XML 147 R16.htm IDEA: XBRL DOCUMENT v2.4.0.8
Regulatory Matters
12 Months Ended
Dec. 31, 2013
Regulatory Matters

(7) REGULATORY MATTERS

Regulatory Assets and Regulatory Liabilities

The components of Pepco Holdings’ regulatory asset and liability balances at December 31, 2013 and 2012 are as follows:

 

     2013      2012  
     (millions of dollars)  

Regulatory Assets

     

Pension and OPEB costs

   $ 667       $ 1,171   

Securitized stranded costs (a)

     350         416   

Smart Grid costs (a)

     251         230   

Recoverable income taxes

     225         177   

Deferred energy supply costs (a)

     136         183   

Demand-side management costs (a)

     125         57   

Incremental storm restoration costs (a)

     72         89   

MAPP abandonment costs (a)

     68         88   

Deferred debt extinguishment costs (a)

     47         53   

Recoverable workers’ compensation and long-term disability costs

     26         31   

Deferred losses on gas derivatives

     —           4   

Other

     120         115   
  

 

 

    

 

 

 

Total Regulatory Assets

   $ 2,087       $ 2,614   
  

 

 

    

 

 

 

Regulatory Liabilities

  

Asset removal costs

   $ 275       $ 324   

Deferred energy supply costs

     46         78   

Deferred income taxes due to customers

     45         45   

Deferred gains on gas derivatives

     1         —     

Excess depreciation reserve

     —           11   

Other

     32         43   
  

 

 

    

 

 

 

Total Regulatory Liabilities

   $ 399       $ 501   
  

 

 

    

 

 

 

 

(a) A return is generally earned on these deferrals.

A description for each category of regulatory assets and regulatory liabilities follows:

Pension and OPEB Costs: Represents unrecognized net actuarial losses and prior service cost (credit) for Pepco Holdings’ defined benefit pension and other postretirement benefit (OPEB) plans that are expected to be recovered by Pepco, DPL and ACE in rates. The utilities have historically included these items as a part of its cost of service in its customer rates. This regulatory asset is adjusted at least annually when the funded status of Pepco Holdings’ defined benefit pension and OPEB plans are re-measured. See Note (9), “Pension and Other Postretirement Benefits,” for more information about the components of the unrecognized pension and OPEB costs.

Securitized Stranded Costs: Certain contract termination payments under a contract between ACE and an unaffiliated non-utility generator (NUG) and costs associated with the regulated operations of ACE’s electricity generation business are no longer recoverable through customer rates (collectively referred to as “stranded costs”). The stranded costs are amortized over the life of Transition Bonds issued by Atlantic City Electric Transition Funding LLC (ACE Funding) (Transition Bonds) to securitize the recoverability of these stranded costs. These bonds mature between 2014 and 2023. A customer surcharge is collected by ACE to fund principal and interest payments on the Transition Bonds.

 

Smart Grid Costs: Represents AMI costs associated with the installation of smart meters and the early retirement of existing meters throughout Pepco’s and DPL’s service territories that are recoverable from customers. AMI has not been approved by the NJBPU for ACE in New Jersey.

Recoverable Income Taxes: Represents amounts recoverable from Power Delivery’s customers for tax benefits applicable to utility operations of Pepco, DPL and ACE previously recognized in income tax expense before the companies were ordered to account for the tax benefits as deferred income taxes. As the temporary differences between the financial statement basis and tax basis of assets reverse, the deferred recoverable balances are reversed.

Deferred Energy Supply Costs: The regulatory asset represents primarily deferred costs associated with a net under-recovery of Default Electricity Supply costs incurred by Pepco, DPL and ACE that are probable of recovery in rates. The regulatory liability represents primarily deferred costs associated with a net over-recovery of Default Electricity Supply costs incurred that will be refunded by Pepco, DPL and ACE to customers.

Demand-Side Management Costs: Represents recoverable costs associated with customer energy efficiency and conservation programs in Pepco’s and DPL’s Maryland jurisdictions.

Incremental Storm Restoration Costs: Represents total incremental storm restoration costs incurred for repair work due to major storm events in 2012 and 2011, including Hurricane Sandy, the June 2012 derecho, Hurricane Irene and the 2011 severe winter storm (for Pepco), that are recoverable from customers in the Maryland and New Jersey jurisdictions. Pepco’s and DPL’s costs related to Hurricane Sandy, the June 2012 derecho, Hurricane Irene and Pepco’s costs related to the 2011 severe winter storm are being amortized and recovered in rates, each over a five-year period. ACE’s costs related to Hurricane Sandy, the June 2012 derecho and Hurricane Irene are being amortized and recovered in rates, each over a three-year period.

MAPP Abandonment Costs: Represents the probable recovery of abandoned costs prudently incurred in connection with the Mid-Atlantic Power Pathway (MAPP) project which was terminated by PJM Interconnection, LLC (PJM) on August 24, 2012. The regulatory asset includes the costs of land, land rights, supplies and materials, engineering and design, environmental services, and project management and administration. The regulatory asset will be reduced as the result of sale or alternative use of these assets. As of December 31, 2013, these assets were earning a return of 12.8%. For additional information, see “MAPP Project” discussion below.

Deferred Debt Extinguishment Costs: Represents the costs of debt extinguishment of Pepco, DPL and ACE associated with issuances of debt for which recovery through regulated utility rates is considered probable, and if approved, will be amortized to interest expense during the authorized rate recovery period.

Recoverable Workers’ Compensation and Long-Term Disability Costs: Represents accrued workers’ compensation and long-term disability costs for Pepco, which are recoverable from customers when actual claims are paid to employees.

Deferred Losses on Gas Derivatives: Represents losses associated with hedges of natural gas purchases that are recoverable through the Gas Cost Rate approved by the DPSC.

Other: Represents miscellaneous regulatory assets that generally are being amortized over 1 to 20 years.

Asset Removal Costs: The depreciation rates for Pepco and DPL include a component for removal costs, as approved by the relevant federal and state regulatory commissions. Accordingly, Pepco and DPL have recorded regulatory liabilities for their estimate of the difference between incurred removal costs and the amount of removal costs recovered through depreciation rates.

 

Deferred Income Taxes Due to Customers: Represents the portions of deferred income tax assets applicable to utility operations of Pepco and DPL that have not been reflected in current customer rates for which future payment to customers is probable. As the temporary differences between the financial statement basis and tax basis of assets reverse, deferred recoverable income taxes are amortized.

Deferred Gains on Gas Derivatives: Represents gains associated with hedges of natural gas purchases that will be refunded to customers through the Gas Cost Rate approved by the DPSC.

Excess Depreciation Reserve: The excess depreciation reserve was recorded as part of an ACE New Jersey rate case settlement. This excess reserve is the result of a change in estimated depreciable lives and a change in depreciation technique from remaining life to whole life that caused an over-recovery for depreciation expense from customers when the remaining life method had been used. The excess was amortized as a reduction in Depreciation and amortization expense over an 8.25 year period, and expired in 2013.

Other: Includes miscellaneous regulatory liabilities.

Rate Proceedings

The following table shows, for each of PHI’s utility subsidiaries, the electric distribution base rate cases currently pending. Additional information concerning each of these filings is provided in the discussion below.

 

Jurisdiction/Company

   Requested Revenue
Requirement Increase
    Requested Return
on Equity
    Filing
Date
   Expected Timing
of Decision
     (millions of dollars)                 

DC – Pepco

   $  44.8 (a)     10.25   March 8, 2013    Q1, 2014

DE – DPL (Electric)

   $  39.0 (b)     10.25   March 22, 2013    Q2, 2014

MD – Pepco

   $  43.3        10.25   December 4, 2013    Q3, 2014

 

(a) Reflects Pepco’s updated revenue requirement as filed on December 3, 2013.
(b) Reflects DPL’s updated revenue requirement as filed on September 20, 2013.

The following table shows, for each of PHI’s utility subsidiaries, the distribution base rate cases completed in 2013. Additional information concerning each of these cases is provided in the discussion below.

 

Jurisdiction/Company

   Approved Revenue
Requirement Increase
     Approved Return
on Equity
    Completion
Date
   Rate Effective
Date
     (millions of dollars)                  

NJ – ACE

   $ 25.5         9.75   June 21, 2013    July 1, 2013

MD – Pepco

   $ 27.9        9.36   July 12, 2013    July 12, 2013

MD – DPL

   $ 15.0        9.81 % (a)    August 30, 2013    September 15, 2013

DE – DPL (Gas)

   $ 6.8         9.75 % (b)    October 22, 2013    November 1, 2013

 

(a) Return on equity (ROE) has not been determined by any proceeding and is specified only for the purposes of calculating the AFUDC and regulatory asset carrying costs.
(b) ROE has not been determined by any proceeding and is specified only for reporting purposes and for calculating the AFUDC, construction work in process (CWIP), regulatory asset carrying costs and other accounting metrics.

 

Bill Stabilization Adjustment

PHI’s utility subsidiaries have proposed in each of their respective jurisdictions the adoption of a mechanism to decouple retail distribution revenue from the amount of power delivered to retail customers. To date:

 

    A BSA has been approved and implemented for Pepco and DPL electric service in Maryland and for Pepco electric service in the District of Columbia.

 

    A proposed modified fixed variable rate design (MFVRD) for DPL electric and natural gas service in Delaware was filed in 2009 for consideration by the DPSC and while there was little activity associated with this filing in 2013, the proceeding remains open.

 

    In New Jersey, a BSA proposed by ACE in 2009 was not approved and there is no BSA proposal currently pending.

Under the BSA, customer distribution rates are subject to adjustment (through a credit or surcharge mechanism), depending on whether actual distribution revenue per customer exceeds or falls short of the revenue-per-customer amount approved by the applicable public service commission. The MFVRD proposed in Delaware contemplates a fixed customer charge (i.e., not tied to the customer’s volumetric consumption of electricity or natural gas) to recover the utility’s fixed costs, plus a reasonable rate of return.

Delaware

Electric Distribution Base Rates

On March 22, 2013, DPL submitted an application with the DPSC to increase its electric distribution base rates. The filing seeks approval of an annual rate increase of approximately $39 million (as adjusted by DPL on September 20, 2013), based on a requested ROE of 10.25%. The requested rate increase seeks to recover expenses associated with DPL’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. The DPSC suspended the full proposed increase and, as permitted by state law, DPL implemented an interim increase of $2.5 million on June 1, 2013, subject to refund and pending final DPSC approval. On October 8, 2013, the DPSC approved DPL’s request to implement an additional interim increase of $25.1 million, effective on October 22, 2013, bringing the total interim rates in effect subject to refund to $27.6 million. A final DPSC decision is expected by the second quarter of 2014.

Forward Looking Rate Plan

On October 2, 2013, DPL filed a multi-year rate plan, referred to as the Forward Looking Rate Plan (FLRP). As proposed, the FLRP would provide for annual electric distribution base rate increases over a four-year period in the aggregate amount of approximately $56 million. The FLRP as proposed provides the opportunity to achieve estimated earned ROEs of 7.41% and 8.80% in years one and two, respectively, and 9.75% in both years three and four of the plan.

In addition, DPL proposed that as part of the FLRP, in order to provide a higher minimum required standard of reliability for DPL’s customers than that to which DPL is currently subject, the standards by which DPL’s reliability is measured would be made more stringent in each year of the FLRP. In addition, DPL has offered to refund an aggregate of $500,000 to customers in each year of the FLRP that it fails to meet the proposed stricter minimum reliability standards.

On October 22, 2013, the DPSC opened a docket for the purpose of reviewing the details of the FLRP, but stated that it would not address the FLRP until the pending electric distribution base rate case discussed above was concluded. DPL expects that the FLRP will be updated and re-filed at the conclusion of the electric distribution base rate case. A schedule for the FLRP docket has not yet been established.

