ENVIRONMENTAL

Duke Energy is subject to international, federal, state, and local regulations regarding air and water quality, hazardous and solid waste disposal, and other environmental matters. The Subsidiary Registrants are subject to federal, state, and local regulations regarding air and water quality, hazardous and solid waste disposal and other environmental matters. These regulations can be changed from time to time, imposing new obligations on the Duke Energy Registrants.

The following environmental matters impact all of the Duke Energy Registrants.

Remediation Activities

The Duke Energy Registrants are responsible for environmental remediation at various contaminated sites. These include some properties that are part of ongoing operations and sites formerly owned or used by Duke Energy entities. These sites are in various stages of investigation, remediation, and monitoring. Managed in conjunction with relevant federal, state, and local agencies, activities vary with site conditions and locations, remediation requirements, complexity, and sharing of responsibility. If remediation activities involve joint and several liability provisions, strict liability, or cost recovery or contribution actions, the Duke Energy Registrants could potentially be held responsible for contamination caused by other parties. The Duke Energy Registrants may share liability associated with contamination with other potentially responsible parties, and may also benefit from insurance policies or contractual indemnities that cover some or all cleanup costs. The Duke Energy Registrants continually assess the nature and extent of known or potential environmental contingencies. Liabilities are recorded when losses become probable and are reasonably estimable. The Duke Energy Registrants have accrued costs associated with remediation activities at some of their current and former sites for the stages of investigation, remediation, and monitoring that can be reasonably estimated, as well as other relevant environmental contingent liabilities. The Duke Energy Registrants cannot estimate the total costs that may be incurred in connection with the remediation at all stages of all sites because the extent of environmental impact, allocation among potentially responsible parties, remediation alternatives, and/or regulatory decisions have not yet been determined. Additional costs associated with remediation activities at certain sites are likely to be incurred in the future. These additional costs could be significant. Costs associated with remediation activities within the Duke Energy Registrants' operations are typically expensed as Operation, maintenance and other in the Condensed Consolidated Statements of Operations unless regulatory recovery of the costs is deemed probable.

The following table contains information regarding reserves for probable and estimable costs related to the Duke Energy Registrants' various environmental sites. These amounts are recorded in Other within Deferred Credits and Other Liabilities on the Duke Energy Registrants' Condensed Consolidated Balance Sheets.

                      
(in millions)Duke Energy Duke Energy Carolinas Progress Energy Duke Energy Progress Duke Energy Florida Duke Energy Ohio Duke Energy Indiana
Balance at December 31, 2011$ 61 $ 12 $ 23 $ 11 $ 12 $ 28 $ 9
Provisions / adjustments  43   1   16   4   12   10   2
Cash reductions  (19)     (7)   (2)   (5)   (15)   (2)
Balance at September 30, 2012$ 85 $ 13 $ 32 $ 13 $ 19 $ 23 $ 9
                      
                      
Balance at December 31, 2012$ 75 $ 12 $ 33 $ 14 $ 19 $ 15 $ 8
Provisions / adjustments  6     5   1   4   (1)   1
Cash reductions  (17)     (6)   (2)   (4)   (8)   (2)
Balance at September 30, 2013$ 64 $ 12 $ 32 $ 13 $ 19 $ 6 $ 7
                      

The PUCO has approved Duke Energy Ohio's deferral of the costs incurred for probable and estimable costs related to the MGP environmental sites. Duke Energy Ohio is seeking recovery of those costs in its natural gas distribution rate case as discussed in Note 4.

Additional losses in excess of recorded reserves the Duke Energy Registrants' could incur for the stages of investigation, remediation, and monitoring for their environmental sites that can be reasonably estimated at this time are presented in the table below.

       
(in millions)   
Duke Energy   $ 75
Duke Energy Carolinas     29
Progress Energy     6
Duke Energy Progress     3
Duke Energy Florida     3
Duke Energy Ohio     35
Duke Energy Indiana     5
       

Clean Water Act 316(b)

The EPA proposed a cooling water intake structures rule on April 20, 2011. The proposed rule advances one main approach and three alternatives. The main approach establishes aquatic protection requirements for existing facilities that withdraw 2 million gallons or more of water per day from U.S. water sources for cooling purposes. Based on the main approach proposed, most, if not all of the steam electric generating facilities the Duke Energy Registrants own are likely affected sources unless retired prior to implementation of the 316(b) requirements.

