The following information discusses significant updates regarding orders and pending rate filings. This Note should be read in conjunction with Note 5. Regulatory Assets and Liabilities to the Consolidated Financial Statements in the Annual Report on Form 10-K for the year ended December 31, 2014.
In addition to items previously reported in the Annual Report on Form 10-K, significant 2015 regulatory orders received and currently pending rate filings with the FERC and the BPU by PSE&G are as follows:
Energy Strong Recovery Filing—In June 2015, PSE&G updated its Energy Strong cost recovery petition seeking BPU approval to recover in base rates estimated annual increases in electric revenues of $6 million and gas revenues of $17 million. These increases represent recovery of Energy Strong investment costs in service as of May 31, 2015. The petition requests rates to be effective September 1, 2015, consistent with the BPU Order of approval of the Energy Strong program. This matter is pending.
Basic Gas Supply Service (BGSS)—On April 15, 2015, the BPU issued an Order approving PSE&G’s provisional BGSS rate of 45 cents per therm which had been implemented on October 1, 2014. In March 2015, PSE&G filed a letter with the BPU to extend the 28 cents per therm residential rate reduction via a bill credit for one additional month through April 30, 2015, which provided an additional approximate $31 million credit to customers.
On June 1, 2015, PSE&G made its Annual BGSS Filing with the BPU requesting a reduction of $70 million in annual BGSS revenues. If approved, the BGSS rate would be reduced from approximately 45 cents to 40 cents per therm effective October 1, 2015.
Weather Normalization Clause—On April 15, 2015, the BPU approved PSE&G's final filing with respect to excess revenues collected during the colder than normal 2013-2014 Winter Period (October 1, 2013 through May 31, 2014). Effective October 1, 2014, PSEG commenced returning $45 million in revenues to its customers during the 2014-2015 Winter Period (October 1, 2014 through May 31, 2015).
In June 2015, PSE&G filed a petition requesting approval to refund excess revenues collected during the colder than normal 2014-2015 Winter Period. This refund would be made to customers over the 2015-2016 Winter Period (October 1, 2015 through May 31, 2016). Colder weather in the 2014-2015 Winter Period resulted in an excess collection of $40 million of revenues to be refunded to customers.
Solar and Energy Efficiency - Green Program Recovery Charges (GPRC)—In April 2015, the BPU approved PSE&G’s petition for an Energy Efficiency Economic Stimulus Extension II Program (EEE Ext II) to extend three EEE subprograms (multi-family, direct install and hospital efficiency). The Order allows PSE&G to extend the subprogram offerings under the same clause recovery process as its existing EEE Program and allows for $95 million of additional capital expenditures over the next three years and $12 million of additional administrative expenses over the next 15 years. The EEE Ext II program was added as a ninth component of the GPRC rate effective May 1, 2015.
In July of each year, PSE&G files for annual recovery for its Green Program investments which include a return on its investment and recovery of expenses. In May 2015, the BPU approved PSE&G’s July 2014 filing requesting recovery of costs and investments in the first eight combined components of the electric and gas GPRC for the period October 1, 2014 through September 30, 2015. In July 2015, PSE&G filed its annual GPRC cost recovery petition with the BPU once again requesting recovery of costs and investments for the first eight combined components of the electric and gas GPRC. The filing proposes rates for the period October 1, 2015 through September 30, 2016 designed to recover approximately $64 million and $10 million in electric and gas revenues, respectively, on an annual basis associated with PSE&G's implementation of these BPU approved programs. The matter is pending.
Transmission Formula Rate Filings—In June 2015, PSE&G filed its 2014 true-up adjustment pertaining to its formula rates in effect for 2014, which resulted in an adjustment of $19 million less than the 2014 filed revenues. The adjustment was primarily due to the impact of bonus depreciation and lower interest rates which PSE&G had recognized in its Consolidated Statement of Operations for the year ended December 31, 2014.
