XML 81 R54.htm IDEA: XBRL DOCUMENT v3.8.0.1
Commitments and Contingencies - Coal Supply (Details)
3 Months Ended 9 Months Ended 12 Months Ended
Feb. 01, 2016
USD ($)
Jan. 31, 2016
USD ($)
Dec. 31, 2015
USD ($)
Sep. 30, 2017
USD ($)
Sep. 30, 2016
USD ($)
Sep. 30, 2017
USD ($)
Sep. 30, 2016
USD ($)
Dec. 31, 2016
USD ($)
Oct. 20, 2017
USD ($)
Jun. 30, 2017
Feb. 01, 2017
Aug. 01, 2016
payment
Public Utilities, Commitments And Contingencies [Line Items]                        
Other current assets       $ 56,421,000   $ 56,421,000   $ 73,444,000        
Regulatory disallowances and restructuring costs       0 $ 16,451,000 0 $ 17,225,000          
PNM                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Other current assets       48,883,000   48,883,000   67,355,000        
Regulatory disallowances and restructuring costs       0 16,451,000 0 $ 17,225,000          
PNM | Surface                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Regulatory assets       100,000,000   100,000,000            
PNM | Loss on long-term purchase commitment | Surface                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Loss contingency accrual       41,400,000   41,400,000   41,000,000        
Final reclamation, capped amount to be collected           100,000,000.0            
PNM | Loss on long-term purchase commitment | Underground                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Loss contingency accrual       14,700,000   14,700,000   14,000,000        
PNM | Loss on long-term purchase commitment | San Juan Generating Station | Surface                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Regulatory disallowances and restructuring costs     $ 16,500,000                  
Estimate of possible loss       100,900,000   100,900,000            
PNM | Loss on long-term purchase commitment | San Juan Generating Station | Underground                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Estimate of possible loss       127,400,000   127,400,000            
Coal supply | PNM | San Juan Generating Station                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Other current assets       31,900,000   31,900,000   48,700,000        
Estimated increase in coal cost                   51.00%    
Coal supply | NM Capital | San Juan Generating Station                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Payments to fund long-term loans to unaffiliated third party   $ 125,000,000.0                    
Loan agreement among several entities   $ 125,000,000.0                    
Interest rate   7.25%                 9.25%  
Requirement to post reclamation bonds       118,700,000   118,700,000            
Cash used to support bank letter or credit arrangement   $ 30,300,000   30,300,000   30,300,000            
Coal supply | NM Capital | San Juan Coal Company, Westmoreland                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Payments to fund long-term loans to unaffiliated third party $ 125,000,000.0                      
Loan receivable   $ 125,000,000   66,200,000   66,200,000            
Scheduled principal payment proceeds       9,600,000   9,600,000            
Scheduled interest payment proceeds       1,800,000   1,800,000            
Prepayment penalty       0   0            
BTMU Term Loan Agreement | NM Capital                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Long-term Debt $ 125,000,000.0     60,900,000   60,900,000            
Subsequent event | Coal supply | Unaffiliated third party | San Juan Coal Company, Westmoreland                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Amount held in a restricted bank account                 $ 11,400,000      
Increase in coal mine decommissioning liability | PNM                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Expense reflected in regulatory disallowances and restructuring costs         $ 4,800,000     $ 4,500,000        
Mine Reclamation Trust | PNM                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Required contribution to Reclamation Trust, current fiscal year       5,800,000   5,800,000            
Reclamation Trust Funding, Year 2       8,300,000   8,300,000            
Reclamation Trust Funding, Year 3       8,700,000   8,700,000            
Four Corners | Mine Reclamation Trust | PNM                        
Public Utilities, Commitments And Contingencies [Line Items]                        
Required contribution to Reclamation Trust, current fiscal year       2,300,000   2,300,000            
Reclamation Trust Funding, Year 2       2,100,000   2,100,000            
Reclamation Trust Funding, Year 3       $ 2,100,000   $ 2,100,000            
Number of annual installment payments | payment                       13