Following are the investments by PSCo in jointly owned generation, transmission and gas facilities and the related ownership percentages as of Dec. 31, 2013:
(Thousands of Dollars)
 
Plant in
Service
 
Accumulated
Depreciation
 
CWIP
 
Ownership %
Electric Generation:
 
 
 
 
 
 
 
 
Hayden Unit 1
 
$
97,879

 
$
63,474

 
$
53

 
75.5
%
Hayden Unit 2
 
119,972

 
57,875

 
5,563

 
37.4

Hayden Common Facilities
 
36,916

 
16,055

 
2

 
53.1

Craig Units 1 and 2
 
60,089

 
34,754

 
537

 
9.7

Craig Common Facilities 1, 2 and 3
 
37,177

 
17,247

 

 
6.5

Comanche Unit 3
 
877,489

 
63,963

 
581

 
66.7

Comanche Common Facilities
 
19,812

 
711

 
2,255

 
82.0

Electric Transmission:
 
 
 
 
 
 
 
 
Transmission and other facilities, including substations
 
150,502

 
59,118

 
827

 
Various

Gas Transportation:
 
 
 
 
 
 
 
 
Rifle, Colo. to Avon, Colo.
 
16,278

 
6,044

 

 
60.0

Total
 
$
1,416,114

 
$
319,241

 
$
9,818

 
 