Vogtle Units No. 3 and No. 4 Construction Project - Narrative (Details) - Vogtle Units No. 3 & No. 4
$ in Millions
1 Months Ended 3 Months Ended 6 Months Ended 9 Months Ended 12 Months Ended
Apr. 30, 2020
Aug. 31, 2018
USD ($)
Sep. 30, 2020
USD ($)
Jun. 30, 2020
USD ($)
Sep. 30, 2020
USD ($)
unit
Dec. 31, 2008
unit
MW
Public Utility Property Plant and Equipment            
Ownership interest (as a percent)     30.00%   30.00%  
Total investment in additional Vogtle units     $ 5,700   $ 5,700  
Construction contingency estimate   $ 800        
Estimated project-level construction contingency   $ 240        
Excess project contingency, total       $ 75    
Ownership amount of excess project contingency       23    
Additional construction contingency, total       250    
Ownership amount of additional project level contingency       $ 75    
Additional construction contingency, construction productivity and field support     10      
Ownership amount of additional construction contingency, construction productivity and field support     $ 3      
Workforce reduction, percent 20.00%          
Minimum            
Public Utility Property Plant and Equipment            
COVID related costs         150  
Ownership amount of COVID related costs         45  
Maximum            
Public Utility Property Plant and Equipment            
COVID related costs         250  
Ownership amount of COVID related costs         $ 75  
Ownership participation agreement            
Public Utility Property Plant and Equipment            
Number of additional nuclear units | unit         2  
Ownership interest (as a percent)     30.00%   30.00%  
Project budget         $ 7,500  
Project extension term         1 year  
EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.            
Public Utility Property Plant and Equipment            
Number of nuclear units | unit           2
Generating capacity of each nuclear unit | MW           1,100
Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.            
Public Utility Property Plant and Equipment            
Written notice period for termination of agreement         30 days  
Global Amendments To Term Sheet            
Public Utility Property Plant and Equipment            
Percentage of costs disallowed for recovery     6.00%   6.00%  
Global Amendments To Term Sheet | Minimum            
Public Utility Property Plant and Equipment            
Percentage of ownership approval to change primary construction contractor     90.00%   90.00%