The deadline for issuance of the final 316(b) rule is November 2013. If the rule is finalized as proposed, modifications to the intakes could be required as early as mid- to-late 2017. The Duke Energy Registrants are unable to predict the outcome of this rulemaking.

Cross-State Air Pollution Rule (CSAPR)

On August 8, 2011, the final Cross-State Air Pollution Rule (CSAPR) was published in the Federal Register. The CSAPR established state-level annual sulfur dioxide (SO2) budgets and annual seasonal nitrogen oxide (NOx) budgets that were to take effect on January 1, 2012.

On August 21, 2012, the D.C. Circuit Court vacated the CSAPR. The court also directed the EPA to continue administering the Clean Air Interstate Rule (CAIR). The Duke Energy Registrants have been complying with the CAIR since 2009. The CAIR requires additional reductions in SO2 and NOx emissions beginning in 2015. On June 24, 2013, the U.S. Supreme Court (Supreme Court) granted the EPA's petitions for a writ of certiorari. Oral arguments will be heard on December 10, 2013. The Supreme Court is likely to issue its decision on the merits by mid-2014.

The Duke Energy Registrants cannot predict the outcome of the proceedings. Continued compliance with the CAIR pending the outcome of the rehearing process will not result in the Duke Energy Registrants adding new emission controls.

Coal Combustion Residuals (CCR)

On June 21, 2010, the EPA proposed a regulation under the Resource Conservation and Recovery Act, related to coal combustion residuals (CCR). CCR is a term the EPA uses to describe the coal combustion byproducts associated with the generation of electricity. The EPA proposal contains two regulatory options whereby CCRs not employed in approved beneficial use applications would either (i) be regulated as hazardous waste or (ii) continue to be regulated as non-hazardous waste.

On October 29, 2013, the U.S. District Court for the District of Columbia ordered the EPA to complete the timeline for CCR rulemaking within 60 days. The Duke Energy Registrants cannot predict the outcome of this rulemaking, but the impact could be significant.

Steam Electric Effluent Limitation Guidelines

On June 7, 2013, the EPA proposed Steam Electric Effluent Limitations Guidelines (ELGs). The EPA is under a court order to complete a final rule by May 22, 2014. The EPA has proposed eight options for the rule, which vary in stringency and cost. The proposed regulation applies to seven waste streams, including wastewater from air pollution control equipment and ash transport water. Most, if not all of the steam electric generating facilities the Duke Energy Registrants own are likely affected sources. Compliance is proposed as soon as possible after July 1, 2017, but may extend until July 1, 2022. The Duke Energy Registrants are unable to predict the outcome of the rulemaking, but the impact could be significant.

Greenhouse Gas New Source Performance Standards (NSPS)

On September 20, 2013, the EPA proposed a rule to establish carbon dioxide (CO2) emissions standards for new pulverized coal, IGCC, and natural gas combined cycle electric generating units commencing construction on or after the date the proposal appears in the Federal Register. Any future coal and IGCC units will be required to employ carbon capture and storage technology to meet the proposed CO2 emission standard.

 

The Duke Energy Registrants do not expect a material impact on their future results of operations or cash flows based on the EPA's proposal. The final rule, however, could be significantly different from the proposal. It is not known when the EPA might finalize the rule.

On June 25, 2013, the President of the United States issued a memorandum directing the EPA to propose CO2 emissions requirements for existing fossil-fueled electric generating units by June 1, 2014, and to finalize the guidelines for states to develop their own regulations for implementing the guidelines by June 1, 2015. The memorandum directed the EPA to require states to submit their implementation regulations for approval by June 30, 2016.

The Duke Energy Registrants are unable to predict the outcome of this rulemaking.

