Commitments and Contingencies Commitments and Contingencies
Leases
We lease certain facilities and equipment under non-cancelable operating leases. Operating lease amounts exclude property taxes, insurance, and maintenance expenses on leased properties. As of September 30, 2023, our operating leases had remaining lease terms of approximately 1 year to 12 years, some of which included options to extend 5 additional years. During the fiscal years ended September 30, 2023 and 2022, the Company recorded $3.7 million and $2.0 million of operating lease expense, respectively. The Company’s finance leases and short term leases are immaterial.

During the fiscal year ended September 30, 2023, there was a change in circumstances surrounding the use of our leased facilities and related right-of-use (ROU) assets due to the restructuring of our business and active pursuit of selling the discontinued operations and the indium phosphide wafer fabrication facility assets. Recoverability of the long-lived assets was measured by comparing the carrying amount of the asset groups to the future net undiscounted cash flows expected to be generated by the asset groups. The comparison indicated that certain of the asset groups was not recoverable, and an impairment of $1.4 million was recorded as this was the amount by which the carrying value of the asset group exceeded the related estimated fair value, which was based on discounted future operating cash flows.

Maturities of operating lease liabilities as of September 30, 2023 were as follows:
(in thousands)Amount
2024$4,614 
20254,137 
20263,072 
20272,757 
20282,830 
Thereafter22,179 
Total lease payments$39,589 
Less imputed interest(15,674)
Total operating lease liabilities$23,915 

Weighted-average remaining lease term and discount rate related to operating leases are as follows:
September 30,
20232022
Weighted average remaining lease term (years)10.09.8
Weighted average discount rate9.5 %5.4 %

Supplemental cash information and non-cash activities related to operating leases are as follows:
September 30,
(in thousands)
20232022
Operating cash outflows from operating leases$3,749 $2,011 
Right-of-use assets obtained in exchange for operating lease liabilities$2,577 $1,529 

Asset Retirement Obligations

ARO consists of legal requirements to decommission assets, restore the existing leased facilities to their original state, and perform certain environmental work due to the presence of a manufacturing fabrication operation. ARO includes assumptions related to renewal option periods for those facilities where we expect to extend lease terms. The Company recognizes its estimate of the fair value of its ARO in the period incurred in long-term liabilities and is also capitalized as property, plant and equipment. The fair value of ARO was estimated by discounting projected cash flows over the estimated life of the related assets using credit adjusted risk-free rates which ranged from 1.73% to 4.03%.

The following table summarizes ARO activity:
September 30,
(in thousands)20232022
Balance at beginning of period$4,664 $2,049 
Acquisition-related adjustment(604)2,500 
Accretion expense134 90 
Revision in estimated cash flows— 25 
Balance at end of period$4,194 $4,664 

Indemnifications

We have agreed to indemnify certain customers against claims of infringement of intellectual property rights of others in our sales contracts with these customers. Historically, we have not paid any claims under these customer indemnification obligations. We enter into indemnification agreements with each of our directors and executive officers pursuant to which we agree to indemnify them for certain potential expenses and liabilities arising from their status as a director or executive officer of the Company. We maintain director and officer insurance, which covers certain liabilities relating to our obligation to indemnify our directors and executive officers in certain circumstances. It is not possible to determine the aggregate maximum potential loss under these indemnification agreements due to the limited history of prior indemnification claims and the unique facts and circumstances involved in each particular claim.

Legal Proceedings

We are subject to various legal proceedings, claims, and litigation, either asserted or unasserted, that arise in the ordinary course of business. The outcome of these matters is currently not determinable and we are unable to estimate a range of loss, should a loss occur, from these proceedings. The ultimate outcome of legal proceedings involves judgments, estimates, and inherent uncertainties and the results of these matters cannot be predicted with certainty. Professional legal fees are expensed when incurred. We accrue for contingent losses when such losses are probable and reasonably estimable. In the event that estimates or assumptions prove to differ from actual results, adjustments are made in subsequent periods to reflect more current information. Should we fail to prevail in any legal matter, or should several legal matters be resolved against the Company in the same reporting period, then the financial results of that particular reporting period could be materially affected.

Intellectual Property Lawsuits

We protect our proprietary technology by applying for patents where appropriate and, in other cases, by preserving the technology, related know-how, and information as trade secrets. The success and competitive position of our product lines are impacted by the ability to obtain intellectual property protection for research and development efforts. We have, from time to time, exchanged correspondence with third parties regarding the assertion of patent or other intellectual property rights in connection with certain of our products and processes.

Resilience Litigation

In February 2021, Resilience Capital (“Resilience”) filed a complaint against us with the Delaware Chancery Court containing claims arising from the February 2020 sale of SDI’s real property (the “Concord Property Sale”) located in Concord, California (the “Concord Real Property”) to Eagle Rock Holdings, LP (“Buyer”) and that certain Single-Tenant Triple Net Lease, dated as of February 10, 2020, entered into by and between SDI and the Buyer, pursuant to which SDI leased from the Buyer the Concord Real Property for a 15 year term. The Resilience complaint seeks, among other items, (a) a declaration that the Concord Property Sale included a non-cash component, (b) a decree requiring us and Resilience to follow the appraisal requirements set forth in that certain Purchase and Sale Agreement (the “SDI Purchase Agreement”), dated as of June 7, 2019, by and among the Company, The Resilience Fund IV, L.P., The Resilience Fund IV-A, L.P., Aerospace Newco Holdings, Inc. and Ember Acquisition Sub, Inc., (c) recovery of Resilience’s costs and expenses, and (d) pre- and post-judgment interest.

In April 2021, we filed with the Delaware Chancery Court our answer to the Resilience complaint and counterclaims against Resilience, in which we are seeking, among other items, (a) dismissal of the Resilience complaint and/or granting of judgment in favor of EMCORE with respect to the Resilience complaint, (b) entering final judgment against Resilience awarding damages to us for Resilience’s fraud and breaches of the SDI Purchase Agreement in an amount to be proven at trial and not less than $1,565,000, (c) a judicial determination of the respective rights and duties of us and Resilience under the SDI Purchase Agreement, (d) an award to us of costs and expenses, and (e) pre- and post-judgment interest.
In April 2023, we and Resilience entered into a Settlement and Release Agreement (the “Resilience Settlement Agreement”). The material financial terms of the Resilience Settlement Agreement required (i) a payment of $0.5 million by us to Resilience, which payment was made by us during the three months ended June 30, 2023, (ii) appraisals of the Concord Real Property, conducted in 2023 with a date of value as of January 2, 2020, which resulted in a further payment obligation by us in an amount equal to approximately $1.3 million, which payment was made by us in October 2023, and (iii) a mutual release of all claims, including claims arising under the SDI Purchase Agreement, and a dismissal of the litigation by all parties. On October 10, 2023, the Delaware Chancery Court granted the parties' stipulation of dismissal with prejudice to the Delaware Chancery Court of all claims made by each party.

In April 2023, the underwriters of the representation and warranty insurance policies the Company acquired in connection with the SDI Purchase Agreement agreed to pay the Company $1.15 million within 15 business days in exchange for a release of any and all claims under the policies. We received payment during the three months ended June 30, 2023.