XML 90 R69.htm IDEA: XBRL DOCUMENT v3.24.1
Electric plant, construction and related agreements - Electric plant (Details) - USD ($)
$ in Thousands
Dec. 31, 2023
Dec. 31, 2022
Public Utility Property Plant and Equipment    
Investment $ 14,414,830 $ 9,569,359
Accumulated Depreciation (5,418,738) (5,183,589)
Total construction work in progress 3,294,641 7,716,035
Plant acquisition adjustments $ 290,725 280,396
Vogtle Units No. 1 & No. 2    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 30.00%  
Investment $ 3,035,806 3,024,112
Accumulated Depreciation $ (1,948,158) (1,916,942)
Vogtle Units No. 3 & No. 4    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 30.00%  
Investment $ 4,771,526 58,189
Accumulated Depreciation (43,418) (8,627)
Total construction work in progress $ 3,128,720 7,583,291
Hatch Units No. 1 & No. 2    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 30.00%  
Investment $ 1,019,809 991,852
Accumulated Depreciation $ (559,001) (533,771)
Wansley Units No. 1 & No. 2    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 30.00%  
Investment $ 24,710 20,312
Accumulated Depreciation $ (27,152) (15,337)
Scherer Unit No. 1    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 60.00%  
Investment $ 1,372,241 1,378,904
Accumulated Depreciation $ (660,580) (636,799)
Doyle    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 148,902 145,780
Accumulated Depreciation $ (127,378) (124,306)
Rocky Mountain Units No. 1, No. 2 & No. 3    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 75.00%  
Investment $ 618,955 616,278
Accumulated Depreciation $ (308,827) (296,624)
Hartwell    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 233,662 232,532
Accumulated Depreciation $ (131,434) (125,092)
Hawk Road Energy Facility    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 272,416 269,837
Accumulated Depreciation $ (79,985) (74,685)
Talbot    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 308,837 301,869
Accumulated Depreciation $ (167,033) (162,137)
Chattahoochee    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 343,531 324,310
Accumulated Depreciation $ (168,292) (171,272)
BC Smith Energy Facility    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 352,005 339,189
Accumulated Depreciation $ (126,886) (121,318)
TA Smith Energy Facility    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 689,198 686,517
Accumulated Depreciation $ (228,997) (208,142)
Washington County    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 171,034 170,432
Accumulated Depreciation $ (92,498) (88,585)
Baconton    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 100.00%  
Investment $ 32,987 0
Accumulated Depreciation (16,379) 0
Transmission    
Public Utility Property Plant and Equipment    
Investment 122,452 107,992
Accumulated Depreciation (65,784) (64,785)
Other production    
Public Utility Property Plant and Equipment    
Investment 101,061 106,424
Accumulated Depreciation $ (60,710) (65,922)
Scherer Unit No. 2    
Public Utility Property Plant and Equipment    
Ownership interest (as a percent) 60.00%  
Investment $ 795,698 794,830
Accumulated Depreciation (606,226) (569,245)
Environmental and other generation improvements    
Public Utility Property Plant and Equipment    
Total construction work in progress $ 165,921 $ 132,744