Mercury and Air Toxics Standards (MATS)

The final Mercury and Air Toxics Standards rule, previously referred to as the Utility MACT Rule, was issued on February 16, 2012. The final rule establishes emission limits for hazardous air pollutants from new and existing coal-fired and oil-fired steam electric generating units. The rule requires sources to comply with emission limits by April 16, 2015. Under the Clean Air Act (CAA), permitting authorities have the discretion to grant up to a one-year compliance extension, on a case-by-case basis, to sources that are unable to complete the installation of emission controls before the compliance deadline. The Duke Energy Registrants continue to develop and implement strategies for complying with the rule. Strategies to achieve compliance with the final rule will include installing new air emission control equipment, developing monitoring processes, fuel switching, and accelerating retirement of some coal-fired electric-generating units. For additional information, refer to Note 4 regarding potential plant retirements.

Numerous petitions for review of the final rule have been filed with the D.C. Circuit Court. Oral arguments have not been scheduled. The Duke Energy Registrants cannot predict the outcome of the litigation or how it might affect their compliance with the MATS requirements.

Refer to the table below for a summary of estimated costs to comply with the MATS regulations.

Estimated Cost and Impacts of EPA Rulemakings

The ultimate compliance requirements for MATS, Clean Water 316(b), CCRs and ELGs will not be known until all the rules have been finalized. However, for planning purposes, the Duke Energy Registrants currently estimate the cost of new control equipment that may need to be installed on existing power plants to comply with these EPA regulations could total $5 billion to $6 billion, excluding AFUDC, over the next 10 years. The table below includes estimated costs for new control equipment necessary to comply with the MATS rule, which is the only rule that has been finalized

      
(in millions)Range
Duke Energy$ 650- 800
Duke Energy Carolinas  65- 85
Progress Energy  7- 30
Duke Energy Progress  5- 10
Duke Energy Florida  2- 20
Duke Energy Ohio  40- 85
Duke Energy Indiana  540- 600
      

The Duke Energy Registrants also expect to incur increased fuel, purchased power, operation and maintenance, and other expenses, and costs for replacement generation for potential coal-fired power plant retirements as a result of these EPA regulations. Until the final regulatory requirements are known and can be fully evaluated, the potential compliance costs associated with these EPA regulatory actions are subject to considerable uncertainty. Therefore, the actual compliance costs incurred may be materially different from these estimates based on the timing and requirements of the final EPA regulations. The Duke Energy Registrants intend to seek regulatory recovery of amounts incurred associated with regulated operations in complying with these regulations. Refer to Note 4 for further information regarding potential plant retirements and regulatory filings related to the Duke Energy Registrants.

LITIGATION

Duke Energy

Progress Energy Merger Shareholder Litigation

On May 31, 2013, the Delaware Chancery Court consolidated four shareholder derivative lawsuits filed in 2012. The Court also appointed a lead plaintiff and counsel for plaintiffs and designated the case as In Re Duke Energy Corporation Derivative Litigation. The lawsuit names as defendants James E. Rogers and the ten other members of the Duke Energy board of directors who were also members of the pre-merger Duke Energy board of directors (Legacy Duke Energy Directors). Duke Energy is named as a nominal defendant. The case alleges claims for breach of fiduciary duties of loyalty and care in connection with the post-merger change in CEO. On October 1, 2013, defendants filed a motion to stay the case pending final disposition of the Nieman v. Duke Energy Corporation, et al. case in North Carolina. A decision is pending on the motion to stay.

On August 3, 2012, Duke Energy was served with a shareholder Derivative Complaint, which was transferred to the North Carolina Business Court (Krieger v. Johnson, et al.). The lawsuit names as defendants, William D. Johnson, James E. Rogers and the Legacy Duke Energy Directors. Duke Energy is named as a nominal defendant. The lawsuit alleges claims for breach of fiduciary duty in granting excessive compensation to Mr. Johnson. A decision on a motion to dismiss made by Mr. Rogers and the Legacy Duke Energy Directors remains pending.

Two shareholder Derivative Complaints, filed in 2012 in federal district court in Delaware, were consolidated as Tansey v. Rogers, et al. The case alleges claims for breach of fiduciary duty and waste of corporate assets, as well as claims under Section 14(a) and 20(a) of the Exchange Act. Duke Energy is named as a nominal defendant. On May 17, 2013, the judge granted defendants' motion to stay the litigation until a decision is rendered on the motion to dismiss in the Nieman v. Duke Energy Corporation, et al. case in North Carolina.