 

Gas Distribution Base Rates

On December 7, 2012, DPL submitted an application with the DPSC to increase its natural gas distribution base rates. The filing sought approval of an annual rate increase of approximately $12.0 million (as adjusted by DPL on July 15, 2013), based on a requested ROE of 10.25%. The requested rate increase sought to recover expenses associated with DPL’s ongoing efforts to maintain safe and reliable gas service. On October 22, 2013, the DPSC approved a settlement entered into on August 27, 2013 by the DPSC Staff, the Delaware Division of the Public Advocate and DPL, which provides for an annual rate increase of $6.8 million. While the approved settlement provided that no understanding was reached concerning the appropriate ROE, it specified that for reporting purposes and for calculating the AFUDC, CWIP, regulatory asset carrying costs and other accounting metrics, the rate of 9.75% should be used. The new rates became effective on November 1, 2013.

The approved settlement also provides for a phase-in of the recovery of the deferred costs associated with DPL’s deployment of the interface management unit (IMU). The IMU is part of its AMI and allows for the remote reading of gas meters. Recovery of such costs will occur through base rates over a two-year period, assuming specific milestones are met and pursuant to the following schedule: 50% of the IMU portion of DPL’s AMI will be put into rates on May 1, 2014, and the remainder will be put into rates on March 1, 2015. DPL also agreed in the settlement that its next natural gas distribution base rate application may be filed with the DPSC no earlier than January 1, 2015.

Gas Cost Rates

DPL makes an annual Gas Cost Rate (GCR) filing with the DPSC for the purpose of allowing DPL to recover natural gas procurement costs through customer rates. On August 28, 2013, DPL made its 2013 GCR filing. The rates proposed in the 2013 GCR filing would result in a GCR decrease of approximately 5.5%. On September 26, 2013, the DPSC issued an order authorizing DPL to place the new rates into effect on November 1, 2013, subject to refund and pending final DPSC approval.

District of Columbia

On March 8, 2013, Pepco filed an application with the DCPSC to increase its annual electric distribution base rates by approximately $44.8 million (as adjusted by Pepco on December 3, 2013), based on a requested ROE of 10.25%. The requested rate increase seeks to recover expenses associated with Pepco’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. Evidentiary hearings were held in November 2013 and a final DCPSC decision is expected in the first quarter of 2014.

Maryland

DPL Electric Distribution Base Rates

On March 29, 2013, DPL submitted an application with the MPSC to increase its electric distribution base rates by approximately $22.8 million, based on a requested ROE of 10.25%. The requested rate increase sought to recover expenses associated with DPL’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. DPL also proposed a three-year Grid Resiliency Charge rider for recovery of costs totaling approximately $10.2 million associated with its plan to accelerate investments in electric distribution infrastructure in a condensed timeframe. Acceleration of resiliency improvements was one of several recommendations included in a September 2012 report from Maryland’s Grid Resiliency Task Force (as discussed below under “Resiliency Task Forces”). Specific projects under DPL’s Grid Resiliency Charge plan included accelerating its tree-trimming cycle and upgrading five additional feeders per year for two years. In addition, DPL proposed a reliability performance-based mechanism that would allow DPL to earn up to $500,000 as an incentive for meeting enhanced reliability goals in 2015, but provided for a credit to customers of up to $500,000 in total if DPL did not meet at least the minimum reliability performance targets. DPL requested that any credits or charges would flow through the proposed Grid Resiliency Charge rider.

 

On August 30, 2013, the MPSC issued a final order approving a settlement among DPL, the MPSC staff and the Maryland Office of People’s Counsel (OPC). The approved settlement provides for an annual rate increase of approximately $15 million. While the settlement does not specify an overall ROE, the parties did agree that the ROE for purposes of calculating the AFUDC and regulatory asset carrying costs would be 9.81%. The approved settlement also provides for (i) recovery of storm restoration costs incurred as a result of recent major storm events, including the derecho storm in June 2012 and Hurricane Sandy in October 2012, by amortizing the related deferred operation and maintenance expenses of approximately $6 million over a five-year period with the unamortized balance included in rate base, and (ii) a Grid Resiliency Charge for recovery of costs totaling approximately $4.2 million associated with DPL’s proposed plan to accelerate investments related to certain priority feeders, provided that before implementing the surcharge, DPL provides additional information to the MPSC related to performance objectives, milestones and costs, and makes annual filings with the MPSC thereafter concerning this project, which will permit the MPSC to establish the applicable Grid Resiliency Charge rider for the following year. The approved settlement does not provide for approval of a portion of the Grid Resiliency Charge related to the proposed acceleration of the tree-trimming cycle, or DPL’s proposed reliability performance-based mechanism. The new rates became effective on September 15, 2013.

Pepco Electric Distribution Base Rates

In December 2011, Pepco submitted an application with the MPSC to increase its electric distribution base rates. The filing sought approval of an annual rate increase of approximately $68.4 million (subsequently reduced by Pepco to $66.2 million), based on a requested ROE of 10.75%. In July 2012, the MPSC issued an order approving an annual rate increase of approximately $18.1 million, based on an ROE of 9.31%. The order also reduced Pepco’s depreciation rates, which lowered annual depreciation and amortization expenses by an estimated $27.3 million. The lower depreciation rates resulted from, among other things, the rebalancing of excess reserves for estimated future removal costs identified in a depreciation study conducted as part of the rate case filing. The identified excess reserves for estimated future removal costs, reported as Regulatory liabilities, were reclassified to Accumulated depreciation among various plant accounts. Among other things, the order additionally authorized Pepco to recover the actual cost of AMI meters installed during the 2011 test year and states that cost recovery for AMI deployment will be allowed in future rate cases in which Pepco demonstrates that the system is cost effective. The new revenue rates and lower depreciation rates were effective on July 20, 2012. The Maryland OPC has sought rehearing on the portion of the order allowing Pepco to recover the costs of AMI meters installed during the test year; that motion remains pending.

On November 30, 2012, Pepco submitted an application with the MPSC to increase its electric distribution base rates. The filing sought approval of an annual rate increase of approximately $60.8 million, based on a requested ROE of 10.25%. The requested rate increase sought to recover expenses associated with Pepco’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. Pepco also proposed a three-year Grid Resiliency Charge rider for recovery of costs totaling approximately $192 million associated with its plan to accelerate investments in infrastructure in a condensed timeframe. Acceleration of resiliency improvements was one of several recommendations included in a September 2012 report from Maryland’s Grid Resiliency Task Force (as discussed below under “Resiliency Task Forces”). Specific projects under Pepco’s Grid Resiliency Charge plan included acceleration of its tree-trimming cycle, upgrade of 12 additional feeders per year for two years and undergrounding of six distribution feeders. In addition, Pepco proposed a reliability performance-based mechanism that would allow Pepco to earn up to $1 million as an incentive for meeting enhanced reliability goals in 2015, but provided for a credit to customers of up to $1 million in total if Pepco does not meet at least the minimum reliability performance targets. Pepco requested that any credits/charges would flow through the proposed Grid Resiliency Charge rider.

 

On July 12, 2013, the MPSC issued an order related to Pepco’s November 30, 2012 application approving an annual rate increase of approximately $27.9 million, based on an ROE of 9.36%. The order provides for the full recovery of storm restoration costs incurred as a result of recent major storm events, including the derecho storm in June 2012 and Hurricane Sandy in October 2012, by including the related capital costs in the rate base and amortizing the related deferred operation and maintenance expenses of $23.6 million over a five-year period. The order excludes the cost of AMI meters from Pepco’s rate base until such time as Pepco demonstrates the cost effectiveness of the AMI system; as a result, costs for AMI meters incurred with respect to the 2012 test year and beyond will be treated as other incremental AMI costs incurred in conjunction with the deployment of the AMI system that are deferred and on which a return is earned, but only until such cost effectiveness has been demonstrated and such costs are included in rates. However, the MPSC’s July 2012 order in Pepco’s previous electric distribution base rate case, which allowed Pepco to recover the costs of meters installed during the 2011 test year for that case, remains in effect, and the Maryland OPC’s motion for rehearing in that case remains pending.

The order also approved a Grid Resiliency Charge for recovery of costs totaling approximately $24.0 million associated with Pepco’s proposed plan to accelerate investments related to certain priority feeders, provided that, before implementing the surcharge, Pepco provides additional information to the MPSC related to performance objectives, milestones and costs, and makes annual filings with the MPSC thereafter concerning this project, which will permit the MPSC to establish the applicable Grid Resiliency Charge rider for each following year. The MPSC did not approve the proposed acceleration of the tree-trimming cycle or the undergrounding of six distribution feeders. The MPSC also rejected Pepco’s proposed reliability performance-based mechanism. The new rates were effective on July 12, 2013.

On July 26, 2013, Pepco filed a notice of appeal of the July 12, 2013 order in the Circuit Court for the City of Baltimore. Other parties also have filed notices of appeal, which have been consolidated with Pepco’s appeal. In its memorandum filed with the appeals court, Pepco asserts that the MPSC erred in failing to grant Pepco an adequate ROE, denying a number of other cost recovery mechanisms and limiting Pepco’s test year data to no more than four months of forecasted data in future rate cases. The memoranda filed with the appeals court by the other parties primarily assert that the MPSC erred or acted arbitrarily and capriciously in allowing the recovery of certain costs by Pepco and refusing to reduce Pepco’s rate base by known and measurable accumulated depreciation.

On December 4, 2013, Pepco submitted an application with the MPSC to increase its electric distribution base rates. The filing seeks approval of an annual rate increase of approximately $43.3 million, based on a requested ROE of 10.25%. The requested rate increase seeks to recover expenses associated with Pepco’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. A decision is expected in the third quarter of 2014.

New Jersey

Electric Distribution Base Rates

On December 11, 2012, ACE submitted an application with the NJBPU, updated on January 4, 2013, to increase its electric distribution base rates by approximately $70.4 million (excluding sales-and-use taxes), based on a requested ROE of 10.25%. This proposed net increase was comprised of (i) a proposed increase to ACE’s distribution rates of approximately $72.1 million and (ii) a net decrease to ACE’s Regulatory Asset Recovery Charge (a customer charge to recover deferred, NJBPU-approved expenses incurred as part of ACE’s public service obligation) in the amount of approximately $1.7 million. The requested rate increase seeks to recover expenses associated with ACE’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service and to recover system restoration costs associated with the derecho storm in June 2012 and Hurricane Sandy in October 2012. On June 21, 2013, the NJBPU approved a settlement of the parties providing for an increase in ACE’s electric distribution base rates in the amount of $25.5 million, based on an ROE of 9.75%. The base distribution revenue increase includes full recovery of the approximately $70.0 million in incremental storm restoration costs incurred as a result of recent major storm events, including the derecho storm and Hurricane Sandy, by including the related capital costs of approximately $44.2 million in rate base and amortizing the related deferred operation and maintenance expenses of approximately $25.8 million over a three-year period. Rates were effective on July 1, 2013.

