XML 32 R61.htm IDEA: XBRL DOCUMENT v3.20.1
Regulatory and Rate Matters - PNM (Details)
1 Months Ended 3 Months Ended 6 Months Ended 12 Months Ended
Apr. 15, 2020
USD ($)
MMBTU
numberOfAMIMeters
Feb. 01, 2018
Jan. 10, 2018
USD ($)
Jul. 03, 2017
Dec. 07, 2016
USD ($)
Sep. 28, 2016
USD ($)
lease
MW
Aug. 27, 2015
USD ($)
Aug. 31, 2016
USD ($)
lease
MW
Mar. 31, 2020
USD ($)
MW
Sep. 30, 2019
Mar. 31, 2019
USD ($)
Jun. 30, 2019
USD ($)
Dec. 31, 2019
USD ($)
GWh
Dec. 31, 2017
Mar. 27, 2020
MW
May 16, 2019
MW
Mar. 31, 2017
MW
Jan. 31, 2016
MW
Public Utilities, Commitments And Contingencies [Line Items]                                    
Income taxes (benefit)                 $ 1,880,000   $ (1,223,000)              
Regulatory disallowances and restructuring costs                 $ 0   1,345,000              
Percent of non-fuel revenue requirement change implemented   50.00%                                
Excess return on jurisdictional equity that would require refund                 0.50%                  
PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Income taxes (benefit)                 $ 2,359,000   (1,973,000)              
Regulatory disallowances and restructuring costs                 $ 0   1,345,000              
Solar generation capacity (in megawatts) | MW                             300      
Action plan, covered period       4 years                            
2015 Electric Rate Case | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Requested rate increase (decrease)             $ 123,500,000                      
Requested rate increase (decrease) of non-fuel revenue             $ 121,700,000                      
Approved rate increase (decrease)           $ 61,200,000                        
Renewable Portfolio Standard | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Number of megawatts of Solar PV facilities | MW                 157                  
Current output in the geothermal facility (in megawatts) | MW                 15                  
Solar generation capacity (in megawatts) | MW                 133.0                  
Renewable Energy Rider | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Recorded revenues from renewable rider                 $ 15,100,000   12,700,000              
Revenue from renewable energy rider, year two                 $ 58,900,000                  
Integrated Resource Plan, 2011 | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Frequency of IRP filings                 3 years                  
Planning period covered of IRP                 20 years                  
Integrated Resource Plan, 2017 | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Planning period covered of IRP       20 years                            
Integrated Resource Plan, 2020 | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Planning period covered of IRP                   20 years                
NMPRC                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Requested rate increase (decrease)         $ 99,200,000                          
Requested return on equity         10.125%                          
Period of time for proposed return to customers the benefit of the reduction in New Mexico's corporate income tax rate                           3 years        
Action plan, covered period                 4 years                  
NMPRC | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Requested rate increase (decrease)     $ 10,300,000                              
Requested return on equity     9.575%                              
Period of time for proposed return to customers the benefit of the reduction in New Mexico's corporate income tax rate     3 years                              
Proposed revision to rider that will allow for recovery                         $ 49,600,000          
Required Percentage by 2011 | Renewable Portfolio Standard | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Required percentage of renewable energy in portfolio to electric sales                 10.00%                  
Required Percentage by 2015 | Renewable Portfolio Standard | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Required percentage of renewable energy in portfolio to electric sales                 15.00%                  
Required Percentage by 2020 | Renewable Portfolio Standard | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Required percentage of renewable energy in portfolio to electric sales                 20.00%                  
Minimum | Renewable Portfolio Standard | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Profit incentive sliding scale multiplier                         0.071          
Maximum | Renewable Portfolio Standard | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Reasonable cost threshold in megawatts per hour                 $ 60                  
Palo Verde Nuclear Generating Station, Unit 2 Leases | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Number of megawatts purchased (in megawatts) | MW           64.1   64.1                 64.1 64.1
Number of megawatts nuclear generation (in megawatts) | MW           114.6   114.6               114.6 114.6  
Number of leases under which assets were purchased | lease           3   3                    
Public utilities, aggregate annual rent expense               $ 18,100,000                    
Palo Verde Nuclear Generating Station, Unit 2 Leases | 2015 Electric Rate Case | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Hearing examiner's proposed disallowance of recovery               $ 163,300,000                    
Initial rate base value           $ 83,700,000                        
Disallowance of the recovery undepreciated costs of capitalized leasehold improvements           $ 43,800,000                        
Pre-tax regulatory disallowance                     19,700,000              
New Mexico Wind | Renewable Portfolio Standard 2014 | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Number of megawatts for wind energy | MW                 204                  
Red Mesa Wind | Renewable Portfolio Standard 2014 | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Number of megawatts for wind energy | MW                 102                  
La Joya Wind | Renewable Portfolio Standard | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Number of megawatts for wind energy | MW                 140                  
Four Corners                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Regulatory disallowances and restructuring costs     $ 47,600,000                              
Regulatory disallowance     $ 148,100,000                              
New Mexico 2015 Rate Case | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Pre-tax impairment of investments                     $ 1,300,000 $ 150,600,000            
Undepreciated capitalized improvements                 $ 39,700,000                  
New Mexico 2015 Rate Case | Palo Verde Nuclear Generating Station, Unit 2 Leases | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Number of megawatts purchased (in megawatts) | MW                 64.1             64.1    
Portion of purchase price                 $ 73,200,000                  
Income taxes (benefit)                 45,700,000                  
Leaseholds and Leasehold Improvements | New Mexico 2015 Rate Case | Palo Verde Nuclear Generating Station, Unit 1 and 4 Leases | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Undepreciated capitalized improvements                 $ 37,700,000                  
Subsequent event | Energy Efficiency and Load Management Program | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Energy efficiency and load management programs targeted energy savings (in Gigawatts) | MMBTU 80                                  
Program costs related to energy efficiency, in year two $ 31,400,000                                  
Program costs related to energy efficiency, in year three 31,000,000.0                                  
Program costs related to energy efficiency, in year four $ 29,600,000                                  
Number of AMI meters to be installed | numberOfAMIMeters 5,000                                  
Program costs related to meter installation $ 2,900,000                                  
Subsequent event | Minimum | Renewable Portfolio Standard | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Profit incentive sliding scale multiplier 0.071                                  
Energy efficiency and load management programs targeted energy savings (in Gigawatts) | MMBTU 80                                  
Disincentives and Incentives Added | 2017 Energy Efficiency and Load Management Program | PNM                                    
Public Utilities, Commitments And Contingencies [Line Items]                                    
Energy efficiency and load management programs profit incentive, minimum                         $ 1,800,000          
Energy efficiency and load management programs targeted energy savings (in Gigawatts) | GWh                         59          
Energy efficiency and load management programs additional incentive targeted energy savings (in Gigawatts) | GWh                         68