XML 87 R67.htm IDEA: XBRL DOCUMENT v3.20.4
Electric plant, construction and related agreements - Project Budget and Actual Costs (Details) - Vogtle Units No. 3 & No. 4 - USD ($)
$ in Millions
6 Months Ended 12 Months Ended
Jun. 30, 2020
Dec. 31, 2020
Project Budget    
Project-Level Contingency $ 75.0 $ 112.5
Remaining Project Budget    
Proceeds from guarantee agreement   1,100.0
Jointly Owned Nuclear Power Plant    
Project Budget    
Construction Costs   5,559.0
Financing Costs   1,578.0
Total Costs   7,137.0
Project-Level Contingency   113.0
Oglethorpe-Level Contingency   250.0
Total Contingency   363.0
Totals   7,500.0
Actual Costs    
Construction Costs   4,754.0
Financing Costs   1,259.0
Total Costs   6,013.0
Project-Level Contingency   0.0
Oglethorpe-Level Contingency   0.0
Total Contingency   0.0
Totals   6,013.0
Remaining Project Budget    
Construction Costs   805.0
Financing Costs   319.0
Total Costs   1,124.0
Project-Level Contingency   113.0
Oglethorpe-Level Contingency   250.0
Total Contingency   363.0
Totals   $ 1,487.0