Update and Reconciliation of Certain Under-Recovered Balances

In February 2012 and March 2013, ACE submitted petitions with the NJBPU seeking to reconcile and update (i) charges related to the recovery of above-market costs associated with ACE’s long-term power purchase contracts with the NUGs, (ii) costs related to surcharges for the New Jersey Societal Benefit Program (a statewide public interest program for low income customers) and ACE’s uncollected accounts and (iii) operating costs associated with ACE’s residential appliance cycling program. In June 2012, the NJBPU approved a stipulation of settlement related to ACE’s February 2012 filing, which provided for an overall annual rate increase of $55.3 million that went into effect on July 1, 2012. In May 2013, the NJBPU approved a stipulation of settlement related to ACE’s March 2013 filing, which provided for an overall annual rate increase of $52.2 million (in addition to the $55.3 million approved by the NJBPU in June 2012) that went into effect on June 1, 2013. These rate increases, which primarily provide for the recovery of above-market costs associated with the NUG contracts and will have no effect on ACE’s operating income, were placed into effect provisionally and were subject to a review by the NJBPU of the final underlying costs for reasonableness and prudence. On February 19, 2014, the NJBPU approved a stipulation of settlement for both proceedings, which made final the provisional rates that went into effect on July 1, 2012 and June 1, 2013, respectively.

Service Extension Contributions Refund Order

On July 19, 2013, in compliance with a 2012 Superior Court of New Jersey Appellate Division (Appellate Division) court decision, the NJBPU released an order requiring utilities to issue refunds to persons or entities that paid non-refundable contributions for utility service extensions to certain areas described as “Areas Not Designated for Growth.” The order is limited to eligible contributions paid between March 20, 2005 and December 20, 2009. ACE is processing the refund requests that meet the eligibility criteria established in the order as they are received. Although ACE believes it received approximately $11 million of contributions between March 20, 2005 and December 20, 2009, it is currently unable to reasonably estimate the amount that it may be required to refund using the eligibility criteria established by the order. At this time, ACE does not expect that any such amount refunded will have a material effect on its consolidated financial condition, results of operations or cash flows, as any amounts that may be refunded will generally increase the value of ACE’s property, plant and equipment and may ultimately be recovered through depreciation and cost of service. It is anticipated that the NJBPU will commence a rulemaking proceeding to further implement the directives of the Appellate Division decision.

Generic Consolidated Tax Adjustment Proceeding

In January 2013, the NJBPU initiated a generic proceeding to examine whether a consolidated tax adjustment (CTA) should continue to be used, and if so, how it should be calculated in determining a utility’s cost of service. Under the NJBPU’s current policy, when a New Jersey utility is included in a consolidated group income tax return, an allocated amount of any reduction in the consolidated group’s taxes as a result of losses by affiliates is used to reduce the utility’s rate base, upon which the utility earns a return. Consequently, this policy has substantially reduced ACE’s rate base and ACE’s position is that the CTA should be eliminated. A stakeholder process has been initiated by the NJBPU to aid in this examination. No formal schedule has been set for the remainder of the proceeding or for the issuance of a decision.

 

Federal Energy Regulatory Commission

On October 17, 2013, the FERC issued a ruling on challenges filed by the Delaware Municipal Electric Corporation, Inc. (DEMEC) to DPL’s 2011 and 2012 annual formula rate updates. In 2006, FERC approved a formula rate for DPL that is incorporated into the PJM tariff. The formula rate establishes the treatment of costs and revenues and the resulting rates for DPL. Pursuant to the protocols approved by FERC and after a period of discovery, interested parties have an opportunity to file challenges regarding the application of the formula rate. The FERC order sets various issues in this proceeding for hearing, including challenges regarding formula rate inputs, deferred income items, prepayments of estimated income taxes, rate base reductions, various administrative and general expenses and the inclusion in rate base of CWIP related to the MAPP project (which has been abandoned). Settlement discussions began in this matter on November 5, 2013 before an administrative law judge at FERC.

On December 12, 2013, DEMEC filed a formal challenge to the DPL 2013 annual formula rate update, including a request to consolidate the 2013 challenge with the two prior challenges. This challenge is pending at FERC. PHI cannot predict when a final FERC decision in this proceeding will be issued.

On February 27, 2013, the public service commissions and public advocates of the District of Columbia, Maryland, Delaware and New Jersey, as well as DEMEC, filed a joint complaint with FERC against Pepco, DPL and ACE, as well as Baltimore Gas and Electric Company (BGE). The complainants challenged the base ROE and the application of the formula rate process, each associated with the transmission service that PHI’s utilities provide. The complainants support an ROE within a zone of reasonableness of 6.78% and 10.33%, and have argued for a base ROE of 8.7%. The base ROE currently authorized by FERC for PHI’s utilities is (i) 11.3% for facilities placed into service after January 1, 2006, and (ii) 10.8% for facilities placed into service prior to 2006. As currently authorized, the 10.8% base ROE for facilities placed into service prior to 2006 is eligible for a 50-basis-point incentive adder for being a member of a regional transmission organization. PHI, Pepco, DPL and ACE believe the allegations in this complaint are without merit and are vigorously contesting it. On April 3, 2013, Pepco, DPL and ACE filed their answer to this complaint, requesting that FERC dismiss the complaint against them on the grounds that it failed to meet the required burden to demonstrate that the existing rates and protocols are unjust and unreasonable. PHI cannot predict when a final FERC decision in this proceeding will be issued.

MPSC New Generation Contract Requirement

In September 2009, the MPSC initiated an investigation into whether Maryland electric distribution companies (EDCs) should be required to enter into long-term contracts with entities that construct, acquire or lease, and operate, new electric generation facilities in Maryland. In April 2012, the MPSC issued an order determining that there is a need for one new power plant in the range of 650 to 700 megawatts (MWs) beginning in 2015. The order requires Pepco, DPL and BGE (collectively, the Contract EDCs) to negotiate and enter into a contract with the winning bidder of a competitive bidding process in amounts proportional to their relative SOS loads. Under the contract, the winning bidder will construct a 661 MW natural gas-fired combined cycle generation plant in Waldorf, Maryland, with an expected commercial operation date of June 1, 2015. The order acknowledged the Contract EDCs’ concerns about the requirements of the contract and directed them to negotiate with the winning bidder and submit any proposed changes in the contract to the MPSC for approval. The order further specified that each of the Contract EDCs will recover its costs associated with the contract through surcharges on its respective SOS customers.

In April 2012, a group of generating companies operating in the PJM region filed a complaint in the U.S. District Court for the District of Maryland challenging the MPSC’s order on the grounds that it violates the Commerce Clause and the Supremacy Clause of the U.S. Constitution. In May 2012, the Contract EDCs and other parties filed notices of appeal in circuit courts in Maryland requesting judicial review of the MPSC’s order. The Maryland circuit court appeals were consolidated in the Circuit Court for Baltimore City.

 

On April 16, 2013, the MPSC issued an order approving a final form of the contract and directing the Contract EDCs to enter into the contract with the winning bidder in amounts proportional to their relative SOS loads. On June 4, 2013, Pepco and DPL each entered into identical contracts in accordance with the terms of the MPSC’s order; however, under each contract’s terms, it will not become effective, if at all, until all legal proceedings related to these contracts and the actions of the MPSC in the related proceeding have been resolved.

On September 30, 2013, the U.S. District Court for the District of Maryland issued a ruling that the MPSC’s April 2012 order violated the Supremacy Clause of the U.S. Constitution by attempting to regulate wholesale prices. In contrast, on October 1, 2013, the Maryland Circuit Court for Baltimore City upheld the MPSC’s orders requiring the Contract EDCs to enter into the contracts.

On October 24, 2013, the Federal district court issued an order ruling that the contracts are illegal and unenforceable. The Federal district court order and its associated ruling could impact the state circuit court appeal, to which the Contract EDCs are parties, although such impact, if any, cannot be determined at this time. The Contract EDCs, the Maryland Office of People’s Counsel and one generating company have appealed the Maryland Circuit Court’s decision to the Maryland Court of Special Appeals. In addition, in November 2013 both the winning bidder and the MPSC appealed the Federal district court decision to the U.S. Court of Appeals for the Fourth Circuit. These appeals remain pending.

Assuming the contracts, as currently written, were to become effective by the expected commercial operation date of June 1, 2015, PHI continues to believe that Pepco and DPL may be required to account for their proportional share of the contracts as a derivative instrument at fair value with an offsetting regulatory asset because they would recover any payments under the contracts from SOS customers. PHI, Pepco and DPL have concluded that any accounting for these contracts would not be required until all legal proceedings related to these contracts and the actions of the MPSC in the related proceeding have been resolved.

PHI, Pepco and DPL continue to evaluate these proceedings to determine, should the contracts be found to be valid and enforceable, (i) the extent of the negative effect that the contracts may have on PHI’s, Pepco’s and DPL’s respective credit metrics, as calculated by independent rating agencies that evaluate and rate PHI, Pepco and DPL and their debt issuances, (ii) the effect on Pepco’s and DPL’s ability to recover their associated costs of the contracts if a significant number of SOS customers elect to buy their energy from alternative energy suppliers, and (iii) the effect of the contracts on the financial condition, results of operations and cash flows of each of PHI, Pepco and DPL.

ACE Standard Offer Capacity Agreements

In April 2011, ACE entered into three Standard Offer Capacity Agreements (SOCAs) by order of the NJBPU, each with a different generation company, as more fully described in Note (13), “Derivative Instruments and Hedging Activities.” ACE and the other New Jersey EDCs entered into the SOCAs under protest, arguing that the EDCs were denied due process and that the SOCAs violate certain of the requirements under the New Jersey law under which the SOCAs were established (the NJ SOCA Law). On October 22, 2013, in light of the decision of the U.S. District Court for the District of New Jersey described below, the state appeals of the NJBPU implementation orders filed by the EDCs and generators, were dismissed without prejudice subject to the parties exercising their appellate rights in the Federal courts.

In February 2011, ACE joined other plaintiffs in an action filed in the U.S. District Court for the District of New Jersey challenging the NJ SOCA Law on the grounds that it violates the Commerce Clause and the Supremacy Clause of the U.S. Constitution. On October 11, 2013, the Federal district court issued a ruling that the NJ SOCA Law is preempted by the Federal Power Act and violates the Supremacy Clause, and is therefore null and void. On October 21, 2013 a joint motion to stay the Federal district court’s decision pending appeal was filed by the NJBPU and one of the SOCA generation companies. In that motion, the NJBPU notified the Federal district court that it would take no action to force implementation of the SOCAs pending the appeal or such other action—such as FERC approval of the SOCAs—that would cure the constitutional issues to the Federal district court’s satisfaction. On October 25, 2013, the Federal district court issued an order denying the joint motion to stay and ruling that the SOCAs are void, invalid and unenforceable. On October 31, 2013, one of the SOCA generation companies filed a notice of appeal of the October 25, 2013 Federal district court decision with the U.S. Court of Appeals for the Third Circuit (the Federal circuit court). On November 8, 2013, the other remaining SOCA generating company filed a motion to intervene in the proceedings and a notice of appeal of the October 25, 2013 Federal district court decision. On November 21, 2013, the NJBPU filed its notice of appeal of the October 25, 2013 Federal district court decision. On November 14, 2013, the Federal circuit court granted the motion to intervene and on December 13, 2013, the Federal circuit court issued an order consolidating the appeals filed by the NJBPU and the SOCA generating companies of the October 25, 2013 Federal district court decision. The matter has been placed on an expedited schedule and appeal proceedings remain pending. The Federal circuit court is tentatively scheduled to hear the appeal on March 27, 2014.

One of the three SOCAs was terminated effective July 1, 2013 because of an event of default of the generation company that was a party to the SOCA. The remaining two SOCAs were terminated effective November 19, 2013, as a result of a termination notice delivered by ACE after the Federal district court’s October 25, 2013 decision.

In light of the Federal district court order (which has not been stayed pending appeal), ACE derecognized both the derivative assets (liabilities) for the estimated fair value of the SOCAs and the offsetting regulatory liabilities (assets) in the fourth quarter of 2013.

