Regulatory and Rate Matters - Proceeding Regarding Definition of Future Test Year (Details) - 2014 Electric Rate Case [Member] - Public Service Company of New Mexico [Member]
Nov. 30, 2015
Jul. 31, 2015
May 27, 2015
Public Utilities, General Disclosures [Line Items]      
Defined future test year as period that begins a period of time following the filing of an application to increase rates (no later than)     45 days
Belief that the correct interpretation of future test year is period time after filing of an application (up to)     13 months
Motion for a temporary stay   30 days  
Redefined future test year as period that begins a period of time following the filing of a rate case application (up to) 13 months