Duke Energy, the Legacy Duke Energy Directors and certain Duke Energy officers are also defendants in a purported securities class action lawsuit (Nieman v. Duke Energy Corporation, et al)This lawsuit consolidates three lawsuits originally filed in July 2012, and is pending in the United States District Court for the Western District of North Carolina. The plaintiffs allege federal Securities Act and Exchange Act claims based on allegations of materially false and misleading representations and omissions in the Registration Statement filed on July 7, 2011, and purportedly incorporated into other documents, all in connection with the post-merger change in CEO. The claims are purportedly brought on behalf of a class of all persons who purchased or otherwise acquired Duke Energy securities between June 11, 2012 and July 9, 2012. On July 26, 2013, the Magistrate Judge recommended the District Court Judge deny the defendants' motion to dismiss. On October 2, 2013, the District Judge heard defendants' objections to this recommendation. A decision is pending on the motion to dismiss.

It is not possible to predict whether Duke Energy will incur any liability or to estimate the damages, if any, it might incur in connection with these lawsuits.

Alaskan Global Warming Lawsuit

On February 26, 2008, the governing bodies of an Inupiat village in Alaska, filed suit in the U.S. Federal Court for the Northern District of California against Peabody Coal and various oil and power company defendants, including Duke Energy and certain of its subsidiaries. Plaintiffs brought the action on their own behalf and on behalf of the village's 400 residents. The lawsuit alleges that defendants' emissions of CO2 contributed to global warming and constitute a private and public nuisance. Plaintiffs also allege that certain defendants, including Duke Energy, conspired to mislead the public with respect to global warming. The plaintiffs in the case requested damages in the range of $95 million to $400 million related to the cost of relocating the Village of Kivalina. On May 20, 2013, the plaintiffs' Petition for Certiorari to the Supreme Court was denied, ending the case.

Price Reporting Cases

A total of five lawsuits were filed against Duke Energy affiliates and other energy companies and remain pending in a consolidated, single federal court proceeding in Nevada.

Each of these cases contain similar claims, that defendants' allegedly manipulated natural gas markets by various means, including providing false information to natural gas trade publications and entering into unlawful arrangements and agreements in violation of the antitrust laws of the respective states. Plaintiffs seek damages in unspecified amounts.

On July 19, 2011, the judge granted a defendant's motion for summary judgment in two of the remaining five cases to which Duke Energy affiliates are a party. The Ninth Circuit Court of Appeals subsequently reversed the lower court's decision. On August 26, 2013, the defendants, including Duke Energy, filed a petition for certiorari to the U.S. Supreme Court.

It is not possible to predict whether Duke Energy will incur any liability or to estimate the damages, if any, it might incur in connection with the remaining matters. However, based on Duke Energy's past experiences with similar cases of this nature, it does not believe its exposure under these remaining matters is material.

Crescent Resources Litigation

On September 3, 2010, the Crescent Resources (Crescent) Litigation Trust sued Duke Energy along with various affiliates and several individuals, including current and former employees of Duke Energy, in the U.S. Bankruptcy Court for the Western District of Texas. The case was subsequently transferred to the United States District Court in Austin, Texas. The Crescent Resources Litigation Trust was established in May 2010 pursuant to the plan of reorganization approved in the Crescent bankruptcy proceedings. The complaint alleges in 2006 the defendants caused Crescent to borrow approximately $1.2 billion and immediately thereafter distribute most of the loan proceeds to Crescent's parent company without benefit to Crescent. The complaint further alleges that Crescent was rendered insolvent by the transactions, and that the loan proceeds of $1.2 billion as well as Crescent's interest of $252 million and fee payments to the creditor banks of $15 million are subject to recovery by the Crescent bankruptcy estate as an alleged fraudulent transfer. The plaintiff requests return of the loan proceeds, the payments to the creditor banks and accrued interest from the time of the transfers, as well as other statutory and equitable relief, punitive damages, and attorneys' fees. Duke Energy and its affiliated defendants believe that the referenced 2006 transactions were legitimate and did not violate any state or federal law. The defendants' motion for partial summary judgment to dismiss the plaintiff's claims for return of interest and fees paid by Crescent to the creditor banks was granted in part with respect to the interest payments and denied with respect to the fee payments.