Resiliency Task Forces

In July 2012, the Maryland governor signed an Executive Order directing his energy advisor, in collaboration with certain state agencies, to solicit input and recommendations from experts on how to improve the resiliency and reliability of the electric distribution system in Maryland. The resulting Grid Resiliency Task Force issued its report in September 2012, in which it made 11 recommendations. The governor forwarded the report to the MPSC in October 2012, urging the MPSC to quickly implement the first four recommendations: (i) strengthen existing reliability and storm restoration regulations; (ii) accelerate the investment necessary to meet the enhanced metrics; (iii) allow surcharge recovery for the accelerated investment; and (iv) implement clearly defined performance metrics into the traditional ratemaking scheme. Pepco’s electric distribution base rate case filed with the MPSC on November 30, 2012 and DPL’s electric distribution base rate case filed with the MPSC on March 29, 2013, each attempted to address the Grid Resiliency Task Force recommendations. In July and August 2013, the MPSC issued orders in the Pepco and DPL Maryland electric distribution base rate cases, respectively, that only partially approved the proposed Grid Resiliency Charge. See “Rate Proceedings – Maryland” above for more information about these base rate cases.

In August 2012, the District of Columbia mayor issued an Executive Order establishing the Mayor’s Power Line Undergrounding Task Force (the DC Undergrounding Task Force). The stated purpose of the DC Undergrounding Task Force was to pool the collective resources available in the District of Columbia to produce an analysis of the technical feasibility, infrastructure options and reliability implications of undergrounding new or existing overhead distribution facilities in the District of Columbia. These resources included legislative bodies, regulators, utility personnel, experts and other parties who could contribute in a meaningful way to the DC Undergrounding Task Force. On May 13, 2013, the DC Undergrounding Task Force issued a written recommendation endorsing a $1 billion plan of the DC Undergrounding Task Force to underground 60 of the District of Columbia’s most outage-prone power lines, which lines would be owned and maintained by Pepco. The legislation providing for implementation of the report’s recommendations contemplates that: (i) Pepco would fund approximately $500 million of the $1 billion estimated cost to complete this project, recovering those costs through surcharges on the electric bills of Pepco District of Columbia customers; (ii) $375 million of the undergrounding project cost would be financed by the District of Columbia’s issuance of securitized bonds, which bonds would be repaid through surcharges on the electric bills of Pepco District of Columbia customers (Pepco would not earn a return on or of the cost of the assets funded with the proceeds received from the issuance of the securitized bonds, but ownership and responsibility for the operation and maintenance of such assets would be transferred to Pepco for a nominal amount); and (iii) the remaining amount would be funded through the District of Columbia Department of Transportation’s existing capital projects program. This legislation was approved in the Council of the District of Columbia on February 4, 2014 and is awaiting the signature of the Mayor of the District of Columbia. Once signed by the Mayor and transmitted to Congress, the legislation will undergo a 30-day Congressional review period before becoming law, which is expected to occur in the second quarter of 2014. The final step would be DCPSC approval of the underground project plan and financing orders required by the legislation to establish the customer surcharges contemplated by the legislation, a decision on which is expected during the fourth quarter of 2014.

MAPP Project

On August 24, 2012, the board of PJM terminated the MAPP project and removed it from PJM’s regional transmission expansion plan. PHI had been directed to construct the MAPP project, a 152-mile high-voltage interstate transmission line, to address the reliability needs of the region’s transmission system. In December 2012, PHI submitted a filing to FERC seeking recovery of approximately $88 million of abandoned MAPP costs over a five-year recovery period. The FERC filing addressed, among other things, the prudence of the recoverable costs incurred, the proposed period over which the abandoned costs are to be amortized and the rate of return on these costs during the recovery period.

In February 2013, FERC issued an order concluding that the MAPP project was cancelled for reasons beyond the control of Pepco and DPL, finding that the prudently incurred costs associated with the abandonment of the MAPP project are eligible to be recovered, and setting for hearing and settlement procedures the prudence of the abandoned costs and the amortization period for those costs.

On December 18, 2013, PHI submitted a settlement agreement to FERC, which provides for recovery of PHI’s abandoned MAPP costs over a three-year recovery period beginning June 1, 2013. The settlement agreement, which is subject to FERC approval, would resolve all issues concerning the recovery of abandonment costs associated with the cancellation of the MAPP project. PHI cannot predict the timing or results of a final FERC decision in this proceeding.

As of December 31, 2013, PHI had a regulatory asset related to the MAPP abandoned costs of approximately $68 million, representing the original filing amount of approximately $88 million of abandoned costs referred to above less: (i) approximately $2 million of disallowed costs written off in 2013; (ii) $4 million of materials transferred to inventories for use on other projects; and (iii) $14 million of amortization expense recorded in 2013. The regulatory asset balance includes the costs of land, land rights, engineering and design, environmental services, and project management and administration.

 

 

Potomac Electric Power Co [Member]
 
Regulatory Matters

 

(6) REGULATORY MATTERS

Regulatory Assets and Regulatory Liabilities

The components of Pepco’s regulatory asset and liability balances at December 31, 2013 and 2012 are as follows:

 

     2013      2012  
     (millions of dollars)  

Regulatory Assets

     

Smart Grid costs (a)

   $ 168       $ 159   

Recoverable income taxes

     107         75   

Demand-side management costs (a)

     98         45   

Incremental storm restoration costs (a)

     37         44   

MAPP abandonment costs (a)

     37         50   

Recoverable workers’ compensation and long-term disability costs

     26         31   

Deferred debt extinguishment costs (a)

     25         28   

Deferred energy supply costs

     6         4   

Other

     59         51   
  

 

 

    

 

 

 

Total Regulatory Assets

   $ 563       $ 487   
  

 

 

    

 

 

 

Regulatory Liabilities

     

Asset removal costs

   $ 102       $ 122   

Other

     11         19   
  

 

 

    

 

 

 

Total Regulatory Liabilities

   $ 113       $ 141   
  

 

 

    

 

 

 

 

(a) A return is generally earned on these deferrals.

A description for each category of regulatory assets and regulatory liabilities follows:

Smart Grid Costs: Represents advanced metering infrastructure (AMI) costs associated with the installation of smart meters and the early retirement of existing meters throughout Pepco’s service territory that are recoverable from customers.

Recoverable Income Taxes: Represents amounts recoverable from Pepco’s customers for tax benefits applicable to utility operations that were previously recognized in income tax expense before the company was ordered to account for the tax benefits as deferred income taxes. As the temporary differences between the financial statement basis and tax basis of assets reverse, the deferred recoverable balances are reversed.

Demand-Side Management Costs: Represents recoverable costs associated with customer energy efficiency and conservation programs in Pepco’s Maryland jurisdiction.

Incremental Storm Restoration Costs: Represents total incremental storm restoration costs incurred for repair work due to major storm events in 2012 and 2011, including Hurricane Sandy, the June 2012 derecho, Hurricane Irene, and the 2011 severe winter storm, that are recoverable from customers in the Maryland jurisdiction. Pepco’s costs related to Hurricane Sandy, the June 2012 derecho, Hurricane Irene and the 2011 severe winter storm are being amortized and recovered in rates, each over a five-year period.

MAPP Abandonment Costs: Represents the probable recovery of abandoned costs prudently incurred in connection with the Mid-Atlantic Power Pathway (MAPP) project which was terminated on August 24, 2012. The regulatory asset includes the costs of land, land rights, supplies and materials, engineering and design, environmental services, and project management and administration. The regulatory asset will be reduced as the result of sale or alternative use of these assets. As of December 31, 2013, these assets were earning a return of 12.8%. For additional information, see “MAPP Project” discussion below.

 

Recoverable Workers’ Compensation and Long-Term Disability Costs: Represents accrued workers’ compensation and long-term disability costs for Pepco, which are recoverable from customers when actual claims are paid to employees.

Deferred Debt Extinguishment Costs: Represents the costs of debt extinguishment associated with issuances of debt for which recovery through regulated utility rates is considered probable, and if approved, will be amortized to interest expense during the authorized rate recovery period.

Deferred Energy Supply Costs: The regulatory asset represents primarily deferred costs associated with a net under-recovery of Default Electricity Supply costs incurred by Pepco that are probable of recovery in rates.

Other: Represents miscellaneous regulatory assets that generally are being amortized over 1 to 20 years.

Asset Removal Costs: The depreciation rates for Pepco include a component for removal costs, as approved by the relevant federal and state regulatory commissions. Accordingly, Pepco has recorded regulatory liabilities for its estimate of the difference between incurred removal costs and the amount of removal costs recovered through depreciation rates.

Other: Includes miscellaneous regulatory liabilities.

Rate Proceedings

Bill Stabilization Adjustment

Pepco proposed in each of its respective jurisdictions the adoption of a BSA mechanism to decouple retail distribution revenue from the amount of power delivered to retail customers. The BSA proposal has been approved and implemented for Pepco electric service in Maryland and in the District of Columbia.

Under the BSA, customer distribution rates are subject to adjustment (through a credit or surcharge mechanism), depending on whether actual distribution revenue per customer exceeds or falls short of the revenue-per-customer amount approved by the applicable public service commission.

District of Columbia

On March 8, 2013, Pepco filed an application with the DCPSC to increase its annual electric distribution base rates by approximately $44.8 million (as adjusted by Pepco on December 3, 2013), based on a requested ROE of 10.25%. The requested rate increase seeks to recover expenses associated with Pepco’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. Evidentiary hearings were held in November 2013 and a final DCPSC decision is expected in the first quarter of 2014.

Maryland

In December 2011, Pepco submitted an application with the MPSC to increase its electric distribution base rates. The filing sought approval of an annual rate increase of approximately $68.4 million (subsequently reduced by Pepco to $66.2 million), based on a requested ROE of 10.75%. In July 2012, the MPSC issued an order approving an annual rate increase of approximately $18.1 million, based on an ROE of 9.31%. The order also reduced Pepco’s depreciation rates, which lowered annual depreciation and amortization expenses by an estimated $27.3 million. The lower depreciation rates resulted from, among other things, the rebalancing of excess reserves for estimated future removal costs identified in a depreciation study conducted as part of the rate case filing. The identified excess reserves for estimated future removal costs, reported as Regulatory liabilities, were reclassified to Accumulated depreciation among various plant accounts. Among other things, the order additionally authorized Pepco to recover the actual cost of AMI meters installed during the 2011 test year and states that cost recovery for AMI deployment will be allowed in future rate cases in which Pepco demonstrates that the system is cost effective. The new revenue rates and lower depreciation rates were effective on July 20, 2012. The Maryland OPC has sought rehearing on the portion of the order allowing Pepco to recover the costs of AMI meters installed during the test year; that motion remains pending.

On November 30, 2012, Pepco submitted an application with the MPSC to increase its electric distribution base rates. The filing sought approval of an annual rate increase of approximately $60.8 million, based on a requested ROE of 10.25%. The requested rate increase sought to recover expenses associated with Pepco’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. Pepco also proposed a three-year Grid Resiliency Charge rider for recovery of costs totaling approximately $192 million associated with its plan to accelerate investments in infrastructure in a condensed timeframe. Acceleration of resiliency improvements was one of several recommendations included in a September 2012 report from Maryland’s Grid Resiliency Task Force (as discussed below under “Resiliency Task Forces”). Specific projects under Pepco’s Grid Resiliency Charge plan included acceleration of its tree-trimming cycle, upgrade of 12 additional feeders per year for two years and undergrounding of six distribution feeders. In addition, Pepco proposed a reliability performance-based mechanism that would allow Pepco to earn up to $1 million as an incentive for meeting enhanced reliability goals in 2015, but provided for a credit to customers of up to $1 million in total if Pepco does not meet at least the minimum reliability performance targets. Pepco requested that any credits/charges would flow through the proposed Grid Resiliency Charge rider.

