XML 39 R25.htm IDEA: XBRL DOCUMENT v3.24.1.u1
Leases, Commitments, Guarantees and Contingencies (Tables)
3 Months Ended
Mar. 31, 2024
Leases, Commitments, Guarantees and Contingencies  
Summary of related terms and discount rates

Weighted-average remaining lease term for operating leases

11.4 years

Weighted-average discount rate for operating leases

6.2%

Summary of lease costs

For the three months ended March 31,

    

2024

    

2023

Operating lease cost

$

7,259

$

24,948

Variable and short-term lease cost

 

1,033

 

803

Sublease income

(1,246)

(1,350)

Total lease cost

$

7,046

$

24,401

Schedule of future minimum rental income under operating leases

April 2024 through December 2024

    

$

15,726

2025

 

17,974

2026

 

14,910

2027

 

12,983

2028

 

9,976

Thereafter

 

56,592

Total future minimum operating lease payments

$

128,161

Summary of commitments and obligations

The following table summarizes the Company’s commitments and obligations as noted for each of the next five years and thereafter (in thousands):

    

Total

    

Apr - Dec 2024

    

2025

    

2026

    

2027

    

2028

    

Thereafter

Operating lease payments for aircraft and facility obligations

$

128,161

$

15,726

$

17,974

$

14,910

$

12,983

$

9,976

$

56,592

Firm aircraft and spare engine commitments

 

610,945

143,810

230,725

236,410

Interest commitments (1)

 

442,822

84,964

97,933

78,149

56,289

40,947

84,540

Principal maturities on long-term debt

 

2,918,971

339,156

532,255

510,598

464,289

292,862

779,811

Total commitments and obligations

$

4,100,899

$

583,656

$

878,887

$

840,067

$

533,561

$

343,785

$

920,943

(1)At March 31, 2024, the Company’s long-term debt had fixed interest rates.