Vogtle Units No. 3 and No. 4 Construction Project
3 Months Ended
Mar. 31, 2018
Vogtle Units No. 3 and No. 4 Construction Project  
Vogtle Units No. 3 and No. 4 Construction Project

 

(L)           Vogtle Units No. 3 and No. 4 Construction Project.    We, Georgia Power, the Municipal Electric Authority of Georgia, and the City of Dalton, Georgia, acting by and through its Board of Water, Light and Sinking Fund Commissioners, doing business as Dalton Utilities (collectively, the Co-owners) are parties to an Ownership Participation Agreement that, along with other agreements, governs our participation in two additional nuclear units at Plant Vogtle, Units No. 3 and No. 4. The Co-owners appointed Georgia Power to act as agent under this agreement. Our ownership interest and proportionate share of the cost to construct these units is 30%. Pursuant to this agreement, Georgia Power has designated Southern Nuclear Operating Company, Inc. as its agent for licensing, engineering, procurement, contract management, construction and pre-operation services.

In 2008, Georgia Power, acting for itself and as agent for the Co-owners, entered into an Engineering, Procurement and Construction Agreement (the EPC Agreement) with Westinghouse Electric Company LLC and Stone & Webster, Inc., which was subsequently acquired by Westinghouse and changed its name to WECTEC Global Project Services Inc. (collectively, Westinghouse). Pursuant to the EPC Agreement, Westinghouse agreed to design, engineer, procure, construct and test two 1,100 megawatt nuclear units using the Westinghouse AP1000 technology and related facilities at Plant Vogtle.

Until March 2017, construction on Units No. 3 and No. 4 continued under the substantially fixed-price EPC Agreement. In March 2017, Westinghouse filed for bankruptcy protection under Chapter 11 of the United States Bankruptcy Code. In connection with the bankruptcy filing, Georgia Power, acting for itself and as agent for the other Co-owners, entered into an Interim Assessment Agreement with Westinghouse and WECTEC Staffing Services LLC to provide for a continuation of work at Vogtle Units No. 3 and No. 4. The Interim Assessment Agreement expired in July 2017 upon the effective date of the Services Agreement.

Effective in July 2017, Georgia Power, acting for itself and as agent for the other Co-owners, and Westinghouse entered into a services agreement (the Services Agreement), pursuant to which Westinghouse is providing facility design and engineering services, procurement and technological support and staff augmentation on a time and materials cost basis. The Services Agreement will continue until the start-up and testing of Vogtle Units No. 3 and No. 4 is complete and electricity is generated and sold from both units. The Services Agreement is terminable by the Co-owners upon 30 days' written notice.

In October 2017, Georgia Power, acting for itself and as agent for the other Co-owners, entered into a construction completion agreement with Bechtel Power Corporation, whereby Bechtel will serve as the primary contractor for the remaining construction activities for Vogtle Units No. 3 and No. 4 (the Bechtel Agreement). The Bechtel Agreement is a cost reimbursable plus fee arrangement, whereby Bechtel is reimbursed for actual costs plus a base fee and an at-risk fee, which is subject to adjustment based on Bechtel's performance against cost and schedule targets. Each Co-owner is severally, and not jointly, liable for its proportionate share, based on its ownership interest, of all amounts owed to Bechtel under the Bechtel Agreement. The Co-owners may terminate the Bechtel Agreement at any time for their convenience, provided that the Co-owners will be required to pay amounts related to work performed prior to the termination (including the applicable portion of the base fee), certain termination-related costs and, at certain stages of the work, the applicable portion of the at-risk fee. Bechtel may terminate the Bechtel Agreement under certain circumstances, including, certain Co-owner suspensions of work, certain breaches of the Bechtel Agreement by the Co-owners, Co-owner insolvency and certain other events. Pursuant to the Loan Guarantee Agreement between us and the Department of Energy, we are required to obtain the Department of Energy's approval of the Bechtel Agreement prior to obtaining any further advances under the Loan Guarantee Agreement.