On July 12, 2013, the MPSC issued an order related to Pepco’s November 30, 2012 application approving an annual rate increase of approximately $27.9 million, based on an ROE of 9.36%. The order provides for the full recovery of storm restoration costs incurred as a result of recent major storm events, including the derecho storm in June 2012 and Hurricane Sandy in October 2012, by including the related capital costs in the rate base and amortizing the related deferred operation and maintenance expenses of $23.6 million over a five-year period. The order excludes the cost of AMI meters from Pepco’s rate base until such time as Pepco demonstrates the cost effectiveness of the AMI system; as a result, costs for AMI meters incurred with respect to the 2012 test year and beyond will be treated as other incremental AMI costs incurred in conjunction with the deployment of the AMI system that are deferred and on which a return is earned, but only until such cost effectiveness has been demonstrated and such costs are included in rates. However, the MPSC’s July 2012 order in Pepco’s previous electric distribution base rate case, which allowed Pepco to recover the costs of meters installed during the 2011 test year for that case, remains in effect, and the Maryland OPC’s motion for rehearing in that case remains pending.

The order also approved a Grid Resiliency Charge for recovery of costs totaling approximately $24.0 million associated with Pepco’s proposed plan to accelerate investments related to certain priority feeders, provided that, before implementing the surcharge, Pepco provides additional information to the MPSC related to performance objectives, milestones and costs, and makes annual filings with the MPSC thereafter concerning this project, which will permit the MPSC to establish the applicable Grid Resiliency Charge rider for each following year. The MPSC did not approve the proposed acceleration of the tree-trimming cycle or the undergrounding of six distribution feeders. The MPSC also rejected Pepco’s proposed reliability performance-based mechanism. The new rates were effective on July 12, 2013.

On July 26, 2013, Pepco filed a notice of appeal of the July 12, 2013 order in the Circuit Court for the City of Baltimore. Other parties also have filed notices of appeal, which have been consolidated with Pepco’s appeal. In its memorandum filed with the appeals court, Pepco asserts that the MPSC erred in failing to grant Pepco an adequate ROE, denying a number of other cost recovery mechanisms and limiting Pepco’s test year data to no more than four months of forecasted data in future rate cases. The memoranda filed with the appeals court by the other parties primarily assert that the MPSC erred or acted arbitrarily and capriciously in allowing the recovery of certain costs by Pepco and refusing to reduce Pepco’s rate base by known and measurable accumulated depreciation.

 

On December 4, 2013, Pepco submitted an application with the MPSC to increase its electric distribution base rates. The filing seeks approval of an annual rate increase of approximately $43.3 million, based on a requested ROE of 10.25%. The requested rate increase seeks to recover expenses associated with Pepco’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. A decision is expected in the third quarter of 2014.

Federal Energy Regulatory Commission

On February 27, 2013, the public service commissions and public advocates of the District of Columbia, Maryland, Delaware and New Jersey, as well as the Delaware Municipal Electric Corporation, Inc., filed a joint complaint with the Federal Energy Regulatory Commission (FERC) against Pepco and its affiliates Delmarva Power & Light Company (DPL) and Atlantic City Electric Company (ACE), as well as Baltimore Gas and Electric Company (BGE). The complainants challenged the base ROE and the application of the formula rate process, each associated with the transmission service that Pepco and its utility affiliates provide. The complainants support an ROE within a zone of reasonableness of 6.78% and 10.33%, and have argued for a base ROE of 8.7%. The base ROE currently authorized by FERC for Pepco and its utility affiliates is (i) 11.3% for facilities placed into service after January 1, 2006, and (ii) 10.8% for facilities placed into service prior to 2006. As currently authorized, the 10.8% base ROE for facilities placed into service prior to 2006 is eligible for a 50-basis-point incentive adder for being a member of a regional transmission organization. Pepco believes the allegations in this complaint are without merit and is vigorously contesting it. On April 3, 2013, Pepco filed its answer to this complaint, requesting that FERC dismiss the complaint against it on the grounds that it failed to meet the required burden to demonstrate that the existing rates and protocols are unjust and unreasonable. Pepco cannot predict when a final FERC decision in this proceeding will be issued.

MPSC New Generation Contract Requirement

In September 2009, the MPSC initiated an investigation into whether Maryland electric distribution companies (EDCs) should be required to enter into long-term contracts with entities that construct, acquire or lease, and operate, new electric generation facilities in Maryland. In April 2012, the MPSC issued an order determining that there is a need for one new power plant in the range of 650 to 700 megawatts (MWs) beginning in 2015. The order requires Pepco, its affiliate DPL and BGE (collectively, the Contract EDCs) to negotiate and enter into a contract with the winning bidder of a competitive bidding process in amounts proportional to their relative Standard Offer Service (SOS) loads. Under the contract, the winning bidder will construct a 661 MW natural gas-fired combined cycle generation plant in Waldorf, Maryland, with an expected commercial operation date of June 1, 2015. The order acknowledged the Contract EDCs’ concerns about the requirements of the contract and directed them to negotiate with the winning bidder and submit any proposed changes in the contract to the MPSC for approval. The order further specified that each of the Contract EDCs will recover its costs associated with the contract through surcharges on its respective SOS customers.

In April 2012, a group of generating companies operating in the PJM Interconnection, LLC (PJM) region filed a complaint in the U.S. District Court for the District of Maryland challenging the MPSC’s order on the grounds that it violates the Commerce Clause and the Supremacy Clause of the U.S. Constitution. In May 2012, the Contract EDCs and other parties filed notices of appeal in circuit courts in Maryland requesting judicial review of the MPSC’s order. The Maryland circuit court appeals were consolidated in the Circuit Court for Baltimore City.

On April 16, 2013, the MPSC issued an order approving a final form of the contract and directing the Contract EDCs to enter into the contract with the winning bidder in amounts proportional to their relative SOS loads. On June 4, 2013, Pepco and DPL each entered into identical contracts in accordance with the terms of the MPSC’s order; however, under each contract’s terms, it will not become effective, if at all, until all legal proceedings related to these contracts and the actions of the MPSC in the related proceeding have been resolved.

 

On September 30, 2013, the U.S. District Court for the District of Maryland issued a ruling that the MPSC’s April 2012 order violated the Supremacy Clause of the U.S. Constitution by attempting to regulate wholesale prices. In contrast, on October 1, 2013, the Maryland Circuit Court for Baltimore City upheld the MPSC’s orders requiring the Contract EDCs to enter into the contracts.

On October 24, 2013, the Federal district court issued an order ruling that the contracts are illegal and unenforceable. The Federal district court order and its associated ruling could impact the state circuit court appeal, to which the Contract EDCs are parties, although such impact, if any, cannot be determined at this time. The Contract EDCs, the Maryland Office of People’s Counsel and one generating company have appealed the Maryland Circuit Court’s decision to the Maryland Court of Special Appeals. In addition, in November 2013 both the winning bidder and the MPSC appealed the Federal district court decision to the U.S. Court of Appeals for the Fourth Circuit. These appeals remain pending.

Assuming the contracts, as currently written, were to become effective by the expected commercial operation date of June 1, 2015, Pepco continues to believe that it may be required to account for its proportional share of the contracts as a derivative instrument at fair value with an offsetting regulatory asset because they would recover any payments under the contracts from SOS customers. Pepco has concluded that any accounting for these contracts would not be required until all legal proceedings related to these contracts and the actions of the MPSC in the related proceeding have been resolved.

Pepco continues to evaluate these proceedings to determine, should the contracts be found to be valid and enforceable, (i) the extent of the negative effect that the contracts may have on Pepco’s credit metrics, as calculated by independent rating agencies that evaluate and rate Pepco and its debt issuances, (ii) the effect on Pepco’s ability to recover its associated costs of the contracts if a significant number of SOS customers elect to buy their energy from alternative energy suppliers, and (iii) the effect of the contracts on the financial condition, results of operations and cash flows of Pepco.

Resiliency Task Forces

In July 2012, the Maryland governor signed an Executive Order directing his energy advisor, in collaboration with certain state agencies, to solicit input and recommendations from experts on how to improve the resiliency and reliability of the electric distribution system in Maryland. The resulting Grid Resiliency Task Force issued its report in September 2012, in which it made 11 recommendations. The governor forwarded the report to the MPSC in October 2012, urging the MPSC to quickly implement the first four recommendations: (i) strengthen existing reliability and storm restoration regulations; (ii) accelerate the investment necessary to meet the enhanced metrics; (iii) allow surcharge recovery for the accelerated investment; and (iv) implement clearly defined performance metrics into the traditional ratemaking scheme. Pepco’s electric distribution base rate case filed with the MPSC on November 30, 2012 attempted to address the Grid Resiliency Task Force recommendations. In July 2013, the MPSC issued an order in the Pepco Maryland electric distribution base rate case that only partially approved the proposed Grid Resiliency Charge. See “Rate Proceedings – Maryland” above for more information about the base rate case.

In August 2012, the District of Columbia mayor issued an Executive Order establishing the Mayor’s Power Line Undergrounding Task Force (the DC Undergrounding Task Force). The stated purpose of the DC Undergrounding Task Force was to pool the collective resources available in the District of Columbia to produce an analysis of the technical feasibility, infrastructure options and reliability implications of undergrounding new or existing overhead distribution facilities in the District of Columbia. These resources included legislative bodies, regulators, utility personnel, experts and other parties who could contribute in a meaningful way to the DC Undergrounding Task Force. On May 13, 2013, the DC Undergrounding Task Force issued a written recommendation endorsing a $1 billion plan of the DC Undergrounding Task Force to underground 60 of the District of Columbia’s most outage-prone power lines, which lines would be owned and maintained by Pepco. The legislation providing for implementation of the report’s recommendations contemplates that: (i) Pepco would fund approximately $500 million of the $1 billion estimated cost to complete this project, recovering those costs through surcharges on the electric bills of Pepco District of Columbia customers; (ii) $375 million of the undergrounding project cost would be financed by the District of Columbia’s issuance of securitized bonds, which bonds would be repaid through surcharges on the electric bills of Pepco District of Columbia customers (Pepco would not earn a return on or of the cost of the assets funded with the proceeds received from the issuance of the securitized bonds, but ownership and responsibility for the operation and maintenance of such assets would be transferred to Pepco for a nominal amount); and (iii) the remaining amount would be funded through the District of Columbia Department of Transportation’s existing capital projects program. This legislation was approved in the Council of the District of Columbia on February 4, 2014 and is awaiting the signature of the Mayor of the District of Columbia. Once signed by the Mayor and transmitted to Congress, the legislation will undergo a 30-day Congressional review period before becoming law, which is expected to occur in the second quarter of 2014. The final step would be DCPSC approval of the underground project plan and financing orders required by the legislation to establish the customer surcharges contemplated by the legislation, a decision on which is expected during the fourth quarter of 2014.

MAPP Project

On August 24, 2012, the board of PJM terminated the MAPP project and removed it from PJM’s regional transmission expansion plan. Pepco had been directed to construct the MAPP project, a 152-mile high-voltage interstate transmission line, to address the reliability needs of the region’s transmission system. In December 2012, Pepco submitted a filing to FERC seeking recovery of approximately $50 million of abandoned MAPP costs over a five-year recovery period. The FERC filing addressed, among other things, the prudence of the recoverable costs incurred, the proposed period over which the abandoned costs are to be amortized and the rate of return on these costs during the recovery period.

In February 2013, FERC issued an order concluding that the MAPP project was cancelled for reasons beyond the control of Pepco, finding that the prudently incurred costs associated with the abandonment of the MAPP project are eligible to be recovered, and setting for hearing and settlement procedures the prudence of the abandoned costs and the amortization period for those costs.

