XML 61 R48.htm IDEA: XBRL DOCUMENT v3.21.2
Vogtle Units No. 3 and No. 4 Construction Project - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4 - USD ($)
$ in Millions
3 Months Ended 6 Months Ended
Jun. 30, 2021
Mar. 31, 2021
Dec. 31, 2020
Jun. 30, 2021
Project Budget        
Project-Level Contingency $ 78.0 $ 32.0 $ 112.5  
Remaining Project Budget        
Proceeds from guarantee agreement       $ 1,100.0
Jointly Owned Nuclear Power Plant        
Project Budget        
Construction Costs       6,013.0
Financing Costs       1,735.0
Total Costs       7,748.0
Project-Level Contingency       78.0
Oglethorpe-Level Contingency       424.0
Total Contingency       502.0
Total Contingency       8,250.0
Actual Costs        
Construction Costs       5,145.0
Financing Costs       1,385.0
Total Costs       6,530.0
Project-Level Contingency       0.0
Oglethorpe-Level Contingency       0.0
Total Contingency       0.0
Totals       6,530.0
Remaining Project Budget        
Construction Costs       868.0
Financing Costs       350.0
Total Costs       1,218.0
Project-Level Contingency       78.0
Oglethorpe-Level Contingency       424.0
Total Contingency       502.0
Totals       $ 1,720.0