PSE And G [Member]  
Regulatory Assets [Line Items]  
Rate Filings
Rate Filings
The following information discusses significant updates regarding orders and pending rate filings. This Note should be read in conjunction with Note 5. Regulatory Assets and Liabilities to the Consolidated Financial Statements in the Annual Report on Form 10-K for the year ended December 31, 2014.
In addition to items previously reported in the Annual Report on Form 10-K, significant 2015 regulatory orders received and currently pending rate filings with the FERC and the BPU by PSE&G are as follows:
Energy Strong Recovery Filing—In June 2015, PSE&G updated its Energy Strong cost recovery petition seeking BPU approval to recover in base rates estimated annual increases in electric revenues of $6 million and gas revenues of $17 million. These increases represent recovery of Energy Strong investment costs in service as of May 31, 2015. The petition requests rates to be effective September 1, 2015, consistent with the BPU Order of approval of the Energy Strong program. This matter is pending.
Basic Gas Supply Service (BGSS)—On April 15, 2015, the BPU issued an Order approving PSE&G’s provisional BGSS rate of 45 cents per therm which had been implemented on October 1, 2014. In March 2015, PSE&G filed a letter with the BPU to extend the 28 cents per therm residential rate reduction via a bill credit for one additional month through April 30, 2015, which provided an additional approximate $31 million credit to customers.
On June 1, 2015, PSE&G made its Annual BGSS Filing with the BPU requesting a reduction of $70 million in annual BGSS revenues. If approved, the BGSS rate would be reduced from approximately 45 cents to 40 cents per therm effective October 1, 2015.
Weather Normalization Clause—On April 15, 2015, the BPU approved PSE&G's final filing with respect to excess revenues collected during the colder than normal 2013-2014 Winter Period (October 1, 2013 through May 31, 2014). Effective October 1, 2014, PSEG commenced returning $45 million in revenues to its customers during the 2014-2015 Winter Period (October 1, 2014 through May 31, 2015).
In June 2015, PSE&G filed a petition requesting approval to refund excess revenues collected during the colder than normal 2014-2015 Winter Period. This refund would be made to customers over the 2015-2016 Winter Period (October 1, 2015 through May 31, 2016). Colder weather in the 2014-2015 Winter Period resulted in an excess collection of $40 million of revenues to be refunded to customers.
Solar and Energy Efficiency - Green Program Recovery Charges (GPRC)—In April 2015, the BPU approved PSE&G’s petition for an Energy Efficiency Economic Stimulus Extension II Program (EEE Ext II) to extend three EEE subprograms (multi-family, direct install and hospital efficiency). The Order allows PSE&G to extend the subprogram offerings under the same clause recovery process as its existing EEE Program and allows for $95 million of additional capital expenditures over the next three years and $12 million of additional administrative expenses over the next 15 years. The EEE Ext II program was added as a ninth component of the GPRC rate effective May 1, 2015.
In July of each year, PSE&G files for annual recovery for its Green Program investments which include a return on its investment and recovery of expenses. In May 2015, the BPU approved PSE&G’s July 2014 filing requesting recovery of costs and investments in the first eight combined components of the electric and gas GPRC for the period October 1, 2014 through September 30, 2015. In July 2015, PSE&G filed its annual GPRC cost recovery petition with the BPU once again requesting recovery of costs and investments for the first eight combined components of the electric and gas GPRC. The filing proposes rates for the period October 1, 2015 through September 30, 2016 designed to recover approximately $64 million and $10 million in electric and gas revenues, respectively, on an annual basis associated with PSE&G's implementation of these BPU approved programs. The matter is pending.
Transmission Formula Rate Filings—In June 2015, PSE&G filed its 2014 true-up adjustment pertaining to its formula rates in effect for 2014, which resulted in an adjustment of $19 million less than the 2014 filed revenues. The adjustment was primarily due to the impact of bonus depreciation and lower interest rates which PSE&G had recognized in its Consolidated Statement of Operations for the year ended December 31, 2014.