XML 87 R63.htm IDEA: XBRL DOCUMENT v3.7.0.1
Commitments And Contingent Liabilities (Environmental Matters) (Detail)
6 Months Ended
Jun. 30, 2017
USD ($)
Potentially_Responsible_Party
entity
site
Station
Plant
mi
Mar. 31, 2007
Potentially_Responsible_Party
Site Contingency [Line Items]    
Number of miles related to the Passaic River constituting a facility as determined by the US Environmental Protection Agency | mi 17  
Number of miles on Passaic River tidal reach required to be studied as determined by the US Environmental Protection Agency | mi 8  
Cash out settlement offer for PRPs with minimal responsibility $ 280,600  
Number of additional legal entities contacted by EPA in conjunction with Newark Bay study area contamination | entity 11  
Number of operating electric generating stations located on Hackensack River | Station 2  
Number of former MGP contamination sites located on Hackensack river in conjunction with Newark Bay study area contamination | site 1  
PSE And G [Member]    
Site Contingency [Line Items]    
Percentage of cost attributable to potentially responsible party 7.00%  
Power [Member]    
Site Contingency [Line Items]    
Ownership percentage of Keystone Coal fired plant in Pennsylvania 23.00%  
Psd Nsr Regulations Site Contingency [Member] | Power [Member]    
Site Contingency [Line Items]    
Penalty per day from date of violation-minimum $ 25,000  
Penalty per day from date of violation-maximum $ 37,500  
Pse G S Former Mgp Sites [Member]    
Site Contingency [Line Items]    
Number of potentially responsible parties ("PRPs") in connection with environmental liabilities for operations conducted near Passaic River | Potentially_Responsible_Party 51 73
Loss Contingency, Estimate of Possible Loss $ 190,000,000  
Total Spend of Study to date 163,000,000  
Company Share of Total Spend of Study to date $ 12,000,000  
Pse G S Former Mgp Sites [Member] | Power [Member]    
Site Contingency [Line Items]    
Percentage of cost attributable to potentially responsible party 1.00%  
Passaic River Site Contingency [Member]    
Site Contingency [Line Items]    
Estimated Cleanup Costs EPA Preferred Method $ 2,300,000,000  
Accrual for Environmental Loss Contingencies $ 57,000,000  
Number Of Additional Potentially Responsible Parties Directed By New Jersey Department Of Environmental Protection To Arrange Damage Assessment For Lower Passaic River | Potentially_Responsible_Party 56  
Estimated cleanup costs agreed to by two potentially responsible parties $ 80,000,000  
Estimated cost of interim natural resource injury restoration $ 950,000,000  
Passaic River Site Contingency [Member] | PSE And G [Member]    
Site Contingency [Line Items]    
Number of former generating electric station | Plant 1  
Number of former Manufactured Gas Plant (MGP) sites | Plant 4  
Accrual for Environmental Loss Contingencies, Period Increase (Decrease) $ 36,000,000  
Accrual for Environmental Loss Contingencies 46,000,000  
CPG Targeted Method Cleanup Costs Low Estimate 10,000,000  
Passaic River Site Contingency [Member] | Power [Member]    
Site Contingency [Line Items]    
Accrual for Environmental Loss Contingencies, Period Increase (Decrease) 8,000,000  
Accrual for Environmental Loss Contingencies 11,000,000  
CPG Targeted Method Cleanup Costs Low Estimate 3,000,000  
Mgp Remediation Site Contingency [Member] | PSE And G [Member]    
Site Contingency [Line Items]    
Remediation Liability Recorded As Other Current Liabilities 74,000,000  
Remediation Liability Recorded As Other Noncurrent Liabilities 299,000,000  
Regulatory Assets 373,000,000  
Remedial Investigation And Feasibility Study [Member]    
Site Contingency [Line Items]    
Estimated, total cost of the study 30,000,000  
Estimated Total Cost Of Study Low End of Range $ 25,000,000  
Passaic River mile 10.9 contaminant removal [Member]    
Site Contingency [Line Items]    
Percentage of cost attributable to potentially responsible party 3.00%  
Minimum [Member] | Passaic River Site Contingency [Member]    
Site Contingency [Line Items]    
Loss Contingency, Estimate of Possible Loss $ 518,000,000  
Minimum [Member] | Passaic River Site targeted remedy [Member]    
Site Contingency [Line Items]    
Loss Contingency, Estimate of Possible Loss 518,000,000  
Minimum [Member] | Mgp Remediation Site Contingency [Member] | PSE And G [Member]    
Site Contingency [Line Items]    
Loss Contingency, Estimate of Possible Loss 373,000,000  
Accrual for Environmental Loss Contingencies 373,000,000  
Maximum [Member] | Passaic River Site Contingency [Member]    
Site Contingency [Line Items]    
Loss Contingency, Estimate of Possible Loss 3,200,000,000  
Maximum [Member] | Passaic River Site targeted remedy [Member]    
Site Contingency [Line Items]    
Loss Contingency, Estimate of Possible Loss 772,000,000  
Maximum [Member] | Mgp Remediation Site Contingency [Member] | PSE And G [Member]    
Site Contingency [Line Items]    
Loss Contingency, Estimate of Possible Loss $ 430,000,000