On December 18, 2013, Pepco submitted a settlement agreement to FERC, which provides for recovery of Pepco’s abandoned MAPP costs over a three-year recovery period beginning June 1, 2013. The settlement agreement, which is subject to FERC approval, would resolve all issues concerning the recovery of abandonment costs associated with the cancellation of the MAPP project. Pepco cannot predict the timing or results of a final FERC decision in this proceeding.

As of December 31, 2013, Pepco had a regulatory asset related to the MAPP abandoned costs of approximately $37 million, representing the original filing amount of approximately $50 million of abandoned costs referred to above less: (i) approximately $1 million of disallowed costs written off in 2013; (ii) $4 million of materials transferred to inventories for use on other projects; and (iii) $8 million of amortization expense recorded in 2013. The regulatory asset balance includes the costs of land, land rights, engineering and design, environmental services, and project management and administration.

 

Delmarva Power & Light Co/De [Member]
 
Regulatory Matters

(7) REGULATORY MATTERS

Regulatory Assets and Regulatory Liabilities

The components of DPL’s regulatory asset and liability balances at December 31, 2013 and 2012 are as follows:

 

     2013      2012  
     (millions of dollars)  

Regulatory Assets

     

Smart Grid costs (a)

   $ 83       $ 71   

Recoverable income taxes

     76         69   

MAPP abandonment costs (a)

     31         38   

Demand-side management costs (a)

     27         12   

COPCO acquisition adjustment (a)

     22         26   

Deferred debt extinguishment costs (a)

     13         15   

Deferred energy supply costs (b)

     13         13   

Incremental storm restoration costs (a)

     9         11   

Deferred losses on gas derivatives

     —           4   

Other

     37         29   
  

 

 

    

 

 

 

Total Regulatory Assets

   $ 311       $ 288   
  

 

 

    

 

 

 

Regulatory Liabilities

     

Asset removal costs

   $ 173       $ 202   

Deferred income taxes due to customers

     37         38   

Deferred energy supply costs

     3         6   

Deferred gains on gas derivatives

     1         —     

Other

     15         12   
  

 

 

    

 

 

 

Total Regulatory Liabilities

   $         229       $         258   
  

 

 

    

 

 

 

 

(a) A return is earned on these deferrals.
(b) A return is generally earned in Delaware on this deferral.

A description for each category of regulatory assets and regulatory liabilities follows:

Smart Grid Costs: Represents advanced metering infrastructure (AMI) costs associated with the installation of smart meters and the early retirement of existing meters throughout DPL’s service territory that are recoverable from customers.

Recoverable Income Taxes: Represents amounts recoverable from DPL’s customers for tax benefits applicable to utility operations that were previously recognized in income tax expense before the company was ordered to account for the tax benefits as deferred income taxes. As the temporary differences between the financial statement basis and tax basis of assets reverse, the deferred recoverable balances are reversed.

MAPP Abandonment Costs: Represents the probable recovery of abandoned costs prudently incurred in connection with the Mid-Atlantic Power Pathway (MAPP) project which was terminated on August 24, 2012. The regulatory asset includes the costs of land, land rights, supplies and materials, engineering and design, environmental services, and project management and administration. The regulatory asset will be reduced as the result of sale or alternative use of these assets. As of December 31, 2013, these assets were earning a return of 12.8%. For additional information, see “MAPP Project” discussion below.

Demand-Side Management Costs: Represents recoverable costs associated with customer energy efficiency and conservation programs in DPL’s Maryland jurisdiction.

 

COPCO Acquisition Adjustment: On July 19, 2007, the MPSC issued an order which provided for the recovery of a portion of DPL’s goodwill. As a result of this order, $41 million in DPL goodwill was transferred to a regulatory asset. This item is being amortized from August 2007 through August 2018. The return earned is 12.95%.

Deferred Debt Extinguishment Costs: Represents the costs of debt extinguishment associated with issuances of debt for which recovery through regulated utility rates is considered probable, and if approved, will be amortized to interest expense during the authorized rate recovery period.

Deferred Energy Supply Costs: The regulatory asset represents primarily deferred costs associated with a net under-recovery of Default Electricity Supply costs incurred by DPL that are probable of recovery in rates. The regulatory liability represents primarily deferred costs associated with a net over-recovery of Default Electricity Supply costs incurred that will be refunded by DPL to customers.

Incremental Storm Restoration Costs: Represents total incremental storm restoration costs incurred for repair work due to major storm events in 2012 and 2011, including Hurricane Sandy, the June 2012 derecho, and Hurricane Irene, that are recoverable from customers in the Maryland jurisdiction. DPL’s costs related to Hurricane Sandy, the June 2012 derecho and Hurricane Irene are being amortized and recovered in rates, each over a five-year period.

Deferred Losses on Gas Derivatives: Represents losses associated with hedges of natural gas purchases that are recoverable through the Gas Cost Rate approved by the DPSC.

Other: Represents miscellaneous regulatory assets that generally are being amortized over 1 to 20 years.

Asset Removal Costs: The depreciation rates for DPL include a component for removal costs, as approved by the relevant federal and state regulatory commissions. Accordingly, DPL has recorded regulatory liabilities for its estimate of the difference between incurred removal costs and the amount of removal costs recovered through depreciation rates.

Deferred Income Taxes Due to Customers: Represents the portions of deferred income tax assets applicable to utility operations of DPL that have not been reflected in current customer rates for which future payment to customers is probable. As the temporary differences between the financial statement basis and tax basis of assets reverse, deferred recoverable income taxes are amortized.

Deferred Gains on Gas Derivatives: Represents gains associated with hedges of natural gas purchases that will be refunded to customers through the Gas Cost Rate approved by the DPSC.

Other: Includes miscellaneous regulatory liabilities.

Rate Proceedings

Bill Stabilization Adjustment

DPL has proposed in each of its respective jurisdictions the adoption of a mechanism to decouple retail distribution revenue from the amount of power delivered to retail customers. To date:

 

    A BSA has been approved and implemented for DPL electric service in Maryland.

 

    A proposed modified fixed variable rate design (MFVRD) for DPL electric and natural gas service in Delaware was filed in 2009 for consideration by the DPSC and while there was little activity associated with this filing in 2013, the proceeding remains open.

 

Under the BSA, customer distribution rates are subject to adjustment (through a credit or surcharge mechanism), depending on whether actual distribution revenue per customer exceeds or falls short of the revenue-per-customer amount approved by the applicable public service commission. The MFVRD proposed in Delaware contemplates a fixed customer charge (i.e., not tied to the customer’s volumetric consumption of electricity or natural gas) to recover the utility’s fixed costs, plus a reasonable rate of return.

Delaware

Electric Distribution Base Rates

On March 22, 2013, DPL submitted an application with the DPSC to increase its electric distribution base rates. The filing seeks approval of an annual rate increase of approximately $39 million (as adjusted by DPL on September 20, 2013), based on a requested return on equity (ROE) of 10.25%. The requested rate increase seeks to recover expenses associated with DPL’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. The DPSC suspended the full proposed increase and, as permitted by state law, DPL implemented an interim increase of $2.5 million on June 1, 2013, subject to refund and pending final DPSC approval. On October 8, 2013, the DPSC approved DPL’s request to implement an additional interim increase of $25.1 million, effective on October 22, 2013, bringing the total interim rates in effect subject to refund to $27.6 million. A final DPSC decision is expected by the second quarter of 2014.

Forward Looking Rate Plan

On October 2, 2013, DPL filed a multi-year rate plan, referred to as the Forward Looking Rate Plan (FLRP). As proposed, the FLRP would provide for annual electric distribution base rate increases over a four-year period in the aggregate amount of approximately $56 million. The FLRP as proposed provides the opportunity to achieve estimated earned ROEs of 7.41% and 8.80% in years one and two, respectively, and 9.75% in both years three and four of the plan.

In addition, DPL proposed that as part of the FLRP, in order to provide a higher minimum required standard of reliability for DPL’s customers than that to which DPL is currently subject, the standards by which DPL’s reliability is measured would be made more stringent in each year of the FLRP. In addition, DPL has offered to refund an aggregate of $500,000 to customers in each year of the FLRP that it fails to meet the proposed stricter minimum reliability standards.

On October 22, 2013, the DPSC opened a docket for the purpose of reviewing the details of the FLRP, but stated that it would not address the FLRP until the pending electric distribution base rate case discussed above was concluded. DPL expects that the FLRP will be updated and re-filed at the conclusion of the electric distribution base rate case. A schedule for the FLRP docket has not yet been established.

Gas Distribution Base Rates

On December 7, 2012, DPL submitted an application with the DPSC to increase its natural gas distribution base rates. The filing sought approval of an annual rate increase of approximately $12.0 million (as adjusted by DPL on July 15, 2013), based on a requested ROE of 10.25%. The requested rate increase sought to recover expenses associated with DPL’s ongoing efforts to maintain safe and reliable gas service. On October 22, 2013, the DPSC approved a settlement entered into on August 27, 2013 by the DPSC Staff, the Delaware Division of the Public Advocate and DPL, which provides for an annual rate increase of $6.8 million. While the approved settlement provided that no understanding was reached concerning the appropriate ROE, it specified that for reporting purposes and for calculating the AFUDC, construction work in process (CWIP), regulatory asset carrying costs and other accounting metrics, the rate of 9.75% should be used. The new rates became effective on November 1, 2013.

The approved settlement also provides for a phase-in of the recovery of the deferred costs associated with DPL’s deployment of the interface management unit (IMU). The IMU is part of its AMI and allows for the remote reading of gas meters. Recovery of such costs will occur through base rates over a two-year period, assuming specific milestones are met and pursuant to the following schedule: 50% of the IMU portion of DPL’s AMI will be put into rates on May 1, 2014, and the remainder will be put into rates on March 1, 2015. DPL also agreed in the settlement that its next natural gas distribution base rate application may be filed with the DPSC no earlier than January 1, 2015.

Gas Cost Rates

DPL makes an annual Gas Cost Rate (GCR) filing with the DPSC for the purpose of allowing DPL to recover natural gas procurement costs through customer rates. On August 28, 2013, DPL made its 2013 GCR filing. The rates proposed in the 2013 GCR filing would result in a GCR decrease of approximately 5.5%. On September 26, 2013, the DPSC issued an order authorizing DPL to place the new rates into effect on November 1, 2013, subject to refund and pending final DPSC approval.

Maryland

On March 29, 2013, DPL submitted an application with the MPSC to increase its electric distribution base rates by approximately $22.8 million, based on a requested ROE of 10.25%. The requested rate increase sought to recover expenses associated with DPL’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. DPL also proposed a three-year Grid Resiliency Charge rider for recovery of costs totaling approximately $10.2 million associated with its plan to accelerate investments in electric distribution infrastructure in a condensed timeframe. Acceleration of resiliency improvements was one of several recommendations included in a September 2012 report from Maryland’s Grid Resiliency Task Force (as discussed below under “Resiliency Task Forces”). Specific projects under DPL’s Grid Resiliency Charge plan included accelerating its tree-trimming cycle and upgrading five additional feeders per year for two years. In addition, DPL proposed a reliability performance-based mechanism that would allow DPL to earn up to $500,000 as an incentive for meeting enhanced reliability goals in 2015, but provided for a credit to customers of up to $500,000 in total if DPL did not meet at least the minimum reliability performance targets. DPL requested that any credits or charges would flow through the proposed Grid Resiliency Charge rider.

