Vogtle Units No. 3 and No. 4 Construction Project (Details) - Vogtle Units No. 3 & No. 4
9 Months Ended 12 Months Ended
Sep. 30, 2019
USD ($)
item
Dec. 31, 2008
item
MW
Apr. 30, 2019
USD ($)
Public Utility Property Plant and Equipment      
Project budget     $ 7,500,000,000
Current project level budget $ 800,000,000    
Percentage of interest in current project level budget 30.00%    
Interest in current project level budget (Value) $ 240,000,000    
Allocated project level contingency 67,000,000    
Allocated project level contingency from interest in project level budget 20,000,000    
Total investment in additional Vogtle units $ 4,621,837,000    
Ownership participation agreement      
Public Utility Property Plant and Equipment      
Number of additional nuclear units | item 2    
Ownership interest (as a percent) 30.00%    
Ownership participation agreement | Occurrence of certain adverse events      
Public Utility Property Plant and Equipment      
Percentage of costs disallowed for recovery 6.00%    
Project extension term 1 year    
Ownership participation agreement | Minimum | Occurrence of certain adverse events      
Public Utility Property Plant and Equipment      
Ownership interests voting required to continue construction (as a percent) 90.00%    
EPC Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.      
Public Utility Property Plant and Equipment      
Number of nuclear units | item   2  
Generating capacity of each nuclear unit | MW   1,100  
Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.      
Public Utility Property Plant and Equipment      
Written notice period for termination of agreement 30 days