Electric plant, construction and related agreements - Narrative (Details)
$ in Millions
12 Months Ended
Oct. 06, 2023
USD ($)
Oct. 05, 2023
USD ($)
Oct. 04, 2023
USD ($)
Feb. 18, 2019
USD ($)
Dec. 31, 2023
USD ($)
unit
MW
Public Utility Property Plant and Equipment          
Expected monthly increase in cost         $ 20.0
Vogtle Units No. 3 & No. 4          
Public Utility Property Plant and Equipment          
Ownership interest (as a percent)         30.00%
Remaining share paid by counterparty upon exercise of tender option (as a percent)         100.00%
Percentage of disallowed costs excluded from adverse event triggers         6.00%
Vogtle Units No. 3 & No. 4 | Financial Exposure Term One          
Public Utility Property Plant and Equipment          
Ownership interest (as a percent)         30.00%
Vogtle Units No. 3 & No. 4 | Financial Exposure Term Two          
Public Utility Property Plant and Equipment          
Ownership interest (as a percent)         30.00%
Vogtle Units No. 3 & No. 4 | EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.          
Public Utility Property Plant and Equipment          
Number of nuclear units | unit         2
Generating capacity (in megawatts) | MW         1,100
Vogtle Units No. 3 & No. 4 | Ownership participation agreement          
Public Utility Property Plant and Equipment          
Ownership share, generating capacity (in megawatts) | MW         660
Project budget         $ 8,200.0
Proceeds from settlement agreement         1,100.0
Vogtle Units No. 3 & No. 4 | Ownership participation agreement | Minimum          
Public Utility Property Plant and Equipment          
Project budget         8,300.0
Vogtle Units No. 3 & No. 4 | Ownership participation agreement | Maximum          
Public Utility Property Plant and Equipment          
Project budget         8,350.0
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet          
Public Utility Property Plant and Equipment          
Project budget       $ 8,400.0  
Additional construction costs       $ 800.0  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Jointly Owned Nuclear Power Plant | Georgia Power          
Public Utility Property Plant and Equipment          
Project budget   $ 19,200.0      
Total construction costs paid   241.2     384.0
Cost-sharing bands, total liability   99.0      
Cost-sharing bands, financing costs   5.0      
Payments for cost-sharing bands   66.5 $ 37.5    
Total construction costs to be paid $ 105.1 $ 346.3      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Financial Exposure Term One          
Public Utility Property Plant and Equipment          
Proportionate share of construction costs, co-owner (as a percent)       55.70%  
Additional construction costs, responsibility of co-owner       $ 80.0  
Proportionate share of additional construction costs       $ 44.0  
Proportionate share of construction costs, remaining co-owners (as a percent)       44.30%  
Proportionate share of construction costs (as a percent)       24.50%  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Financial Exposure Term Two          
Public Utility Property Plant and Equipment          
Proportionate share of construction costs, co-owner (as a percent)       65.70%  
Additional construction costs, responsibility of co-owner       $ 100.0  
Proportionate share of additional construction costs       $ 55.0  
Proportionate share of construction costs, remaining co-owners (as a percent)       34.30%  
Proportionate share of construction costs (as a percent)       19.00%  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Financial Exposure Term Three          
Public Utility Property Plant and Equipment          
Additional construction costs triggering option to tender ownership         $ 2,100.0
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum          
Public Utility Property Plant and Equipment          
Ownership approval to change primary construction contractor (as a percent)         90.00%
Ownership approval required to continue construction (as a percent)         90.00%
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | Jointly Owned Nuclear Power Plant | Georgia Power          
Public Utility Property Plant and Equipment          
Incremental costs that exceed project budget, percent   30.00%      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | Financial Exposure Term One          
Public Utility Property Plant and Equipment          
Additional construction costs       $ 800.0  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Minimum | Financial Exposure Term Two          
Public Utility Property Plant and Equipment          
Additional construction costs       1,600.0  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | Jointly Owned Nuclear Power Plant | Georgia Power          
Public Utility Property Plant and Equipment          
Incremental costs that exceed project budget, percent   66.00%      
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | Financial Exposure Term One          
Public Utility Property Plant and Equipment          
Additional construction costs       1,600.0  
Vogtle Units No. 3 & No. 4 | Global Amendments to Term Sheet | Maximum | Financial Exposure Term Two          
Public Utility Property Plant and Equipment          
Additional construction costs       $ 2,100.0  
Vogtle Unit No. 3          
Public Utility Property Plant and Equipment          
Jointly owned utility plant, amount in service         $ 4,800.0
Vogtle Unit No. 3 | Georgia Power          
Public Utility Property Plant and Equipment          
Nuclear production tax credit         $ 21.7