During 2009, NMHG's management approved a plan to close its facility in Modena, Italy and consolidate its activities into NMHG's facility in Masate, Italy. These actions were taken to further reduce NMHG's manufacturing capacity to more appropriate levels. As a result, NMHG recognized a charge of approximately $5.6 million during 2009. Of this amount, $5.3 million related to severance and $0.3 million related to lease impairment. During 2010, $1.9 million of the accrual was reversed as a result of a reduction in the expected amount to be paid to former employees due to the finalization of an agreement with the Italian government. Severance payments of $0.3 million were made during the first six months of 2011. Payments related to this restructuring program are expected to continue through 2012. No further charges related to this plan are expected.
During 2008 and 2009, based on the decline in economic conditions, NMHG's management reduced its number of employees worldwide. As a result, NMHG recognized a charge of approximately $6.3 million in 2008 and $3.4 million in 2009 related to severance. During 2009, $1.1 million of the accrual was reversed as a result of a reduction in the expected amount paid to employees. Severance payments of $0.4 million were made during the first six months of 2011. Payments are expected to continue through 2011. No further charges related to this plan are expected.


Following is the detail of the cash charges related to the NMHG programs:
 
Total charges expected to be incurred
 
Total charges incurred through December 31, 2010
NMHG Americas
 
 
 
Severance
$
3.3


 
$
3.3


NMHG Europe
 
 
 
Severance
$
7.6


 
$
7.6


Lease termination
0.3


 
0.3


 
$
7.9


 
$
7.9


NMHG Other
 
 
 
Severance
$
1.1


 
$
1.1


Total charges
$
12.3


 
$
12.3




Following is the activity related to the liability for the NMHG programs. Amounts for severance expected to be paid within one year are included on the line “Accrued payroll” and amounts for severance expected to be paid after one year are included on the line “Other Long-term Liabilities” in the Unaudited Condensed Consolidated Balance Sheets.
 
Severance
Balance at January 1, 2011
$
2.4


Payments
(0.7
)
Foreign currency effect
0.1


Balance at June 30, 2011
$