Construction Program and Jointly-Owned Electric Generating Plants
12 Months Ended
Dec. 31, 2015
Construction Program and Jointly-Owned Electric Generating Plants [Abstract]  
Construction Program and Jointly-Owned Electric Generating Plants
Construction Program and Jointly-Owned Electric Generating Plants
PNM is a participant in several jointly-owned power plant projects. The primary operating or participation agreements for the joint projects expire in July 2016 for Four Corners, July 2022 for SJGS, December 2046 for Luna, and November 2047 for PVNGS. The Four Corners owners executed amendments to the agreements governing the operations of Four Corners that would extend those agreements until July 2041. The amendments are expected to become effective in July 2016.
PNM’s expenditures for additions to utility plant were $404.8 million in 2015, including expenditures on jointly-owned projects. TNMP does not participate in the ownership or operation of any generating plants, but incurred expenditures for additions to utility plant of $124.6 million during 2015. On a consolidated basis, PNMR’s expenditures for additions to utility plant were $558.6 million in 2015.
 
Joint Projects

Under the agreements for the jointly-owned projects, PNM has an undivided interest in each asset and liability of the project and records its pro-rata share of each item in the corresponding asset and liability account on PNM’s Consolidated Balance Sheets. Likewise, PNM records its pro-rata share of each item of operating and maintenance expenses for its jointly-owned plants within the corresponding operating expense account in its Consolidated Statements of Earnings. PNM is responsible for financing its share of the capital and operating costs of the joint projects.
At December 31, 2015, PNM’s interests and investments in jointly-owned generating facilities are:
Station (Fuel Type)
Plant in
Service
 
Accumulated
Depreciation
 
Construction
Work in
Progress
 
Composite
Interest
 
(In thousands)
SJGS (Coal) (1)
$
1,083,331

 
$
(428,684
)
 
$
20,117

 
46.30
%
PVNGS (Nuclear) (2)
$
562,412

 
$
(164,549
)
 
$
38,966

 
10.20
%
Four Corners Units 4 and 5 (Coal)
$
167,874

 
$
(102,559
)
 
$
19,390

 
13.00
%
Luna (Gas)
$
69,259

 
$
(23,048
)
 
$
33

 
33.33
%
 
(1) 
As discussed in Note 16, the NMPRC has approved the shutdown of SJGS Units 2 and 3 as of December 31, 2017. At December 31, 2015, PNM’s carrying value for its current ownership share of SJGS Units 2 and 3 included plant in service of $468.2 million, accumulated depreciation and amortization of $193.3 million, and construction work in progress of $2.2 million for a net undepreciated net book value of $277.1 million, which amounts are included in the table above. At December 31, 2015, PNM recorded a regulatory disallowance of $127.6 million representing its estimate of the portion of the December 31, 2017 net book value of SJGS Units 2 and 3 that will not be recovered from ratepayers, which is reflected as a reduction of plant in service on the Consolidated Balance Sheets.
(2) 
Includes interest in PVNGS Unit 3, interest in common facilities for all PVNGS units, and owned interests in PVNGS Units 1 and 2.
San Juan Generating Station
PNM operates and jointly owns SJGS. SJGS Units 1 and 2 are owned on a 50% shared basis with Tucson. SJGS Unit 3 is owned 50% by PNM, 41.8% by SCPPA, and 8.2% by Tri-State. SJGS Unit 4 is owned 38.457% by PNM, 28.8% by MSR, 10.04% by Anaheim, 8.475% by Farmington, 7.2% by Los Alamos, and 7.028% by UAMPS. See Note 16 for additional information about SJGS, including the agreement for restructuring of SJGS ownership. Under the restructuring agreement, PNM would own 64.5% of Unit 4, PNMR Development would own 12.8% of Unit 4, and SCPPA, Tri-State, MSR, and Anaheim would no longer have any ownership interest in SJGS following the December 31, 2017 restructuring. PNMR anticipates that the interest of PNMR Development will be transferred to PNM, as authorized by the NMPRC, prior to the restructuring date.
Palo Verde Nuclear Generating Station
PNM is a participant in the three units of PVNGS, also known as the Arizona Nuclear Power Project, with APS (the operating agent), SRP, EPE, SCE, SCPPA, and The Department of Water and Power of the City of Los Angeles. PNM has a 10.2% undivided interest in PVNGS, with portions of its interests in Units 1 and 2 held under leases. See Note 7 for additional information concerning the PVNGS leases, including PNM’s notices that it will exercise its option to purchase the assets underlying certain of the leases at the expiration of the leases on January 15, 2016.
Operation of each of the three PVNGS units requires an operating license from the NRC. The NRC issued full power operating licenses for Unit 1 in June 1985, Unit 2 in April 1986, and Unit 3 in November 1987. The full power operating licenses were originally for a period of 40 years and authorize APS, as operating agent for PVNGS, to operate the three PVNGS units. On April 21, 2011, the NRC approved extensions in the operating licenses for the plants for 20 years through June 2045 for Unit 1, April 2046 for Unit 2, and November 2047 for Unit 3. In April 2010, APS entered into a Municipal Effluent Purchase and Sale Agreement that provides effluent water rights necessary for cooling purposes at PVNGS through 2050.
Four Corners Power Plant
PNM is a participant in two units of Four Corners with APS (the operating agent), EPE, SRP, and Tucson. PNM has a 13.0% undivided interest in Units 4 and 5 of Four Corners. The Four Corners plant site is leased from the Navajo Nation and is also subject to an easement from the federal government. APS, on behalf of the Four Corners participants, negotiated amendments to an existing facility lease with the Navajo Nation, which extends the Four Corners leasehold interest from 2016 to 2041. See Note 16 for additional information about Four Corners.
Luna Energy Facility
Luna is a combined-cycle power plant near Deming, New Mexico. Luna is owned equally by PNM, Tucson, and Samchully Power & Utilities 1, LLC. The operation and maintenance of the facility has been contracted to North American Energy Services.
Construction Program
The Company anticipates making substantial capital expenditures for the construction and acquisition of utility plant and other property and equipment. An unaudited summary of the budgeted construction expenditures, including expenditures for jointly-owned projects, and nuclear fuel, is as follows:
 
2016
 
2017
 
2018
 
2019
 
2020
 
Total
 
 
 
 
 
(In millions)
 
 
 
 
PNM
$
396.4

 
$
295.1

 
$
269.3

 
$
220.3

 
$
183.7

 
$
1,364.8

TNMP
114.6

 
101.1

 
114.3

 
117.0

 
126.3

 
573.3

Corporate and Other
35.8

 
18.9

 
14.1

 
15.1

 
15.0

 
98.9

Total PNMR
$
546.8

 
$
415.1

 
$
397.7

 
$
352.4

 
$
325.0

 
$
2,037.0


 
The construction expenditure estimates are under continuing review and subject to ongoing adjustment, as well as to Board review and approval. The construction expenditures above include estimated amounts of $1.3 million related to environmental upgrades at SJGS to address regional haze and $100.8 million related to the identified sources of replacement capacity under the revised plan for compliance described in Note 16. The above construction expenditures also include environmental upgrades at Four Corners estimated to be $88.7 million, and the $163.3 million purchase of the assets underlying three of the PVNGS Unit 2 leases at the expiration of those leases on January 15, 2016.