XML 43 R15.htm IDEA: XBRL DOCUMENT v2.4.0.6
Commitments and Contingencies
6 Months Ended
Jun. 30, 2012
Commitments and Contingencies [Abstract]  
Commitments and Contingencies
6. 
Commitments and Contingencies
 
Except to the extent noted below and in Note 5 to the consolidated financial statements in this Quarterly Report on Form 10-Q the circumstances set forth in Notes 11 and 12 to the consolidated financial statements included in PSCo's Annual Report on Form 10-K for the year ended Dec. 31, 2011, appropriately represent, in all material respects, the current status of commitments and contingent liabilities, and are incorporated herein by reference.  The following include commitments, contingencies and unresolved contingencies that are material to PSCo's financial position.

Purchased Power Agreements

Under certain purchased power agreements, PSCo purchases power from independent power producing entities that own natural gas fueled power plants for which PSCo is required to reimburse natural gas fuel costs, or to participate in tolling arrangements under which PSCo procures the natural gas required to produce the energy that it purchases.  These specific purchased power agreements create a variable interest in the associated independent power producing entity.

PSCo had approximately 1,882 megawatts (MW) of capacity under long-term purchased power agreements as of June 30, 2012 and Dec. 31, 2011 with entities that have been determined to be variable interest entities.  PSCo has concluded that these entities are not required to be consolidated in its consolidated financial statements because it does not have the power to direct the activities that most significantly impact the entities' economic performance.  These agreements have expiration dates through the year 2028.
 
Guarantees and Indemnifications

In connection with the acquisition of 900 MW of natural gas-fired generation from subsidiaries of Calpine Development Holdings Inc. in 2010, PSCo agreed to indemnify the seller for losses arising out of a breach of certain representations and warranties.  The aggregate liability for PSCo pursuant to these indemnities is not subject to a capped dollar amount.  The indemnification obligation expires in December 2012.  PSCo has not recorded a liability related to this indemnity, and it had no assets held as collateral related to this agreement at June 30, 2012 or Dec. 31, 2011.

Environmental Contingencies

Environmental Requirements

Greenhouse Gas (GHG) New Source Performance Standard Proposal (NSPS) and Emission Guideline for Existing Sources - In April 2012, the U.S. Environmental Protection Agency (EPA) proposed a GHG NSPS for newly constructed power plants.  The proposal requires that carbon dioxide (CO2) emission rates be equal to those achieved by a natural gas combined-cycle plant, even if the plant is coal-fired.  The EPA also proposed that NSPS not apply to modified or reconstructed existing power plants and noted that, pursuant to its general NSPS regulations, installation of control equipment on existing plants would not constitute a "modification" to those plants under the NSPS program.  Xcel Energy submitted comments on the proposed GHG NSPS in June 2012.  It is not possible to evaluate the impact of this regulation until its final requirements are known.

The EPA also plans to propose GHG regulations applicable to emissions from existing power plants under the Clean Air Act (CAA).  It is not known when the EPA will propose new standards for existing sources.

Electric Generating Unit (EGU) Mercury and Air Toxics Standards (MATS) Rule - The final EGU MATS rule became effective April 2012.  The EGU MATS rule sets emission limits for acid gases, mercury and other hazardous air pollutants and requires coal-fired utility facilities greater than 25 MW to demonstrate compliance within three to four years of the effective date.  PSCo believes these costs will be recoverable through regulatory mechanisms and does not expect a material impact on results of operations, financial position or cash flows.

Regional Haze Rules - In 2005, the EPA finalized amendments to its regional haze rules regarding provisions that require the installation and operation of emission controls, known as best available retrofit technology (BART), for industrial facilities emitting air pollutants that reduce visibility in certain national parks and wilderness areas throughout the United States.  PSCo generating facilities are subject to BART requirements.  Individual states were required to identify the facilities located in their states that will have to reduce sulfur dioxide, nitrogen oxide and particulate matter (PM) emissions under BART and then set emissions limits for those facilities.

In 2006, the Colorado Air Quality Control Commission (CAQCC) promulgated BART regulations requiring certain major stationary sources to evaluate, install, operate and maintain BART to make reasonable progress toward meeting the national visibility goal.  In January 2011, the CAQCC approved a revised regional haze BART state implementation plan (SIP) incorporating the Colorado CACJA emission reduction plan, which will satisfy regional haze requirements.  In March 2012, the EPA proposed to approve the Colorado SIP, including the CACJA emission reduction plan for PSCo, as satisfying BART requirements.  The emission controls are expected to be installed between late 2012 and 2017.  PSCo expects the cost of any required capital investment will be recoverable from customers through the CACJA emission reduction plan recovery mechanisms or other regulatory mechanisms.

