Vogtle Units No. 3 and No. 4 Construction Project (Tables)
3 Months Ended
Mar. 31, 2022
Vogtle Units No. 3 and No. 4 Construction Project  
Schedule of Project Budget and Actual Costs The table below shows our project budgets and actual costs through March 31, 2022 for our share of the project.
(in millions)
Project Budget - No TenderProject Budget - TenderActual Costs at
March 31, 2022
Construction Costs (1)
$6,487 $6,096 $5,621 
Financing Costs1,922 1,914 1,561 
   Total Costs$8,409 $8,010 $7,182 
Project-Level Contingency$70 $70 $— 
Oglethorpe-Level Contingency21 20 — 
   Total Contingency$91 $90 $— 
Totals$8,500 $8,100 $7,182 
(1) Construction costs are net of $1.1 billion we received from Toshiba Corporation under a Guarantee Settlement Agreement.