Mediation held August 21-22, 2012 was unsuccessful. Duke Energy and its affiliated defendants tendered a partial settlement offer of $50 million in August 2013. This amount was recorded as Operation, maintenance and other in Duke Energy's Condensed Consolidated Statements of Operations during the second quarter of 2013. On October 4, 2013 the Court granted the defendants' motion for summary judgment on the fraudulent transfer claim. State law claims including breach of fiduciary duty against all of the defendants remain in the case. The parties have scheduled mediation for November 2013. Trial has been set to commence in January 2014.

It is not possible to estimate the maximum exposure to loss that may occur in connection with this lawsuit. The ultimate resolution of this matter could have a material effect on the results of operations, cash flows or financial position of Duke Energy.

Brazil Expansion Lawsuit

On August 9, 2011, the State of São Paulo sued Duke Energy International Geracao Paranapenema S.A. (DEIGP) in Brazilian state court. The lawsuit claims DEIGP is under a continuing obligation to expand installed generation capacity in the State of São Paulo by 15 percent pursuant to a stock purchase agreement under which DEIGP purchased generation assets from the state. On August 10, 2011, a judge granted an ex parte injunction ordering DEIGP to present a detailed expansion plan in satisfaction of the 15 percent obligation. DEIGP has previously taken a position that the 15 percent expansion obligation is no longer viable given changes that have occurred in the electric energy sector since privatization. DEIGP submitted its proposed expansion plan on November 11, 2011, but reserved objections regarding enforceability. No trial date has been set. It is not possible to predict whether Duke Energy will incur any liability or to estimate the damages, if any, it might incur in connection with this matter.

 

Duke Energy Carolinas

New Source Review (NSR)

In 1999-2000, the U.S. Department of Justice (DOJ) filed a number of complaints and notices of violation against multiple utilities across the country for alleged violations of the NSR provisions of the CAA. The DOJ filed these complaints on behalf of the EPA and joined by various citizen groups and states. Generally, the government alleges projects performed at various coal-fired units were major modifications, as defined in the CAA. By undertaking these projects, the utilities violated the CAA by not obtaining permits or installing the best available emission controls for SO2, NOx and particulate matter. The complaints seek the installation of pollution control technology on various generating units that allegedly violated the CAA, and unspecified civil penalties in amounts of up to $37,500 per day for each violation. A number of plants owned by Duke Energy Carolinas are subject to these allegations. Duke Energy Carolinas asserts there were no CAA violations because the applicable regulations do not require permitting in cases where the projects undertaken are “routine” or otherwise do not result in a net increase in emissions.

In 2000, the government sued Duke Energy Carolinas in the U.S. District Court in Greensboro, North Carolina. The EPA claims 29 projects performed at 25 of Duke Energy Carolinas' coal-fired units violate these NSR provisions. Three environmental groups intervened in the case. In August 2003, the trial court issued a summary judgment adopting Duke Energy Carolinas' positions on the standard to be used for measuring an increase in emissions, and granted judgment in favor of Duke Energy Carolinas. On April 2, 2007, the trial court's decision was reversed and remanded for trial by the Supreme Court. Duke Energy Carolinas continues to assert the projects were routine or not projected to increase emissions. The parties filed a stipulation in which the United States and the plaintiff-intervenors have dismissed with prejudice 16 claims. In exchange, Duke Energy Carolinas dismissed certain affirmative defenses. The parties filed motions for summary judgment on the remaining claims. On November 6, 2013, the court issued an order denying Duke Energy Carolinas' motion for summary judgment. Duke Energy Carolinas has requested leave to file another motion for summary judgment on alternative grounds. That motion for leave, as well as the Plaintiff's motion for summary judgment, remain pending.