In March 2010, two environmental groups petitioned the U.S. Department of the Interior (DOI) to certify that 12 coal-fired boilers and one coal-fired cement kiln in Colorado are contributing to visibility problems in Rocky Mountain National Park.  The following PSCo plants are named in the petition:  Cherokee, Hayden, Pawnee and Valmont.  The groups allege that the Colorado BART rule is inadequate to satisfy the CAA mandate of ensuring reasonable further progress towards restoring natural visibility conditions in the park.  It is not known when the DOI will rule on the petition.

Revisions to National Ambient Air Quality Standards (NAAQS) for PM - In June 2012, the EPA proposed to lower the primary (health-based) NAAQS for annual average fine PM and to retain the current daily standard for fine PM.  In areas in which PSCo operates power plants, current monitored air concentrations are below the range of the proposed annual primary standard.  The EPA also proposed to add a secondary (welfare-based) NAAQS to improve visibility, primarily in urban areas.  PSCo expects the proposed visibility standard would likely be met where PSCo operates power plants based on currently available information.  A final rule is expected in December 2012 and the EPA is expected to designate non-compliant locations by December 2014.  If such areas are identified, states would then study the sources of the nonattainment and make emission reduction plans to attain the standards.  It is not possible to evaluate the impact of this regulation further until its final requirements are known.
 
Legal Contingencies

Lawsuits and claims arise in the normal course of business. Management, after consultation with legal counsel, has recorded an estimate of the probable cost of settlement or other disposition.  The ultimate outcome of these matters cannot presently be determined.  Accordingly, the ultimate resolution of these matters could have a material effect on PSCo's consolidated financial position, results of operations, and cash flows.

Environmental Litigation

Native Village of Kivalina vs. Xcel Energy Inc. et al. - In February 2008, the City and Native Village of Kivalina, Alaska, filed a lawsuit in U.S. District Court for the Northern District of California against Xcel Energy Inc., the parent company of PSCo, and 23 other utility, oil, gas and coal companies.  Plaintiffs claim that defendants' emission of CO2 and other GHGs contribute to global warming, which is harming their village.  Xcel Energy Inc. believes the claims asserted in this lawsuit are without merit and joined with other utility defendants in filing a motion to dismiss in June 2008.  In October 2009, the U.S. District Court dismissed the lawsuit on constitutional grounds.  In November 2009, plaintiffs filed a notice of appeal to the U.S. Court of Appeals for the Ninth Circuit (Ninth Circuit).  In November 2011, oral arguments were presented.  It is unknown when the Ninth Circuit will render a final opinion.  The amount of damages claimed by plaintiffs is unknown, but likely includes the cost of relocating the village of Kivalina.  Plaintiffs' alleged relocation is estimated to cost between $95 million to $400 million.  While Xcel Energy Inc. believes the likelihood of loss is remote, given the nature of this case and any surrounding uncertainty, it could potentially have a material impact on PSCo's consolidated results of operations, cash flows or financial position.  No accrual has been recorded for this matter.

Comer vs. Xcel Energy Inc. et al. - In May 2011, less than a year after their initial lawsuit was dismissed, plaintiffs in this purported class action lawsuit filed a second lawsuit against more than 85 utility, oil, chemical and coal companies in U.S. District Court in Mississippi.  The complaint alleges defendants' CO2 emissions intensified the strength of Hurricane Katrina and increased the damage plaintiffs purportedly sustained to their property.  Plaintiffs base their claims on public and private nuisance, trespass and negligence.  Among the defendants named in the complaint are Xcel Energy Inc. and PSCo.  The amount of damages claimed by plaintiffs is unknown.  The defendants, including Xcel Energy Inc., believe this lawsuit is without merit and filed a motion to dismiss the lawsuit.  In March 2012, the U.S. District Court granted this motion for dismissal.  In April 2012, plaintiffs appealed this decision to the U.S. Court of Appeals for the Fifth Circuit.  While Xcel Energy Inc. believes the likelihood of loss is remote, given the nature of this case and any surrounding uncertainty, it could potentially have a material impact on PSCo's consolidated results of operations, cash flows or financial position.  No accrual has been recorded for this matter.