XML 31 R18.htm IDEA: XBRL DOCUMENT v3.20.2
Vogtle Units No. 3 and No. 4 Construction Project
9 Months Ended
Sep. 30, 2020
Vogtle Units No. 3 and No. 4 Construction Project  
Vogtle Units No. 3 and No. 4 Construction Project Vogtle Units No. 3 and No. 4 Construction Project.   We, Georgia Power, the Municipal Electric Authority of Georgia, and the City of Dalton, Georgia, acting by and through its Board of Water, Light and Sinking Fund Commissioners, doing business as Dalton Utilities (collectively, the Co-owners) are parties to an Ownership Participation Agreement that, along with other agreements, governs our participation in two additional nuclear units under construction at Plant Vogtle, Units No. 3 and No. 4. The Co-owners appointed Georgia Power to act as agent under this agreement. Our ownership interest and proportionate share of the cost to construct these units is 30%. Pursuant to this agreement, Georgia Power has designated Southern Nuclear Operating Company, Inc. as its agent for licensing, engineering, procurement, contract management, construction and pre-operation services.
In 2008, Georgia Power, acting for itself and as agent for the Co-owners, entered into an Engineering, Procurement and Construction Agreement (the EPC Agreement) with Westinghouse Electric Company LLC and Stone & Webster, Inc., which was subsequently acquired by Westinghouse and changed its name to WECTEC Global Project Services Inc. (collectively, Westinghouse). Pursuant to the EPC Agreement, Westinghouse agreed to design, engineer, procure, construct and test two 1,100 megawatt nuclear units using the Westinghouse AP1000 technology and related facilities at Plant Vogtle.
Until March 2017, construction on Units No. 3 and No. 4 continued under the substantially fixed price EPC Agreement. In March 2017, Westinghouse filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. Effective in July 2017, Georgia Power, acting for itself and as agent for the other Co-owners, and Westinghouse entered into a services agreement (the Services Agreement), pursuant to which Westinghouse is providing facility design and engineering services, procurement and technical support and staff augmentation on a time and materials cost basis. The Services Agreement provides that it will continue until the start-up and testing of Vogtle Units No. 3 and No. 4 is complete and electricity is generated and sold from both units. The Services Agreement is terminable by the Co-owners upon 30 days' written notice.
In October 2017, Georgia Power, acting for itself and as agent for the other Co-owners, entered into a construction completion agreement with Bechtel Power Corporation, pursuant to which Bechtel serves as the primary contractor for the remaining construction activities for Vogtle Units No. 3 and No. 4 (the Bechtel Agreement). The Bechtel Agreement is a cost reimbursable plus fee arrangement, whereby Bechtel is reimbursed for actual costs plus a base fee and an at-risk fee, which is subject to adjustment based on Bechtel's performance against cost and schedule targets. Each Co-owner is severally, and not jointly, liable for its proportionate share, based on its ownership interest, of all amounts owed to Bechtel under the Bechtel Agreement. The Co-owners may terminate the Bechtel Agreement at any time for their convenience, provided that the Co-owners will be required to pay amounts related to work performed prior to the termination (including the applicable portion of the base fee), certain termination-related costs and, at certain stages of the work, the applicable portion of the at-risk fee. Bechtel may terminate the Bechtel Agreement under certain circumstances, including certain Co-owner suspensions of work, certain breaches of the Bechtel Agreement by the Co-owners, Co-owner insolvency and certain other events.
Our current budget for our 30% ownership interest in Vogtle Units No. 3 and No. 4 is $7.5 billion, which includes capital costs, allowance for funds used during construction, our allocation of the project-level contingency and a separate Oglethorpe-level contingency and is based on the Georgia Public Service Commission approved in-service dates of November 2021 and November 2022, respectively. As of September 30, 2020, our total investment in the additional Vogtle units was approximately $5.7 billion. We and some of our members have implemented various rate management programs to lessen the impact on rates when Vogtle Units No. 3 and No. 4 reach commercial operation.
As part of its ongoing processes, Southern Nuclear continues to evaluate cost and schedule forecasts on a regular basis to incorporate current information available, particularly in the areas of engineering support, commodity installation, system turnovers and related test results, and workforce statistics.
