Regulatory Matters
3 Months Ended
Mar. 31, 2015
Regulated Operations [Abstract]  
Regulatory Matters
REGULATORY MATTERS
RATE RELATED INFORMATION
The NCUC, PSCSC, FPSC, IURC, PUCO and KPSC approve rates for retail electric and natural gas services within their states. The FERC approves rates for electric sales to wholesale customers served under cost-based rates (excluding Ohio and Indiana), as well as sales of transmission service.
Duke Energy Carolinas
William States Lee Combined Cycle Facility
On April 9, 2014, the PSCSC granted Duke Energy Carolinas and North Carolina Electric Membership Corporation (NCEMC) a Certificate of Environmental Compatibility and Public Convenience and Necessity (CECPCN) for the construction and operation of a 750 MW combined cycle natural gas-fired generating plant at Duke Energy Carolinas' existing William States Lee Generating Station in Anderson, South Carolina. On May 16, 2014, Duke Energy Carolinas announced its intention to begin construction in summer 2015 and estimates a cost to build of $600 million for its share of the facility, including allowance for funds used during construction (AFUDC). The project is expected to be commercially available in late 2017. NCEMC will own approximately 13 percent of the project. On July 3, 2014, the South Carolina Coastal Conservation League (SCCCL) and Southern Alliance for Clean Energy (SACE) jointly filed a Notice of Appeal with the Court of Appeals of South Carolina seeking the court's review of the PSCSC's decision. The case has been fully briefed and is pending in the Court of Appeals. Duke Energy Carolinas cannot predict the outcome of this matter.
Duke Energy Progress
Sutton Black Start Combustion Turbine CPCN
On April 15, 2015, Duke Energy Progress filed a CPCN application with the NCUC for approval to construct an 84 MW black start combustion turbine (CT) project at the existing Sutton plant (Sutton Black Start CT Project). The Sutton Black Start CT Project would replace three existing CTs with total capacity of 61 MW with two new 42 MW CT units with black start and fast start capability. In addition to peaking system capacity, the Sutton Black Start CT Project will provide regional black start capability and tertiary backup power services for the Brunswick Nuclear Plant. The NCUC has scheduled an evidentiary hearing on June 22, 2015 and a decision is expected by October 2015.
Duke Energy Florida
FERC Transmission Return on Equity Complaint
Seminole Electric Cooperative, Inc. and Florida Municipal Power Agency filed multiple complaints with the FERC alleging Duke Energy Florida's current rate of return on equity in transmission formula rates of 10.8 percent is unjust and unreasonable. The latest complaint, filed on August 12, 2014, claims the rate of return should be reduced to 8.69 percent. The FERC consolidated all complaints for the purposes of settlement, hearing and decision. The parties are engaged in settlement discussions. The outcome of this matter is not expected to be material.
Citrus County Combined Cycle Facility
On October 2, 2014, the FPSC granted Duke Energy Florida a Determination of Need for the construction of a 1,640 MW combined cycle natural gas plant in Citrus County, Florida. The facility is expected to be commercially available in 2018 at an estimated cost of $1.5 billion, including AFUDC. Additional environmental and governmental approvals will be sought for the Citrus County project.
Purchase of Osprey Energy Center
In December 2014, Duke Energy Florida and Osprey Energy Center, LLC, a wholly owned subsidiary of Calpine Corporation (Calpine), entered into an Asset Purchase and Sale Agreement for the purchase of a 599 MW combined cycle natural gas plant in Auburndale, Florida (Osprey Plant acquisition) for approximately $166 million. Closing is subject to the approval of the FERC, FPSC and the expiration of the Hart Scott Rodino waiting period and is expected to occur by the first quarter of 2017 upon the expiration of an existing Power Purchase Agreement between Calpine and Duke Energy Florida.
On January 30, 2015, Duke Energy Florida petitioned the FPSC requesting a determination that the Osprey Plant acquisition or, alternatively, the construction of a 320 MW combustion turbine at its existing Suwannee generating facility with an estimated cost of $197 million is the most cost-effective generation alternative to meet Duke Energy Florida's remaining generation need prior to 2018. A hearing with the FPSC is scheduled for June 2015. On March 13, 2015, Duke Energy Florida made a filing requesting FERC approval of the Osprey Plant acquisition by July 30, 2015. In the FERC proceeding, no protests were filed. Seminole Electric Cooperative intervened to request clarification concerning the transmission facilities to be constructed in connection with the Osprey Plant acquisition. If timely approval of the Osprey Plant acquisition is not received from the FERC, the Suwannee project would be constructed.
