 2017 related to net Manufactured Gas Plant expenditures from August 1, 2015 through July 31, 2016.