The August 2018 project-level budget included an $800 million construction contingency estimate, of which our 30% interest was $240 million. As of June 30, 2020, assignments of contingency exceeded the 2018 construction contingency estimate by $75 million of which our 30% interest was $23 million. This contingency was used to address cost risks related to construction productivity, including the April 2020 reduction in workforce designed to mitigate the impacts of the COVID-19 pandemic described below; craft labor incentives; adding resources for supervision, field support, project management, initial test program, start-up, and operations and engineering support; subcontracts; and
procurement, among other factors. As a result of these factors, Georgia Power established additional construction contingency of $250 million (of which our 30% interest is $75 million), as of June 30, 2020 for further potential risks, including, among other factors, construction productivity and expected impacts of the COVID-19 pandemic; additional resources for supervision, field support, project management, initial test program, start-up, and operations and engineering support; subcontracts; and procurement. During the third quarter of 2020, approximately $10 million, of which our 30% interest is $3 million, of the construction contingency established in the second quarter of 2020 was assigned to the base capital cost forecast for cost risks primarily associated with construction productivity and field support. Georgia Power has stated its expectation to allocate the remainder of this project-level contingency by completion of the project.
The project-level contingency is separate and in addition to our Oglethorpe-level contingency. The Oglethorpe-level contingency, which we have carried at various levels since the beginning of the project, was designed to cover potential cost, schedule, and financing risks associated with our share of the project which may not be covered by project-level contingencies. As construction progresses, the Oglethorpe-level contingency may continue to fluctuate as it represents the difference between known project-level costs and contingencies and our total budget of $7.5 billion. At the end of the project, if there is remaining Oglethorpe-level contingency, we will adjust our project budget to remove this contingency and bill our members based on the actual project costs. The table below shows our project budget and actual costs through September 30, 2020 for our 30% interest in the project.
(in millions)
Project Budget           Actual Costs at September 30, 2020Remaining Project Budget
Construction Costs (1)
$5,501 $4,536 $965 
Financing Costs1,557 1,204 353 
   Total Costs$7,058 $5,740 $1,318 
Project-Level Contingency$72 $— $72 
Oglethorpe-Level Contingency370 — 370 
   Total Contingency$442 $— $442 
Totals$7,500 $5,740 $1,760 
(1) Construction costs are net of $1.1 billion received from Toshiba Corporation under a Guarantee Settlement Agreement.
In mid-March 2020, Southern Nuclear began implementing policies and procedures designed to mitigate the risk of transmission of COVID-19 at the construction site, including worker distancing measures, isolating individuals who have tested positive for COVID-19, are showing symptoms consistent with COVID-19, are being tested for COVID-19, or have been in close contact with such persons, requiring self-quarantine, and adopting additional precautionary measures.
In April 2020, Georgia Power, acting for itself and as agent for the other Co-owners, announced a reduction in workforce at Vogtle Units No. 3 and No. 4, which totaled approximately 20% of the then-existing site workforce. This reduction in workforce was a mitigation action intended to address ongoing challenges with labor productivity that were exacerbated by the impact of the COVID-19 pandemic on the Vogtle Units No. 3 and No. 4 workforce and construction site. The April 2020 workforce reduction was intended to provide operational efficiencies by increasing productivity of the remaining workforce and reducing workforce fatigue and absenteeism. Further, it was also intended to allow for increased social distancing by the workforce and facilitate compliance with the recommendations from the Centers for Disease Control and Prevention. The April 2020 workforce reduction did reduce absenteeism, providing an improvement in operational efficiency and allowing for increased social distancing. Following peaks in April and July and subsequent declines, the number of active cases of COVID-19 at the site continues to fluctuate and impact productivity levels and pace of activity completion. As a result of these factors, overall production improvements were not achieved at the levels anticipated, contributing to the allocation of, and increase in, construction contingency described above.
Southern Nuclear and Georgia Power are pursuing an aggressive site work plan as a strategy to achieve completion of the units by their regulatory-approved in-service dates. Georgia Power has stated that it expects to achieve the regulatory-approved in-service dates of November 2021 and November 2022, respectively.