Duke Energy Ohio
2014 Electric Security Plan
In April 2015, the PUCO modified and approved Duke Energy Ohio's proposed ESP, with a three-year term and an effective date of June 1, 2015. The PUCO approved a competitive procurement process for SSO load, a distribution capital investment rider, and a tracking mechanism for incremental distribution expenses caused by major storms. The PUCO order also approved a placeholder tariff for a price stabilization rider, but denied Duke Energy Ohio's specific request to include OVEC in the rider at this time; however, the order allows Duke Energy Ohio to submit additional information to request recovery in the future. On May 4, 2015, Duke Energy Ohio filed an application for rehearing requesting the PUCO to modify or amend certain aspects of the order.
2012 Natural Gas Rate Case
On November 13, 2013, the PUCO issued an order approving a settlement among Duke Energy Ohio, the PUCO Staff and intervening parties (the Gas Settlement). The Gas Settlement provided for (i) no increase in base rates for natural gas distribution service and (ii) a return on equity of 9.84 percent. The Gas Settlement provided for a subsequent hearing on Duke Energy Ohio’s request for rider recovery of environmental remediation costs associated with its former manufactured gas plant (MGP) sites. After the conclusion of the evidentiary hearing and briefs, the PUCO authorized Duke Energy Ohio to recover $56 million, excluding carrying costs, of environmental remediation costs. The MGP rider became effective in April 2014 for a five-year period. On March 31, 2014, Duke Energy Ohio filed an application with the PUCO to adjust the MGP rider for investigation and remediation costs incurred in 2013.
Certain consumer groups appealed the PUCO’s decision to the Ohio Supreme Court and further asked the court to stay implementation of the PUCO’s order and collections under the MGP rider pending their appeal. The Ohio Supreme Court granted the motion to stay and subsequently required the posting of a bond to effectuate the stay. When the bond was not posted, the PUCO approved Duke Energy Ohio’s request, in January 2015, to reinstate collections under the MGP rider and Duke Energy Ohio resumed billings. Amounts collected prior to the suspension of the rider were immaterial. On March 31, 2015, Duke Energy Ohio filed an application to adjust the MGP rider to recover remediation costs incurred in 2014. Duke Energy Ohio cannot predict the outcome of the appeal of this matter.
Regional Transmission Organization (RTO) Realignment
Duke Energy Ohio, including Duke Energy Kentucky, transferred control of its transmission assets from Midcontinent Independent System Operator, Inc. (MISO) to PJM Interconnection, LLC (PJM), effective December 31, 2011.
On December 22, 2010, the KPSC approved Duke Energy Kentucky’s request to effect the RTO realignment, subject to a commitment not to seek double recovery in a future rate case of the transmission expansion fees that may be charged by MISO and PJM in the same period or overlapping periods.
On May 25, 2011, the PUCO approved a settlement between Duke Energy Ohio, Ohio Energy Group, the Office of Ohio Consumers’ Counsel and the PUCO Staff related to Duke Energy Ohio’s recovery of certain costs of the RTO realignment via a non-bypassable rider. Duke Energy Ohio is allowed to recover all MISO Transmission Expansion Planning (MTEP) costs, including but not limited to Multi-Value Project (MVP) costs, directly or indirectly charged to Ohio customers. Duke Energy Ohio also agreed to vigorously defend against any charges for MVP projects from MISO.
Upon its exit from MISO on December 31, 2011, Duke Energy Ohio recorded a liability for its exit obligation and share of MTEP costs, excluding MVP. This liability was recorded within Other in Current liabilities and Other in Deferred credits and other liabilities on Duke Energy Ohio’s Condensed Consolidated Balance Sheets.
The following table provides a reconciliation of the beginning and ending balances of Duke Energy Ohio’s recorded obligations related to its withdrawal from MISO. As of March 31, 2015, $73 million is recorded as a Regulatory asset on Duke Energy Ohio's Condensed Consolidated Balance Sheets.
(in millions)
December 31, 2014

