XML 96 R34.htm IDEA: XBRL DOCUMENT v2.4.0.8
Joint Ownership of Generation, Transmission and Gas Facilities (Tables)
12 Months Ended
Dec. 31, 2013
Joint Ownership of Generation, Transmission and Gas Facilities [Abstract]  
Investments in Jointly Owned Generation, Transmission and Gas Facilities
Following are the investments by PSCo in jointly owned generation, transmission and gas facilities and the related ownership percentages as of Dec. 31, 2013:
(Thousands of Dollars)
 
Plant in
Service
 
Accumulated
Depreciation
 
CWIP
 
Ownership %
Electric Generation:
 
 
 
 
 
 
 
 
Hayden Unit 1
 
$
97,879

 
$
63,474

 
$
53

 
75.5
%
Hayden Unit 2
 
119,972

 
57,875

 
5,563

 
37.4

Hayden Common Facilities
 
36,916

 
16,055

 
2

 
53.1

Craig Units 1 and 2
 
60,089

 
34,754

 
537

 
9.7

Craig Common Facilities 1, 2 and 3
 
37,177

 
17,247

 

 
6.5

Comanche Unit 3
 
877,489

 
63,963

 
581

 
66.7

Comanche Common Facilities
 
19,812

 
711

 
2,255

 
82.0

Electric Transmission:
 
 
 
 
 
 
 
 
Transmission and other facilities, including substations
 
150,502

 
59,118

 
827

 
Various

Gas Transportation:
 
 
 
 
 
 
 
 
Rifle, Colo. to Avon, Colo.
 
16,278

 
6,044

 

 
60.0

Total
 
$
1,416,114

 
$
319,241

 
$
9,818