On August 30, 2013, the MPSC issued a final order approving a settlement among DPL, the MPSC staff and the Maryland Office of People’s Counsel (OPC). The approved settlement provides for an annual rate increase of approximately $15 million. While the settlement does not specify an overall ROE, the parties did agree that the ROE for purposes of calculating the AFUDC and regulatory asset carrying costs would be 9.81%. The approved settlement also provides for (i) recovery of storm restoration costs incurred as a result of recent major storm events, including the derecho storm in June 2012 and Hurricane Sandy in October 2012, by amortizing the related deferred operation and maintenance expenses of approximately $6 million over a five-year period with the unamortized balance included in rate base, and (ii) a Grid Resiliency Charge for recovery of costs totaling approximately $4.2 million associated with DPL’s proposed plan to accelerate investments related to certain priority feeders, provided that before implementing the surcharge, DPL provides additional information to the MPSC related to performance objectives, milestones and costs, and makes annual filings with the MPSC thereafter concerning this project, which will permit the MPSC to establish the applicable Grid Resiliency Charge rider for the following year. The approved settlement does not provide for approval of a portion of the Grid Resiliency Charge related to the proposed acceleration of the tree-trimming cycle, or DPL’s proposed reliability performance-based mechanism. The new rates became effective on September 15, 2013.

Federal Energy Regulatory Commission

On October 17, 2013, FERC issued a ruling on challenges filed by the Delaware Municipal Electric Corporation, Inc. (DEMEC) to DPL’s 2011 and 2012 annual formula rate updates. In 2006, FERC approved a formula rate for DPL that is incorporated into the PJM Interconnection, LLC (PJM) tariff. The formula rate establishes the treatment of costs and revenues and the resulting rates for DPL. Pursuant to the protocols approved by FERC and after a period of discovery, interested parties have an opportunity to file challenges regarding the application of the formula rate. The FERC order sets various issues in this proceeding for hearing, including challenges regarding formula rate inputs, deferred income items, prepayments of estimated income taxes, rate base reductions, various administrative and general expenses and the inclusion in rate base of CWIP related to the MAPP project (which has been abandoned). Settlement discussions began in this matter on November 5, 2013 before an administrative law judge at FERC.

On December 12, 2013, DEMEC filed a formal challenge to the DPL 2013 annual formula rate update, including a request to consolidate the 2013 challenge with the two prior challenges. This challenge is pending at FERC. PHI cannot predict when a final FERC decision in this proceeding will be issued.

On February 27, 2013, the public service commissions and public advocates of the District of Columbia, Maryland, Delaware and New Jersey, as well as DEMEC, filed a joint complaint with FERC against DPL and its affiliates Potomac Electric Power Company (Pepco) and Atlantic City Electric Company (ACE), as well as Baltimore Gas and Electric Company (BGE). The complainants challenged the base ROE and the application of the formula rate process, each associated with the transmission service that DPL and its utility affiliates provide. The complainants support an ROE within a zone of reasonableness of 6.78% and 10.33%, and have argued for a base ROE of 8.7%. The base ROE currently authorized by FERC for DPL and its utility affiliates is (i) 11.3% for facilities placed into service after January 1, 2006, and (ii) 10.8% for facilities placed into service prior to 2006. As currently authorized, the 10.8% base ROE for facilities placed into service prior to 2006 is eligible for a 50-basis-point incentive adder for being a member of a regional transmission organization. DPL believes the allegations in this complaint are without merit and is vigorously contesting it. On April 3, 2013, DPL filed its answer to this complaint, requesting that FERC dismiss the complaint against it on the grounds that it failed to meet the required burden to demonstrate that the existing rates and protocols are unjust and unreasonable. DPL cannot predict when a final FERC decision in this proceeding will be issued.

MPSC New Generation Contract Requirement

In September 2009, the MPSC initiated an investigation into whether Maryland electric distribution companies (EDCs) should be required to enter into long-term contracts with entities that construct, acquire or lease, and operate, new electric generation facilities in Maryland. In April 2012, the MPSC issued an order determining that there is a need for one new power plant in the range of 650 to 700 megawatts (MWs) beginning in 2015. The order requires DPL, its affiliate Pepco and BGE (collectively, the Contract EDCs) to negotiate and enter into a contract with the winning bidder of a competitive bidding process in amounts proportional to their relative Standard Offer Service (SOS) loads. Under the contract, the winning bidder will construct a 661 MW natural gas-fired combined cycle generation plant in Waldorf, Maryland, with an expected commercial operation date of June 1, 2015. The order acknowledged the Contract EDCs’ concerns about the requirements of the contract and directed them to negotiate with the winning bidder and submit any proposed changes in the contract to the MPSC for approval. The order further specified that each of the Contract EDCs will recover its costs associated with the contract through surcharges on its respective SOS customers.

In April 2012, a group of generating companies operating in the PJM region filed a complaint in the U.S. District Court for the District of Maryland challenging the MPSC’s order on the grounds that it violates the Commerce Clause and the Supremacy Clause of the U.S. Constitution. In May 2012, the Contract EDCs and other parties filed notices of appeal in circuit courts in Maryland requesting judicial review of the MPSC’s order. The Maryland circuit court appeals were consolidated in the Circuit Court for Baltimore City.

On April 16, 2013, the MPSC issued an order approving a final form of the contract and directing the Contract EDCs to enter into the contract with the winning bidder in amounts proportional to their relative SOS loads. On June 4, 2013, DPL and Pepco each entered into identical contracts in accordance with the terms of the MPSC’s order; however, under each contract’s terms, it will not become effective, if at all, until all legal proceedings related to these contracts and the actions of the MPSC in the related proceeding have been resolved.

 

On September 30, 2013, the U.S. District Court for the District of Maryland issued a ruling that the MPSC’s April 2012 order violated the Supremacy Clause of the U.S. Constitution by attempting to regulate wholesale prices. In contrast, on October 1, 2013, the Maryland Circuit Court for Baltimore City upheld the MPSC’s orders requiring the Contract EDCs to enter into the contracts.

On October 24, 2013, the Federal district court issued an order ruling that the contracts are illegal and unenforceable. The Federal district court order and its associated ruling could impact the state circuit court appeal, to which the Contract EDCs are parties, although such impact, if any, cannot be determined at this time. The Contract EDCs, the Maryland Office of People’s Counsel and one generating company have appealed the Maryland Circuit Court’s decision to the Maryland Court of Special Appeals. In addition, in November 2013 both the winning bidder and the MPSC appealed the Federal district court decision to the U.S. Court of Appeals for the Fourth Circuit. These appeals remain pending.

Assuming the contracts, as currently written, were to become effective by the expected commercial operation date of June 1, 2015, DPL continues to believe that it may be required to account for its proportional share of the contracts as a derivative instrument at fair value with an offsetting regulatory asset because they would recover any payments under the contracts from SOS customers. DPL has concluded that any accounting for these contracts would not be required until all legal proceedings related to these contracts and the actions of the MPSC in the related proceeding have been resolved.

DPL continues to evaluate these proceedings to determine, should the contracts be found to be valid and enforceable, (i) the extent of the negative effect that the contracts may have on DPL’s credit metrics, as calculated by independent rating agencies that evaluate and rate DPL and its debt issuances, (ii) the effect on DPL’s ability to recover its associated costs of the contracts if a significant number of SOS customers elect to buy their energy from alternative energy suppliers, and (iii) the effect of the contracts on the financial condition, results of operations and cash flows of DPL.

Resiliency Task Force

In July 2012, the Maryland governor signed an Executive Order directing his energy advisor, in collaboration with certain state agencies, to solicit input and recommendations from experts on how to improve the resiliency and reliability of the electric distribution system in Maryland. The resulting Grid Resiliency Task Force issued its report in September 2012, in which it made 11 recommendations. The governor forwarded the report to the MPSC in October 2012, urging the MPSC to quickly implement the first four recommendations: (i) strengthen existing reliability and storm restoration regulations; (ii) accelerate the investment necessary to meet the enhanced metrics; (iii) allow surcharge recovery for the accelerated investment; and (iv) implement clearly defined performance metrics into the traditional ratemaking scheme. DPL’s electric distribution base rate case filed with the MPSC on March 29, 2013 attempted to address the Grid Resiliency Task Force recommendations. In August 2013, the MPSC issued an order in the DPL Maryland electric distribution base rate case that only partially approved the proposed Grid Resiliency Charge. See “Rate Proceedings – Maryland” above for more information about these base rate cases.

MAPP Project

On August 24, 2012, the board of PJM terminated the MAPP project and removed it from PJM’s regional transmission expansion plan. DPL had been directed to construct the MAPP project, a 152-mile high-voltage interstate transmission line, to address the reliability needs of the region’s transmission system. In December 2012, DPL submitted a filing to FERC seeking recovery of approximately $38 million of abandoned MAPP costs over a five-year recovery period. The FERC filing addressed, among other things, the prudence of the recoverable costs incurred, the proposed period over which the abandoned costs are to be amortized and the rate of return on these costs during the recovery period.

 

In February 2013, FERC issued an order concluding that the MAPP project was cancelled for reasons beyond the control of DPL, finding that the prudently incurred costs associated with the abandonment of the MAPP project are eligible to be recovered, and setting for hearing and settlement procedures the prudence of the abandoned costs and the amortization period for those costs.

On December 18, 2013, DPL submitted a settlement agreement to FERC, which provides for recovery of DPL’s abandoned MAPP costs over a three-year recovery period beginning June 1, 2013. The settlement agreement, which is subject to FERC approval, would resolve all issues concerning the recovery of abandonment costs associated with the cancellation of the MAPP project. DPL cannot predict the timing or results of a final FERC decision in this proceeding.

As of December 31, 2013, DPL had a regulatory asset related to the MAPP abandoned costs of approximately $31 million, representing the original filing amount of approximately $38 million of abandoned costs referred to above less: (i) approximately $1 million of disallowed costs written off in 2013; and (ii) $6 million of amortization expense recorded in 2013. The regulatory asset balance includes the costs of land, land rights, engineering and design, environmental services, and project management and administration.

Atlantic City Electric Co [Member]
 
Regulatory Matters

(6) REGULATORY MATTERS

Regulatory Assets and Regulatory Liabilities

The components of ACE’s regulatory asset and liability balances at December 31, 2013 and 2012 are as follows:

 

     2013      2012  
     (millions of dollars)  

Regulatory Assets

     

Securitized stranded costs (a)

   $ 350       $ 416   

Deferred energy supply costs (a)

     117         166   

Recoverable income taxes

     42         33   

Incremental storm restoration costs

     26         34   

ACE SOCAs

     —           11   

Other

     34         34   
  

 

 

    

 

 

 

Total Regulatory Assets

   $         569       $         694   
  

 

 

    

 

 

 

Regulatory Liabilities

     

Deferred energy supply costs

   $ 38       $ 62   

Federal and state tax benefits, related to securitized stranded costs

     13         16   

Excess depreciation reserve

     —           11   

ACE SOCAs

     —           8   

Other

     6         5   
  

 

 

    

 

 

 

Total Regulatory Liabilities

   $ 57       $ 102   
  

 

 

    

 

 

 

 

(a) A return is generally earned on these deferrals.

A description for each category of regulatory assets and regulatory liabilities follows:

Securitized Stranded Costs: Certain contract termination payments under a contract between ACE and an unaffiliated non-utility generator (NUG) and costs associated with the regulated operations of ACE’s electricity generation business are no longer recoverable through customer rates (collectively referred to as “stranded costs”). The stranded costs are amortized over the life of Transition Bonds issued by ACE Funding to securitize the recoverability of these stranded costs. These Transition Bonds mature between 2013 and 2023. A customer surcharge is collected by ACE to fund principal and interest payments on the Transition Bonds.

Deferred Energy Supply Costs: The regulatory asset represents primarily deferred costs associated with a net under-recovery of Basic Generation Service costs incurred by ACE that are probable of recovery in rates. The regulatory liability represents primarily deferred costs associated with a net over-recovery of Basic Generation Service costs incurred that will be refunded by ACE to customers.