Starting in February 2020, Southern Nuclear also began providing a schedule benchmark that forecasts production levels and adjusts project milestones to align with the regulatory-approved in-service dates. We believe the production
levels and timeframes consistent with the assumptions in this benchmark provide reasonable assurance that Units No. 3 and No. 4 will meet the regulatory-approved in-service dates of November 2021 and November 2022, respectively, within our current $7.5 billion budget.
As construction, including subcontract work, continues and testing and system turnover activities increase, risks remain that challenges with management of contractors and vendors; subcontractor performance; supervision of craft labor and related productivity, particularly in the installation of electrical, mechanical, and instrumentation and controls commodities, ability to attract and retain craft labor, and/or related cost escalation; procurement, fabrication, delivery, assembly, installation, system turnover, and the initial testing and start-up, including any required engineering changes or any remediation related thereto, of plant systems, structures or components (some of which are based on new technology that has only within the last few years began initial operation in the global nuclear industry at this scale), any of which may require additional labor and/or materials; or other issues could arise and further impact the projected schedule and estimated cost.
In addition, the continuing effects of the COVID-19 pandemic could further disrupt or delay construction, testing, supervisory, and support activities at Vogtle Units No. 3 and No. 4. The incremental cost associated with COVID-19 mitigation actions and impacts on construction productivity is currently estimated to be between $150 million and $250 million (of which our 30% interest is $45 million to $75 million) and is included in the project budget and assumes (i) absenteeism rates normalize and (ii) the intended productivity efficiencies and production targets are realized in the coming months. The ultimate impact of the COVID-19 pandemic on the construction schedule and budget for Vogtle Units No. 3 and No. 4 cannot be determined at this time.
There have been technical and procedural challenges to the construction and licensing of Vogtle Units No. 3 and No. 4 at the federal and state level and additional challenges may arise. Processes are in place that are designed to assure compliance with the requirements specified in the Westinghouse Design Control Document and the combined construction and operating licenses, including inspections by Southern Nuclear and the Nuclear Regulatory Commission that occur throughout construction. As a result of such compliance processes, certain license amendment requests have been filed and approved or are pending before the Nuclear Regulatory Commission. Various design and other licensing-based compliance matters, including the timely submittal by Southern Nuclear of inspections, tests, analyses, and acceptance documentation for each unit and the related reviews and approvals by the Nuclear Regulatory Commission necessary to support Nuclear Regulatory Commission authorization to load fuel, may arise, which may result in additional license amendments or require other resolution. On June 15, 2020, the Nuclear Regulatory Commission rejected Nuclear Watch South's April 20, 2020 petition requesting a hearing and challenging the closure of certain inspections, tests, analyses, and acceptance criteria. On August 10, 2020, the Atomic Safety Licensing Board rejected the Blue Ridge Environmental Defense League’s May 11, 2020 petition challenging a license amendment request. The staff of the Nuclear Regulatory Commission has issued the requested amendment to the combined construction and operating license for Vogtle Unit No. 3. The Blue Ridge Environmental Defense League appealed the Atomic Safety Licensing Board’s decision to the Nuclear Regulatory Commission. If any license amendment requests or other licensing-based compliance issues are not resolved in a timely manner, there may be further delays in the project schedule that could result in increased costs to the Co-owners.
The Co-owners' joint ownership agreements, as amended, provide that the holders of at least 90% of the ownership interests in Vogtle Units No. 3 and No. 4 must vote to continue construction, or can vote to suspend construction, if certain adverse events occur, including: (i) the bankruptcy of Toshiba Corporation; (ii) termination or rejection in bankruptcy of certain agreements, including the Services Agreement, the Bechtel Agreement or the agency agreement with Southern Nuclear; (iii) Georgia Power publicly announces its intention not to submit for rate recovery any portion of its investment in Vogtle Units No. 3 and No. 4 (or associated financing costs) or the Georgia Public Service Commission determines that any of Georgia Power's costs relating to the construction of Vogtle Units No. 3 and No. 4 will not be recovered in retail rates, excluding any additional amounts paid by Georgia Power on behalf of the other Co-owners pursuant to the Joint Ownership Agreement and the first 6% of costs during any six-month VCM reporting period that are disallowed by the Public Service Commission for recovery, or for which Georgia Power elects not to seek cost recovery, through retail rates or (iv) an incremental extension of one year or more over the most recently approved schedule (each, a Project Adverse Event).