It is not possible to predict whether Duke Energy Carolinas will incur any liability or to estimate the damages, if any, it might incur in connection with this matter. Ultimate resolution of these matters could have a material effect on the results of operations, cash flows or financial position of Duke Energy Carolinas. However, the appropriate regulatory treatment will be pursued for any costs incurred in connection with such resolution.

Asbestos-related Injuries and Damages Claims

Duke Energy Carolinas has experienced numerous claims for indemnification and medical cost reimbursement related to Asbestos exposure. These claims relate to damages for bodily injuries alleged to have arisen from exposure to or use of asbestos in connection with construction and maintenance activities conducted on its electric generation plants prior to 1985. As of September 30, 2013, there were 157 asserted claims for non-malignant cases with the cumulative relief sought of up to $30 million, and 35 asserted claims for malignant cases with the cumulative relief sought of up to $11 million. Based on Duke Energy Carolinas' experience, it is expected that the ultimate resolution of most of these claims likely will be less than the amount claimed.

Asbestos-related reserves totaled $633 million at September 30, 2013 and $751 million at December 31, 2012. These amounts are classified in Other within Deferred Credits and Other Liabilities and Other within Current Liabilities on Duke Energy Carolinas' Condensed Consolidated Balance Sheets. These reserves are based upon the minimum amount in Duke Energy Carolinas' best estimate of the range of loss for current and future asbestos claims through 2033. Duke Energy Carolinas believes that it is possible there will be additional claims filed after 2033. In light of uncertainties inherent in a longer-term forecast, Duke Energy Carolinas cannot reasonably estimate the indemnity and medical costs that might be incurred after 2033 related to such potential claims. Asbestos-related loss estimates incorporate anticipated inflation, if applicable, and are recorded on an undiscounted basis. These reserves are based upon current estimates and are subject to greater uncertainty as the projection period lengthens. A significant upward or downward trend in the number of claims filed, the nature of the alleged injury, and the average cost of resolving each such claim could change the estimated liability, as could any substantial or favorable verdict at trial. A federal legislative solution, further state tort reform or structured settlement transactions could also change the estimated liability. Given the uncertainties associated with projecting matters into the future and numerous other factors outside its control, it is possible Duke Energy Carolinas may incur asbestos liabilities in excess of the recorded reserves.

Duke Energy Carolinas has third-party insurance to cover certain losses related to asbestos-related injuries and damages above an aggregate self-insured retention of $476 million. Duke Energy Carolinas' cumulative payments began to exceed the self-insurance retention in 2008. Future payments up to the policy limit will be reimbursed by the third party insurance carrier. The insurance policy limit for potential future insurance recoveries indemnification and medical cost claim payments is $897 million in excess of the self-insured retention. Receivables for insurance recoveries were $649 million related to this policy at September 30, 2013 and $781 million at December 31, 2012. These amounts are classified in Other within Investments and Other Assets and Receivables on Duke Energy Carolinas' Condensed Consolidated Balance Sheets. Duke Energy Carolinas is not aware of any uncertainties regarding the legal sufficiency of insurance claims. Duke Energy Carolinas believes the insurance recovery asset is probable of recovery as the insurance carrier continues to have a strong financial strength rating.

Progress Energy

Synthetic Fuels Matters

Progress Energy and a number of its subsidiaries and affiliates are defendants in a lawsuit arising out of an Asset Purchase Agreement dated as of October 19, 1999, and amended as of August 23, 2000 (the Asset Purchase Agreement). Parties to the Asset Purchase Agreement include U.S. Global, LLC (Global); Earthco synthetic fuels facilities (Earthco); certain affiliates of Earthco; EFC Synfuel LLC (which was owned indirectly by Progress Energy) and certain of its affiliates (collectively, the Progress Affiliates). In a case filed in the Circuit Court for Broward County, Florida, in March 2003 (the Florida Global Case), Global requested an unspecified amount of compensatory damages, as well as declaratory relief. Global asserted (i) it was entitled to an interest in two synthetic fuels facilities previously owned by the Progress Affiliates and an option to purchase additional interests in the two synthetic fuels facilities and (ii) it was entitled to damages because the Progress Affiliates prohibited it from procuring purchasers for the synthetic fuels facilities. As a result of the 2007 expiration of the Internal Revenue Code Section 29 tax credit program, all of Progress Energy's synthetic fuels businesses were abandoned and the synthetic fuels businesses were reclassified as discontinued operations.

