Electric plant, construction and related agreements - Narrative (Details)
$ in Millions
1 Months Ended 6 Months Ended 12 Months Ended
Mar. 01, 2021
MW
Apr. 30, 2020
Aug. 31, 2018
USD ($)
Dec. 31, 2020
USD ($)
Jun. 30, 2020
USD ($)
Dec. 31, 2020
USD ($)
unit
MW
Vogtle Units No. 3 & No. 4            
Public Utility Property Plant and Equipment            
Ownership interest (as a percent)       30.00%   30.00%
Total investment in additional Vogtle units       $ 6,000.0   $ 6,000.0
Additional construction costs exceeds EAC     $ 800.0      
Estimated construction project-level contingency     $ 240.0      
Excess project contingency, total         $ 75.0  
Ownership amount of excess project contingency         23.0  
Additional construction contingency, total         250.0 375.0
Ownership amount of additional project level contingency         $ 75.0 112.5
Additional construction contingency, construction productivity and field support       10.0    
Ownership amount of additional construction contingency, construction productivity and field support       $ 3.0    
Workforce reduction, percent   20.00%        
Monthly delay cost           55.0
Vogtle Units No. 3 & No. 4 | Minimum            
Public Utility Property Plant and Equipment            
COVID related costs           325.0
Ownership amount of COVID related costs           98.0
Vogtle Units No. 3 & No. 4 | Maximum            
Public Utility Property Plant and Equipment            
COVID related costs           415.0
Ownership amount of COVID related costs           $ 125.0
Vogtle Units No. 3 & No. 4 | Ownership participation agreement            
Public Utility Property Plant and Equipment            
Number of additional nuclear units | unit           2
Ownership interest (as a percent)       30.00%   30.00%
Project budget           $ 7,500.0
Vogtle Units No. 3 & No. 4 | EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.            
Public Utility Property Plant and Equipment            
Number of nuclear units | unit           2
Generating capacity of each nuclear unit (in megawatts) | MW           1,100
Vogtle Units No. 3 & No. 4 | Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.            
Public Utility Property Plant and Equipment            
Written notice period for termination of agreement           30 days
Vogtle Unit Number 3            
Public Utility Property Plant and Equipment            
Delay period           4 months
Vogtle Unit Number 4            
Public Utility Property Plant and Equipment            
Delay period           3 months
Monthly delay cost           $ 25.0
Natural Gas Processing Plant | Subsequent Event            
Public Utility Property Plant and Equipment            
Generating capacity of each nuclear unit (in megawatts) | MW 511