XML 41 R36.htm IDEA: XBRL DOCUMENT v2.4.0.8
Commitments and Contingencies, Environmental Contingencies (Details) (USD $)
In Millions, unless otherwise specified
Jun. 30, 2014
Greenhouse Gas New Source Performance Standard for Modified and Reconstructed Power Plants
Dec. 31, 2010
Regional Haze Rules
Boiler
Kiln
Group
Jun. 30, 2014
Capital Commitments
Regional Haze Rules
Environmental Requirements [Abstract]      
Percentage of a comparable new plant's capital cost which would have to be exceeded to consider a project as a reconstruction under the proposed GHG NSPS for Modified and Reconstructed Power Plants (in hundredths) 50.00%    
Liability for estimated cost to comply with regulation     $ 359.7
Number of environmental groups who petitioned the U.S. Department of the Interior   2  
Number of coal-fired boilers in Colorado   12  
Number of coal-fired cement kilns in Colorado   1