In November 2009, the court ruled in favor of Global. In December 2009, Progress Energy made a $154 million payment, which represented payment of the total judgment, including prejudgment interest, and a required premium equivalent to two years of interest, to the Broward County Clerk of Court bond account. Progress Energy continued to accrue interest related to this judgment.

On October 3, 2012, the Florida Fourth District Court of Appeals reversed the lower court ruling. The court held that Global was entitled to approximately $90 million of the amount paid into the registry of the court. Progress Energy was entitled to a refund of the remainder of the funds. Progress Energy received cash and recorded a $63 million pre-tax gain for the refund in December 2012. The gain was recorded in Income from Discontinued Operations, net of tax in the Consolidated Statements of Operations.

On May 9, 2013, Global filed a Seventh Amended Complaint asserting a single count for breach of the Asset Purchase Agreement and seeking specific performance. A trial is scheduled to commence in January 2014.

In a second suit filed in the Superior Court for Wake County, N.C., Progress Synfuel Holdings, Inc. et al. v. U.S. Global, LLC (the North Carolina Global Case), the Progress Affiliates seek declaratory relief consistent with their interpretation of the Asset Purchase Agreement. In August 2003, the Wake County Superior Court stayed the North Carolina Global Case, pending the outcome of the Florida Global Case. Based upon the verdict in the Florida Global Case, Progress Energy anticipates dismissal of the North Carolina Global Case.

Duke Energy Progress and Duke Energy Florida

Spent Nuclear Fuel Matters

The Nuclear Waste Policy Act of 1982 (as amended) (NWPA) provides the framework of interim storage and permanent disposal facilities for high-level radioactive waste materials for development by the federal government. The U.S. Department of Energy (DOE) is responsible for the selection and construction of a facility for the permanent disposal of spent nuclear fuel and high-level radioactive waste. Pursuant to the NWPA, Duke Energy Progress and Duke Energy Florida entered into contracts with the DOE for disposal of spent nuclear fuel by no later than January 31, 1998. All similarly situated utilities were required to sign the same Standard Contract for Disposal of Spent Nuclear Fuel. The DOE failed to begin taking spent nuclear fuel by January 31, 1998.

On December 12, 2011, Duke Energy Progress and Duke Energy Florida sued the United States in the U.S. Court of Federal Claims. The lawsuit claims the DOE breached the standard contract and asserts damages incurred from January 1, 2006 through December 31, 2010. Claims for all periods prior to 2006 have been resolved. Duke Energy Progress and Duke Energy Florida assert damages of $84 million and $21 million, respectively, for the period January 1, 2006 through December 31, 2010. The trial occurred September 23-25, 2013. A decision is expected in the fourth quarter 2014. Duke Energy Progress and Duke Energy Florida may file subsequent damage claims as they incur additional costs. Duke Energy Progress and Duke Energy Florida cannot predict the outcome of this matter.

 

Duke Energy Ohio

Antitrust Lawsuit

In January 2008, four plaintiffs, including individual, industrial and nonprofit customers, filed a lawsuit against Duke Energy Ohio in federal court in the Southern District of Ohio. Plaintiffs alleged Duke Energy Ohio conspired to provide inequitable and unfair price advantages for certain large business consumers. The lawsuit alleges this was done by entering into non-public option agreements with large business consumers in exchange for their withdrawal of challenges to Duke Energy Ohio's pending Rate Stabilization Plan (RSP). The RSP was implemented in early 2005. On March 31, 2009, the District Court granted Duke Energy Ohio's motion to dismiss. On June 4, 2012, the Sixth Circuit Court of Appeals reversed the district court's decision and remanded the matter on all claims for trial on the merits. Mediations held in December 2012 and March 2013 were unsuccessful. A ruling is pending on the plaintiffs' motion to certify this matter as a class action. It is not possible to predict whether Duke Energy Ohio will incur any liability or to estimate the damages, if any, which may be incurred in connection with this lawsuit.

