Vogtle Units No. 3 and No. 4 Construction Project (Details) - Vogtle Units Number 3 And Number 4
1 Months Ended 3 Months Ended 12 Months Ended
Jan. 11, 2018
item
Nov. 30, 2017
USD ($)
Jul. 31, 2017
Mar. 31, 2018
USD ($)
item
Dec. 31, 2008
item
MW
Electric plant, construction and related agreements          
Total investment in additional vogtle units | $       $ 3,160,067,000  
Number of petitions filed by parties | item 2        
Ownership participation agreement          
Electric plant, construction and related agreements          
Number of additional nuclear units | item       2  
Ownership interest (as a percent)       30.00%  
Ownership participation agreement | Minimum | Occurrence of certain adverse events          
Electric plant, construction and related agreements          
Ownership interests voting required to continue construction (as a percent)   90.00%      
Increase in project budget | $   $ 1,000,000,000      
Project extension term   1 year      
Ownership approval to change primary construction contractor (as a percent)   90.00%      
Ownership approval required for material amendments (as a percent)   67.00%      
Engineering, Procurement and Construction Agreement (the EPC Agreement) | Westinghouse Electric Company LLC and Stone & Webster, Inc.          
Electric plant, construction and related agreements          
Number of nuclear units | item         2
Generating capacity of each nuclear unit | MW         1,100
Project budget | $       $ 7,000,000,000  
Amended and Restated Services Agreement | Westinghouse Electric Company LLC and Stone & Webster, Inc.          
Electric plant, construction and related agreements          
Written notice period for termination of agreement     30 days