 
Provision /
Adjustments

 
Cash
Reductions

 
March 31, 2015

Duke Energy Ohio
$
94

 
$

 
$
(1
)
 
$
93


MVP. MISO approved 17 MVP proposals prior to Duke Energy Ohio’s exit from MISO on December 31, 2011. Construction of these projects is expected to continue through 2020. Costs of these projects, including operating and maintenance costs, property and income taxes, depreciation and an allowed return, are allocated and billed to MISO transmission owners.
On December 29, 2011, MISO filed a tariff with the FERC providing for the allocation of MVP costs to a withdrawing owner based on monthly energy usage. The FERC set for hearing (i) whether MISO’s proposed cost allocation methodology to transmission owners who withdrew from MISO prior to January 1, 2012 is consistent with the tariff at the time of their withdrawal from MISO, and, (ii) if not, what the amount of and methodology for calculating any MVP cost responsibility should be. On July 16, 2013, a FERC Administrative Law Judge (ALJ) issued an initial decision. Under this initial decision, Duke Energy Ohio would be liable for MVP costs. Duke Energy Ohio filed exceptions to the initial decision, requesting the FERC overturn the ALJ’s decision. After reviewing the initial decision, along with all exceptions and responses filed by the parties, the FERC will issue a final decision. Duke Energy Ohio fully intends to appeal to the federal court of appeals if the FERC affirms the ALJ’s decision. Duke Energy Ohio cannot predict the outcome of these proceedings.
In 2012, MISO estimated Duke Energy Ohio’s MVP obligation over the period from 2012 to 2071 at $2.7 billion, on an undiscounted basis. The estimated obligation is subject to great uncertainty including the ultimate cost of the projects, the annual costs of operations and maintenance, taxes and return over the project lives, the number of years in service for the projects and the allocation to Duke Energy Ohio.
Any liability related to the MISO MVP matter attributable to the Disposal Group was not transferred to Dynegy upon the sale of the nonregulated Midwest generation business.
FERC Transmission Return on Equity and MTEP Cost Settlement
On October 14, 2011, Duke Energy Ohio and Duke Energy Kentucky submitted with the FERC proposed modifications to the PJM Interconnection Open Access Transmission Tariff pertaining to recovery of the transmission revenue requirement as PJM transmission owners. The filing was made in connection with Duke Energy Ohio's and Duke Energy Kentucky's move from MISO to PJM effective January 1, 2012. On April 24, 2012, the FERC issued an order accepting the proposed filing effective January 1, 2012, except that the order denied a request to recover certain costs associated with the move from MISO to PJM without prejudice to the right to submit another filing seeking such recovery and including certain additional evidence, and set the rate of return on equity of 12.38 percent for settlement and hearing. On April 16, 2015, the FERC approved a settlement agreement between Duke Energy Ohio, Duke Energy Kentucky and six PJM transmission customers with load in the Duke Energy Ohio and Duke Energy Kentucky zone. The principal terms of the settlement agreement are that, effective upon the date of FERC approval, (i) the return on equity for wholesale transmission service is reduced to 11.38 percent, (ii) the settling parties agreed not to seek a change in the return on equity that would be effective prior to June 1, 2017 and (iii) Duke Energy Ohio and Duke Energy Kentucky will recover 30 percent of the wholesale portion of costs arising from their obligation to pay any portion of the costs of projects included in any MTEP that was approved prior to the date of Duke Energy Ohio's and Duke Energy Kentucky's integration into PJM.
Duke Energy Indiana
Edwardsport Integrated Gasification Combined Cycle (IGCC) Plant
On November 20, 2007, the IURC granted Duke Energy Indiana a CPCN for the construction of the Edwardsport IGCC power plant. The Citizens Action Coalition of Indiana, Inc., Sierra Club, Inc., Save the Valley, Inc., and Valley Watch, Inc. (collectively, the Joint Intervenors) were intervenors in several matters related to the Edwardsport IGCC Plant.
The Edwardsport IGCC plant was placed in commercial operation in June 2013. Costs for the Edwardsport IGCC plant are recovered from retail electric customers via a tracking mechanism, the IGCC rider. Updates to the IGCC rider are filed semi-annually. An order on the eleventh semi-annual IGCC rider is currently pending. The twelfth and thirteenth semi-annual IGCC riders were combined for hearings which were held in February 2015. Issues in this proceeding include whether the IGCC plant was properly declared in service for ratemaking purposes in June 2013 and the operational performance of the plant during its initial ten months of operations.
The ninth and tenth semi-annual IGCC rider orders have been appealed by the Joint Intervenors. On August 21, 2014, the Indiana Court of Appeals affirmed the IURC order in the tenth IGCC rider proceeding and on October 29, 2014 denied Joint Intervenors' request for rehearing. The Joint Intervenors requested the Indiana Supreme Court to review the decision, which was denied on April 23, 2015, concluding the appeal. On September 8, 2014, the Indiana Court of Appeals remanded the IURC order in the ninth IGCC rider proceeding back to the IURC for further findings. On February 25, 2015, the IURC issued a new order upholding its prior decision and providing additional detailed findings. Joint Intervenors have appealed this remand order to the Indiana Court of Appeals.
On April 2, 2014, the IURC established a subdocket to Duke Energy Indiana’s current fuel adjustment clause proceeding. In this fuel adjustment subdocket, the IURC intends to review underlying causes for net negative generation amounts at the Edwardsport IGCC plant during the period September through November 2013. Duke Energy Indiana contends the net negative generation is related to the consumption of fuel and auxiliary power when the plant was in start-up or off line. In addition to the OUCC, the Duke Energy Indiana Industrial Group, Nucor Steel-Indiana, Steel Dynamics, Inc., and the Joint Intervenors are parties to the subdocket. The IURC has deferred the fuel adjustment subdocket until resolution of the twelfth and thirteenth semi-annual IGCC rider proceedings. In addition, although the IURC approved fuel adjustment clause recovery for the period December 2013 through March 2014, it determined such fuel costs reasonably related to the operational performance of the Edwardsport IGCC plant shall be subject to refund pending the outcome of the twelfth and thirteenth semi-annual IGCC riders.