Asbestos-related Injuries and Damages Claims

Duke Energy Ohio has been named as a defendant or co-defendant in lawsuits related to asbestos exposure at its electric generating stations. The impact on Duke Energy Ohio's results of operations, cash flows or financial position of these cases to date has not been material. Based on estimates under varying assumptions concerning uncertainties, such as, among others: (i) the number of contractors potentially exposed to asbestos during construction or maintenance of Duke Energy Ohio generating plants, (ii) the possible incidence of various illnesses among exposed workers, and (iii) the potential settlement costs without federal or other legislation that addresses asbestos tort actions, Duke Energy Ohio estimates that the range of reasonably possible exposure in existing and future suits over the foreseeable future is not material. This estimated range of exposure may change as additional settlements occur and claims are made and more case law is established.

Duke Energy Indiana

Edwardsport IGCC

On December 11, 2012, Duke Energy Indiana filed an arbitration action against General Electric Company and Bechtel Corporation in connection with their work at the Edwardsport IGCC facility. Duke Energy Indiana is seeking damages of not less than $560 million. An arbitration hearing is scheduled for October 2014. Duke Energy Indiana cannot predict the outcome of this matter.

Other Litigation and Legal Proceedings

The Duke Energy Registrants are involved in other legal, tax and regulatory proceedings arising in the ordinary course of business, some of which involve substantial amounts. The Duke Energy Registrants believe the final disposition of these proceedings will not have a material effect on their results of operations, cash flows or financial position.

The Duke Energy Registrants expense legal costs related to the defense of loss contingencies as incurred.

The Duke Energy Registrants have exposure to certain legal matters as described above. The Duke Energy Registrants have recorded reserves for these proceedings and exposures as presented in the table below. These reserves represent management's best estimate of probable loss as defined in the accounting guidance for contingencies. The amount for Duke Energy includes the reserve related to the Crescent Resources Litigation, which is discussed above. The estimated reasonably possible range of loss for all other non-asbestos related matters in excess of the recorded reserves is not material. Duke Energy Carolinas has insurance coverage for certain of these losses incurred as presented in the table below.

       
(in millions)September 30, 2013 December 31, 2012
Reserves for Legal and Other Matters(a)     
Duke Energy(b)$ 782 $ 846
Duke Energy Carolinas(b)  633   751
Progress Energy  74   79
Duke Energy Progress  10   12
Duke Energy Florida(c)  43   47
Duke Energy Indiana  8   8
Probable Insurance Recoveries(d)     
Duke Energy(e)$ 649 $ 781
Duke Energy Carolinas(e)  649   781
       
(a)Reserves are classified on the Condensed Consolidated Balance Sheets in Other within Deferred Credits and Other Liabilities and Other within Current Liabilities.
(b)Includes reserves for asbestos-related injuries and damages claims.
(c)Includes workers' compensation claims.
(d)Insurance recoveries are classified on the Condensed Consolidated Balance Sheets in Other within Investments and Other Assets and Receivables.
(e)Relates to recoveries associated with asbestos-related injuries and damages claims.
       

OTHER COMMITMENTS AND CONTINGENCIES

General

As part of their normal business, the Duke Energy Registrants are party to various financial guarantees, performance guarantees, and other contractual commitments to extend guarantees of credit and other assistance to various subsidiaries, investees, and other third parties. These guarantees involve elements of performance and credit risk, which are not included on their respective Condensed Consolidated Balance Sheets. The possibility of any of the Duke Energy Registrants having to honor their contingencies is largely dependent upon future operations of various subsidiaries, investees, and other third parties, or the occurrence of certain future events.

In addition, the Duke Energy Registrants enter into various fixed-price, non-cancelable commitments to purchase or sell power, take-or-pay arrangements, transportation, or throughput agreements and other contracts that may or may not be recognized on their respective Condensed Consolidated Balance Sheets. Some of these arrangements may be recognized at fair value on their respective Condensed Consolidated Balance Sheets if such contracts meet the definition of a derivative and the normal purchase/normal sale (NPNS) exception does not apply. In most cases, the Duke Energy Registrants' purchase obligation contracts contain provisions for price adjustments, minimum purchase levels, and other financial commitments.