Vogtle Units No. 3 and No. 4 Construction Project (Details)
1 Months Ended 6 Months Ended 12 Months Ended
Nov. 30, 2017
USD ($)
Jun. 30, 2018
USD ($)
item
Dec. 31, 2008
item
MW
Dec. 31, 2018
USD ($)
Sep. 28, 2017
USD ($)
Loan Guarantee Agreement          
Electric plant, construction and related agreements          
Aggregate Department of Energy-guaranteed borrowings   $ 1,764,658,000      
Term of credit facility (in years)   5 years      
Loan Guarantee Agreement | Maximum          
Electric plant, construction and related agreements          
Aggregate borrowings   $ 3,057,069,461      
Conditional commitment issued by guarantor under the Loan Guarantee Agreement         $ 1,619,679,706
Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.          
Electric plant, construction and related agreements          
Written notice period for termination of agreement   30 days      
Joint Ownership Agreements | Minimum          
Electric plant, construction and related agreements          
Ownership interests voting required to continue construction (as a percent) 90.00%        
Increase in project budget $ 1,000,000,000        
Project extension term 1 year        
Ownership approval to change primary construction contractor (as a percent) 90.00%        
Ownership approval required for material amendments (as a percent) 67.00%        
Vogtle Units Number 3 And Number 4          
Electric plant, construction and related agreements          
Number of petitions filed by parties | item   2      
Estimated additional costs of completion   $ 450,000,000      
Number of subcontractors | item   60      
Estimated increase in construction contingency   $ 240,000,000      
Estimated construction contingency   500,000,000      
Project budget   7,000,000,000      
Total investment in additional vogtle units   3,396,731,000      
Capital market debt issuances   1,387,000,000      
Vogtle Units Number 3 And Number 4 | Extension of the project schedule          
Electric plant, construction and related agreements          
Estimate of additional base capital monthly costs   30,000,000      
Estimate of additional allowance for funds used during construction monthly per unit costs   $ 12,500,000      
Vogtle Units Number 3 And Number 4 | Minimum | Forecast          
Electric plant, construction and related agreements          
Project budget estimated minimum       $ 7,250,000,000  
Vogtle Units Number 3 And Number 4 | Maximum | Forecast          
Electric plant, construction and related agreements          
Project budget estimated maximum       $ 7,500,000,000  
Vogtle Units Number 3 And Number 4 | Ownership participation agreement          
Electric plant, construction and related agreements          
Number of additional nuclear units | item   2      
Ownership interest (as a percent)   30.00%      
Vogtle Units Number 3 And Number 4 | Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc.          
Electric plant, construction and related agreements          
Number of nuclear units | item     2    
Generating capacity of each nuclear unit | MW     1,100    
Co-owners | Vogtle Units Number 3 And Number 4          
Electric plant, construction and related agreements          
Estimated additional costs of completion   $ 1,500,000,000      
Estimated construction project-level contingency   $ 800,000,000