Recoverable Income Taxes: Represents amounts recoverable from ACE’s customers for tax benefits applicable to utility operations previously recognized in income tax expense before the company was ordered to account for the tax benefits as deferred income taxes. As the temporary differences between the financial statement basis and tax basis of assets reverse, the deferred recoverable balances are reversed.

Incremental Storm Restoration Costs: Represents total incremental storm restoration costs incurred for repair work due to major storm events in 2012 and 2011, including Hurricane Sandy, the June 2012 derecho, and Hurricane Irene, that are recoverable from customers in the New Jersey jurisdiction. ACE’s costs related to Hurricane Sandy, the June 2012 derecho and Hurricane Irene are being amortized and recovered in rates, each over a three-year period.

 

ACE SOCAs: The regulatory asset represented unrealized losses associated with the SOCAs that ACE had entered into by order of the NJBPU. The NJBPU had ordered full recovery from distribution customers of payments made by ACE related to the SOCAs. Since these unrealized losses were non-cash, the related regulatory asset does not earn a return. The regulatory liability represented unrealized gains associated with the SOCAs that ACE had entered into by order of the NJBPU. The NJBPU had ordered that any amounts that ACE receives related to the SOCAs be remitted to its distribution customers. As further discussed below, ACE has derecognized their regulatory assets and liabilities related to the SOCAs in the fourth quarter of 2013.

Other: Represents miscellaneous regulatory assets that generally are being amortized over 1 to 20 years.

Federal and State Tax Benefits, Related to Securitized Stranded Costs: Securitized stranded costs include a portion attributable to the future tax benefit expected to be realized when the higher tax basis of the generating facilities divested by ACE is deducted for New Jersey state income tax purposes, as well as the future benefit to be realized through the reversal of federal excess deferred taxes. To account for the possibility that these tax benefits may be given to ACE’s customers through lower rates in the future, ACE established a regulatory liability. The regulatory liability related to federal excess deferred taxes will remain until such time as the Internal Revenue Service (IRS) issues its final regulations with respect to normalization of these federal excess deferred taxes.

Excess Depreciation Reserve: The excess depreciation reserve was recorded as part of an ACE New Jersey rate case settlement. This excess reserve is the result of a change in estimated depreciable lives and a change in depreciation technique from remaining life to whole life that caused an over-recovery for depreciation expense from customers when the remaining life method had been used. The excess was amortized as a reduction in Depreciation and amortization expense over an 8.25 year period, and expired in 2013.

Other: Includes miscellaneous regulatory liabilities.

Rate Proceedings

Bill Stabilization Adjustment

In 2009, ACE proposed in New Jersey the adoption of a bill stabilization adjustment (BSA) mechanism to decouple retail distribution revenue from the amount of power delivered to retail customers. The BSA proposal was not approved and there is no BSA proposal currently pending.

Under the BSA, customer distribution rates are subject to adjustment (through a credit or surcharge mechanism), depending on whether actual distribution revenue per customer exceeds or falls short of the revenue-per-customer amount approved by the applicable public service commission.

Electric Distribution Base Rates

On December 11, 2012, ACE submitted an application with the NJBPU, updated on January 4, 2013, to increase its electric distribution base rates by approximately $70.4 million (excluding sales-and-use taxes), based on a requested return on equity (ROE) of 10.25%. This proposed net increase was comprised of (i) a proposed increase to ACE’s distribution rates of approximately $72.1 million and (ii) a net decrease to ACE’s Regulatory Asset Recovery Charge (a customer charge to recover deferred, NJBPU-approved expenses incurred as part of ACE’s public service obligation) in the amount of approximately $1.7 million. The requested rate increase seeks to recover expenses associated with ACE’s ongoing investments in reliability enhancement improvements and efforts to maintain safe and reliable service. and to recover system restoration costs associated with the derecho storm in June 2012 and Hurricane Sandy in October 2012. On June 21, 2013, the NJBPU approved a settlement of the parties providing for an increase in ACE’s electric distribution base rates in the amount of $25.5 million, based on an ROE of 9.75%. The base distribution revenue increase includes full recovery of the approximately $70.0 million in incremental storm restoration costs incurred as a result of recent major storm events, including the derecho storm and Hurricane Sandy, by including the related capital costs of approximately $44.2 million in rate base and amortizing the related deferred operation and maintenance expenses of approximately $25.8 million over a three-year period. Rates were effective on July 1, 2013.

 

Update and Reconciliation of Certain Under-Recovered Balances

In February 2012 and March 2013, ACE submitted petitions with the NJBPU seeking to reconcile and update (i) charges related to the recovery of above-market costs associated with ACE’s long-term power purchase contracts with the NUGs, (ii) costs related to surcharges for the New Jersey Societal Benefit Program (a statewide public interest program for low income customers) and ACE’s uncollected accounts and (iii) operating costs associated with ACE’s residential appliance cycling program. In June 2012, the NJBPU approved a stipulation of settlement related to ACE’s February 2012 filing, which provided for an overall annual rate increase of $55.3 million that went into effect on July 1, 2012. In May 2013, the NJBPU approved a stipulation of settlement related to ACE’s March 2013 filing, which provided for an overall annual rate increase of $52.2 million (in addition to the $55.3 million approved by the NJBPU in June 2012) that went into effect on June 1, 2013. These rate increases, which primarily provide for the recovery of above-market costs associated with the NUG contracts and will have no effect on ACE’s operating income, were placed into effect provisionally and were subject to a review by the NJBPU of the final underlying costs for reasonableness and prudence. On February 19, 2014, the NJBPU approved a stipulation of settlement for both proceedings, which made final the provisional rates that went into effect on July 1, 2012 and June 1, 2013, respectively.

Service Extension Contributions Refund Order

On July 19, 2013, in compliance with a 2012 Superior Court of New Jersey Appellate Division (Appellate Division) court decision, the NJBPU released an order requiring utilities to issue refunds to persons or entities that paid non-refundable contributions for utility service extensions to certain areas described as “Areas Not Designated for Growth.” The order is limited to eligible contributions paid between March 20, 2005 and December 20, 2009. ACE is processing the refund requests that meet the eligibility criteria established in the order as they are received. Although ACE believes it received approximately $11 million of contributions between March 20, 2005 and December 20, 2009, it is currently unable to reasonably estimate the amount that it may be required to refund using the eligibility criteria established by the order. At this time, ACE does not expect that any such amount refunded will have a material effect on its consolidated financial condition, results of operations or cash flows, as any amounts that may be refunded will generally increase the value of ACE’s property, plant and equipment and may ultimately be recovered through depreciation and cost of service. It is anticipated that NJBPU will commence a rulemaking proceeding to further implement the directives of the Appellate Division decision.

Generic Consolidated Tax Adjustment Proceeding

In January 2013, the NJBPU initiated a generic proceeding to examine whether a consolidated tax adjustment (CTA) should continue to be used, and if so, how it should be calculated in determining a utility’s cost of service. Under the NJBPU’s current policy, when a New Jersey utility is included in a consolidated group income tax return, an allocated amount of any reduction in the consolidated group’s taxes as a result of losses by affiliates is used to reduce the utility’s rate base, upon which the utility earns a return. Consequently, this policy has substantially reduced ACE’s rate base and ACE’s position is that the CTA should be eliminated. A stakeholder process has been initiated by the NJBPU to aid in this examination. No formal schedule has been set for the remainder of the proceeding or for the issuance of a decision.

Federal Energy Regulatory Commission

On February 27, 2013, the public service commissions and public advocates of the District of Columbia, Maryland, Delaware and New Jersey, as well as the Delaware Municipal Electric Corporation, Inc., filed a joint complaint with FERC against ACE and its affiliates Potomac Electric Power Company (Pepco) and Delmarva Power & Light Company (DPL), as well as Baltimore Gas and Electric Company. The complainants challenged the base ROE and the application of the formula rate process, each associated with the transmission service that ACE and its utility affiliates provide. The complainants support an ROE within a zone of reasonableness of 6.78% and 10.33%, and have argued for a base ROE of 8.7%. The base ROE currently authorized by FERC for ACE and its utility affiliates is (i) 11.3% for facilities placed into service after January 1, 2006, and (ii) 10.8% for facilities placed into service prior to 2006. As currently authorized, the 10.8% base ROE for facilities placed into service prior to 2006 is eligible for a 50-basis-point incentive adder for being a member of a regional transmission organization. ACE believes the allegations in this complaint are without merit and is vigorously contesting it. On April 3, 2013, ACE filed its answer to this complaint, requesting that FERC dismiss the complaint against it on the grounds that it failed to meet the required burden to demonstrate that the existing rates and protocols are unjust and unreasonable. ACE cannot predict when a final FERC decision in this proceeding will be issued.

ACE Standard Offer Capacity Agreements

In April 2011, ACE entered into three SOCAs by order of the NJBPU, each with a different generation company, as more fully described in Note (13), “Derivative Instruments and Hedging Activities.” ACE and the other New Jersey electric distribution companies (EDCs) entered into the SOCAs under protest, arguing that the EDCs were denied due process and that the SOCAs violate certain of the requirements under the New Jersey law under which the SOCAs were established (the NJ SOCA Law). On October 22, 2013, in light of the decision of the U.S. District Court for the District of New Jersey described below, the state appeals of the NJBPU implementation orders filed by the EDCs and generators, were dismissed without prejudice subject to the parties exercising their appellate rights in the Federal courts.

In February 2011, ACE joined other plaintiffs in an action filed in the U.S. District Court for the District of New Jersey challenging the NJ SOCA Law on the grounds that it violates the Commerce Clause and the Supremacy Clause of the U.S. Constitution. On October 11, 2013, the Federal district court issued a ruling that the NJ SOCA Law is preempted by the Federal Power Act and violates the Supremacy Clause, and is therefore null and void. On October 21, 2013 a joint motion to stay the Federal district court’s decision pending appeal was filed by the NJBPU and one of the SOCA generation companies. In that motion, the NJBPU notified the Federal district court that it would take no action to force implementation of the SOCAs pending the appeal or such other action—such as FERC approval of the SOCAs—that would cure the constitutional issues to the Federal district court’s satisfaction. On October 25, 2013, the Federal district court issued an order denying the joint motion to stay and ruling that the SOCAs are void, invalid and unenforceable. On October 31, 2013, one of the SOCA generation companies filed a notice of appeal of the October 25, 2013 Federal district court decision with the U.S. Court of Appeals for the Third Circuit (the Federal circuit court). On November 8, 2013, the other remaining SOCA generating company filed a motion to intervene in the proceedings and a notice of appeal of the October 25, 2013 Federal district court decision. On November 21, 2013, the NJBPU filed its notice of appeal of the October 25, 2013 Federal district court decision. On November 14, 2013, the Federal circuit court granted the motion to intervene and on December 13, 2013, the Federal circuit court issued an order consolidating the appeals filed by the NJBPU and the SOCA generating companies of the October 25, 2013 Federal district court decision. The matter has been placed on an expedited schedule and appeal proceedings remain pending. The Federal circuit court is tentatively scheduled to hear the appeal on March 27, 2014.

One of the three SOCAs was terminated effective July 1, 2013 because of an event of default of the generation company that was a party to the SOCA. The remaining two SOCAs were terminated effective November 19, 2013, as a result of a termination notice delivered by ACE after the Federal district court’s October 25, 2013 decision.

In light of the Federal district court order (which has not been stayed pending appeal), ACE derecognized both the derivative assets (liabilities) for the estimated fair value of the SOCAs and the offsetting regulatory liabilities (assets) in the fourth quarter of 2013.