In November 2017, the Co-owners entered into an amendment to their joint ownership agreements for Vogtle Units No. 3 and No. 4 (as amended, the Joint Ownership Agreements) to provide for, among other conditions, additional Co-owner approval requirements. Pursuant to the Joint Ownership Agreements, the holders of at least 90% of the ownership interests in Vogtle Units No. 3 and No. 4 must vote to continue construction if certain adverse events occur, including: (i) the bankruptcy of Toshiba Corporation; (ii) termination or rejection in bankruptcy of certain agreements, including the Services Agreement or the Bechtel Agreement; (iii) the Georgia Public Service Commission or Georgia Power determines that any of Georgia Power's costs relating to the construction of Vogtle Units No. 3 and No. 4 will not be recovered in retail rates because such costs are deemed unreasonable or imprudent; or (iv) an increase in the construction budget contained in Georgia Power's seventeenth Vogtle construction monitoring (VCM) report of more than $1,000,000,000 or extension of the project schedule contained in the seventeenth VCM report of more than one year. In addition, pursuant to the Joint Ownership Agreements, the required approval of holders of ownership interests in Vogtle Units No. 3 and No. 4 is at least (i) 90% for a change of the primary construction contractor and (ii) 67% for material amendments to the Services Agreement or agreements with Southern Nuclear or the primary construction contractor, including the Bechtel Agreement.

On December 21, 2017, the Georgia Public Service Commission took a series of actions related to the construction of Vogtle Units No. 3 and No. 4 and issued its related order on January 11, 2018. Among other actions, the Public Service Commission (i) accepted Georgia Power's recommendation that construction of Vogtle Units No. 3 and No. 4 be completed, with Southern Nuclear Operating Company, Inc. serving as construction manager and Bechtel as primary contractor and (ii) approved the revised schedule placing Unit No. 3 in service in November 2021 and Unit No. 4 in service in November 2022. In its January 11, 2018 order, the Public Service Commission stated if certain conditions and assumptions upon which Georgia Power's seventeenth VCM report are based do not materialize, both Georgia Power and the Public Service Commission reserve the right to reconsider the decision to continue construction. Parties have filed two petitions with the Fulton County Superior Court appealing the Georgia Public Service Commission's January 11, 2018 order. Georgia Power has stated that it believes these appeals have no merit; however, an adverse outcome in either appeal could have a material impact on our financial condition and results of operations.

We expect Vogtle Units No. 3 and No. 4 to be placed in service by November 2021 and November 2022, respectively. Our project budget for the additional Vogtle units is $7.0 billion, which includes capital costs, allowance for funds used during construction and a contingency amount. As of March 31, 2018, our total investment in the additional Vogtle units was approximately $3,160,067,000.

Subsequent to Westinghouse's bankruptcy filing, a number of subcontractors to Westinghouse alleged non-payment by Westinghouse for amounts owed for work performed on Vogtle Units No. 3 and No. 4. Georgia Power, acting for itself and as agent for the Co-owners, has taken actions to remove liens on the site filed by these subcontractors through the posting of surety bonds. Related to such liens, certain subcontractors have filed, and additional subcontractors may file, actions against Westinghouse and the Co-owners to preserve their payment rights with respect to such claims. All amounts associated with the removal of subcontractor liens and payment of other Westinghouse pre-petition accounts payable have been paid or accrued as of March 31, 2018.

As construction continues, risks remain that construction-related challenges, including management of contractors, subcontractors, and vendors, labor productivity and availability, fabrication, delivery, assembly and installation of plant systems, structures and components, or other issues could further impact the projected schedule and cost. Aspects of the Westinghouse AP1000 design are based on new technologies, and commercial operation of this design has yet to be tested.

There have been technical and procedural challenges to the construction and licensing of Vogtle Units No. 3 and No. 4 at the federal and state level and additional challenges may arise. Processes are in place that are designed to assure compliance with the requirements specified in the Westinghouse Design Control Document and the combined construction and operating licenses, including inspections by Southern Nuclear and the Nuclear Regulatory Commission that occur throughout construction. As a result of such compliance processes, certain license amendment requests have been filed and approved or are pending before the Nuclear Regulatory Commission. Various design and other licensing-based compliance matters, including the timely resolution of inspections, tests, analyses, and acceptance criteria and the related approvals by the Nuclear Regulatory Commission, may arise, which may result in additional license amendments or require other resolution. If any license amendment requests or other licensing-based compliance issues are not resolved in a timely manner, there may be further delays in the project schedule that could result in increased costs to the Co-owners.

The ultimate outcome of these matters cannot be determined at this time.