Duke Energy Indiana cannot predict the outcome of the fuel adjustment clause proceedings or pending and future IGCC rider proceedings.
FERC Transmission Return on Equity Complaint
Customer groups have filed with the FERC complaints against MISO and its transmission-owning members, including Duke Energy Indiana, alleging, among other things, that the current base rate of return on equity earned by MISO transmission owners of 12.38 percent is unjust and unreasonable. The latest complaint, filed on February 12, 2015, claims the base rate of return should be reduced to 8.67 percent and requests a consolidation of complaints. On January 5, 2015, the FERC issued an order accepting the MISO transmission owners 0.50 percent adder to the base rate of return on equity based on participation in an RTO subject to it being applied to a return on equity that is shown to be just and reasonable in the pending return on equity complaint. Settlement procedures in the base return on equity proceeding were terminated and a hearing is scheduled for August 17, 2015. Duke Energy Indiana cannot predict the outcome of this matter.
Grid Infrastructure Improvement Plan
On August 29, 2014, Duke Energy Indiana filed a seven-year grid infrastructure improvement plan with the IURC with an estimated cost of $1.9 billion, focusing on the reliability, integrity and modernization of the transmission and distribution system. If approved, 80 percent of the costs will be recovered through a rate tracker. The remaining 20 percent are subject to deferral and subsequent recovery through future rate case proceedings. Hearings were held in January 2015 and Duke Energy Indiana expects a decision in mid-2015.
OTHER REGULATORY MATTERS
Atlantic Coast Pipeline
On September 2, 2014, Duke Energy, Dominion Resources (Dominion), Piedmont Natural Gas and AGL Resources announced the formation of a company, Atlantic Coast Pipeline, LLC (ACP), to build and own the proposed Atlantic Coast Pipeline (the pipeline), a 550-mile interstate natural gas pipeline. The pipeline is designed to meet the needs identified in requests for proposals by Duke Energy Carolinas, Duke Energy Progress and Piedmont Natural Gas. Dominion will build and operate the pipeline and will own 45 percent. Duke Energy will have a 40 percent ownership interest in ACP through its Commercial Power segment. The remaining share will be owned by Piedmont Natural Gas and AGL Resources. Duke Energy Carolinas and Duke Energy Progress, among others, will be customers of the pipeline. Purchases will be made under several 20-year supply contracts, subject to state regulatory approval. In October 2014, the NCUC and PSCSC approved the Duke Energy Carolinas and Duke Energy Progress requests to enter into certain affiliate agreements, pay compensation to ACP and to grant a waiver of certain Code of Conduct provisions relating to contractual and jurisdictional matters. The project will require FERC approval, which ACP will seek to secure by summer 2016. The estimated in-service date of the pipeline is late 2018.
Sabal Trail Transmission, LLC Pipeline
On May 4, 2015, Duke Energy acquired a 7.5 percent ownership interest from Spectra Energy in the proposed 500-mile Sabal Trail natural gas pipeline. Spectra Energy will continue to own 59.5 percent of the pipeline and NextEra Energy will own the remaining 33 percent of the pipeline. The pipeline will traverse Alabama, Georgia and Florida to meet rapidly growing demand for natural gas in those states. The primary customers of the pipeline, Duke Energy Florida and Florida Power & Light Company, have each contracted to buy pipeline capacity for 25-year initial terms. The pipeline, scheduled to begin service in 2017, requires federal and other regulatory approvals. 
NC WARN FERC Complaint
On December 16, 2014, NC WARN filed a complaint with the FERC against Duke Energy Carolinas and Duke Energy Progress that alleged (i) Duke Energy Carolinas and Duke Energy Progress manipulated the electricity market by constructing costly and unneeded generation facilities leading to unjust and unreasonable rates; (ii) Duke Energy Carolinas and Duke Energy Progress failed to comply with Order 1000 by not effectively connecting their transmission systems with neighboring utilities which also have excess capacity; (iii) the plans of Duke Energy Carolinas and Duke Energy Progress for unrealistic future growth lead to unnecessary and expensive generating plants; (iv) the FERC should investigate the practices of Duke Energy Carolinas and Duke Energy Progress and the potential benefits of having them enter into a regional transmission organization; and (v) the FERC should force Duke Energy Carolinas and Duke Energy Progress to purchase power from other utilities rather than construct wasteful and redundant power plants. A copy of the complaint was filed with the PSCSC on January 6, 2015. Duke Energy Carolinas and Duke Energy Progress have filed responses requesting dismissal of the complaint with the FERC and the PSCSC. In April 2015, the FERC and the PSCSC issued separate orders dismissing the NC WARN petition.
Planned and Potential Coal Plant Retirements
The Subsidiary Registrants periodically file Integrated Resource Plans (IRP) with their state regulatory commissions. The IRPs provide a view of forecasted energy needs over a long term (10 to 20 years), and options being considered to meet those needs. Recent IRPs filed by the Subsidiary Registrants included planning assumptions to potentially retire certain coal-fired generating facilities in Florida, Ohio and Indiana earlier than their current estimated useful lives. These facilities do not have the requisite emission control equipment, primarily to meet United States Environmental Protection Agency (EPA) regulations recently approved or proposed.
The table below contains the net carrying value of generating facilities planned for retirement or being evaluated for potential retirement included in recent IRPs. Dollar amounts in the table below are included in Net property, plant and equipment on the Condensed Consolidated Balance Sheets.
 
March 31, 2015
 
Duke Energy

 
Progress Energy(b)

 
Duke Energy Florida(b)

 
Duke Energy Ohio(c)

 
Duke Energy Indiana(d)

Capacity (in MW)
1,704

 
873

 
873

 
163

 
668

Remaining net book value (in millions)(a)
$
243

 
$
120

 
$
120

 
$
9

 
$
114

(a)
Included in Property, plant and equipment, net as of March 31, 2015, on the Condensed Consolidated Balance Sheets.
(b)
Includes Crystal River Units 1 and 2.
(c)
Includes Miami Fort Unit 6, which is expected to be retired by June 1, 2015.
(d)
Includes Wabash River Units 2 through 6. Wabash River Unit 6 is being evaluated for potential conversion to natural gas. Duke Energy Indiana committed to retire or convert the Wabash River Units 2 through 5 by June 2018 in conjunction with a settlement agreement associated with the Edwardsport air permit.
In addition to evaluations based on the extent facilities are equipped to comply with environmental regulations, Duke Energy continually monitors and evaluates the appropriate generation mix and fuel diversity for its generation fleet when making retirement decisions. Duke Energy Carolinas and Duke Energy Progress are evaluating the potential for coal-fired generating unit retirements with a net carrying value of approximately $110 million and $150 million, respectively, included in Net property, plant and equipment on the Condensed Consolidated Balance Sheets.
Duke Energy continues to evaluate the potential need to retire generating facilities earlier than the current estimated useful lives, and plans to seek regulatory recovery, as necessary, for amounts that would not be otherwise recovered when any of these assets are retired. However, such recovery, including recovery of carrying costs on remaining book values, could be subject to future regulatory approvals and therefore cannot be assured.